PARSHWA ENCLAVE
by PARSHAWA PROPERTIES · Jaysingpur, Kolhapur
Possession date of PARSHWA ENCLAVE: 15 February 2024, moved from 31 December 2020 (38 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P53000025963. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (February 2024) has passed.
What do you want to know about PARSHWA ENCLAVE?
How the possession date of PARSHWA ENCLAVE has moved
31 December 2020
Completion date given when the project was registered
15 August 2023
Extended at the builder's request (MahaRERA application EXT53000011252)
Reason the builder gave MahaRERA: “AS PER UDCPR FSI TAKING REVISED SANCTION CAUSE REQUIRE EXTENSION”
15 February 2024
Revised completion date on MahaRERA
Source: PARSHWA ENCLAVE’s extension records on MahaRERA (P53000025963), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PARSHWA ENCLAVE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53000025963
- Status
- Lapsed (registration period ended)
- Builder
- PARSHAWA PROPERTIES
- Location
- Jaysingpur, Kolhapur · 416101
- Project type
- Others
- Registered on
- 2 Aug 2020
- Completion date at registration
- December 2020
- Latest completion date
- February 2024
- Delay so far
- 38 months
- Homes
- 18
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of PARSHWA ENCLAVE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PARSHWA ENCLAVE | 100% | 100% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARSHWA ENCLAVE every month.
PARSHWA ENCLAVE: buildings, flats and land, as filed on MahaRERA
- Buildings: PARSHWA ENCLAVE (6 floors)
- Land: 424 sq m (about 0.1 acres) · sanctioned built-up 1,295 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PARSHWA ENCLAVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PARSHWA ENCLAVE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PARSHWA ENCLAVE
What is the possession date of PARSHWA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PARSHWA ENCLAVE in Jaysingpur, Kolhapur is 15 February 2024 — 38 months later than 31 December 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for PARSHWA ENCLAVE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PARSHWA ENCLAVE's builder has filed on MahaRERA, the official one, is 15 February 2024, already 38 months later than the 31 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PARSHWA ENCLAVE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), PARSHWA ENCLAVE's builder applied to MahaRERA to extend the completion date once: to 15 August 2023, giving the reason "AS PER UDCPR FSI TAKING REVISED SANCTION CAUSE REQUIRE EXTENSION".
What is the RERA number of PARSHWA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PARSHWA ENCLAVE in Jaysingpur, Kolhapur is P53000025963.
Is PARSHWA ENCLAVE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PARSHWA ENCLAVE is registered as P53000025963 and its status is "Lapsed (registration period ended)".
What is the construction status of PARSHWA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), PARSHWA ENCLAVE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PARSHWA ENCLAVE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does PARSHWA ENCLAVE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is PARSHWA ENCLAVE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PARSHWA ENCLAVE is registered on MahaRERA as P53000025963, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 38 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PARSHWA ENCLAVE's possession date changes?
The latest dates are on PARSHWA ENCLAVE's MahaRERA page (P53000025963). GharKundli's Kundli Watch sends a free WhatsApp update on PARSHWA ENCLAVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PARSHWA ENCLAVE have?
According to GharKundli's check of MahaRERA records (updated November 2026), PARSHWA ENCLAVE has one building filed: PARSHWA ENCLAVE with 6 floors.
How big is the land of PARSHWA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), PARSHWA ENCLAVE stands on 424 sq m of land (about 0.1 acres), with 1,295 sq m of sanctioned built-up area.
Where can I read reviews of PARSHWA ENCLAVE?
Google Maps has reviews of PARSHWA ENCLAVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PARSHWA ENCLAVE?
PARSHWA ENCLAVE by PARSHAWA PROPERTIES is in Jaysingpur, Kolhapur (pincode 416101), Maharashtra, and is registered on MahaRERA as P53000025963, per GharKundli's check of MahaRERA records.
How many homes are in PARSHWA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), PARSHWA ENCLAVE has 18 homes in 1 tower registered on MahaRERA.
When was PARSHWA ENCLAVE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PARSHWA ENCLAVE was registered on MahaRERA on 2 August 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on PARSHWA ENCLAVE?
No court cases are listed for PARSHWA ENCLAVE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of PARSHWA ENCLAVE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PARSHAWA PROPERTIES.
Check it yourself on MahaRERA
- How to check the possession date of PARSHWA ENCLAVE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 416101
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.