HERITAGE GRANDEUR
by VARAD DEVELOPERS · Tarabai Park, KolhapurAlso near Nagala Park
Possession date of HERITAGE GRANDEUR: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P53000046120, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about HERITAGE GRANDEUR?
How the possession date of HERITAGE GRANDEUR has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: HERITAGE GRANDEUR’s extension records on MahaRERA (P53000046120), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HERITAGE GRANDEUR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53000046120
- Status
- Registered and active
- Builder
- VARAD DEVELOPERS
- Location
- Tarabai Park, Kolhapur · 416003
- Project type
- Others
- Registered on
- 20 Jun 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 125
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 13
Construction progress of HERITAGE GRANDEUR, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HERITAGE GRANDEUR | 100% | 40% | 20% | 5% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HERITAGE GRANDEUR every month.
HERITAGE GRANDEUR: buildings, flats and land, as filed on MahaRERA
- Buildings: HERITAGE GRANDEUR (16 floors)
- Land: 3,018 sq m (about 0.7 acres) · sanctioned built-up 8,013 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of HERITAGE GRANDEUR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HERITAGE GRANDEUR: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HERITAGE GRANDEUR
What is the possession date of HERITAGE GRANDEUR?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HERITAGE GRANDEUR in Tarabai Park, Kolhapur is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for HERITAGE GRANDEUR?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HERITAGE GRANDEUR's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of HERITAGE GRANDEUR?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of HERITAGE GRANDEUR in Tarabai Park, Kolhapur is P53000046120.
Is HERITAGE GRANDEUR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), HERITAGE GRANDEUR is registered as P53000046120 and its status is "Registered and active".
What is the construction status of HERITAGE GRANDEUR?
According to GharKundli's check of MahaRERA records (updated November 2026), HERITAGE GRANDEUR's status on MahaRERA is "Registered and active". As filed by the builder, slab work on HERITAGE GRANDEUR is 40% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.
Does HERITAGE GRANDEUR have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is HERITAGE GRANDEUR safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), HERITAGE GRANDEUR is registered on MahaRERA as P53000046120, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HERITAGE GRANDEUR's possession date changes?
The latest dates are on HERITAGE GRANDEUR's MahaRERA page (P53000046120). GharKundli's Kundli Watch sends a free WhatsApp update on HERITAGE GRANDEUR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HERITAGE GRANDEUR have?
According to GharKundli's check of MahaRERA records (updated November 2026), HERITAGE GRANDEUR has one building filed: HERITAGE GRANDEUR with 16 floors.
How big is the land of HERITAGE GRANDEUR?
According to GharKundli's check of MahaRERA records (updated November 2026), HERITAGE GRANDEUR stands on 3,018 sq m of land (about 0.7 acres), with 8,013 sq m of sanctioned built-up area.
Where can I read reviews of HERITAGE GRANDEUR?
Google Maps has reviews of HERITAGE GRANDEUR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HERITAGE GRANDEUR?
HERITAGE GRANDEUR by VARAD DEVELOPERS is in Tarabai Park, Kolhapur (pincode 416003), near Nagala Park, Maharashtra, and is registered on MahaRERA as P53000046120, per GharKundli's check of MahaRERA records.
How many homes are in HERITAGE GRANDEUR?
According to GharKundli's check of MahaRERA records (updated November 2026), HERITAGE GRANDEUR has 125 homes in 1 tower registered on MahaRERA.
When was HERITAGE GRANDEUR registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), HERITAGE GRANDEUR was registered on MahaRERA on 20 June 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on HERITAGE GRANDEUR?
No court cases are listed for HERITAGE GRANDEUR on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of HERITAGE GRANDEUR?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VARAD DEVELOPERS, which has 13 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of HERITAGE GRANDEUR
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Kolhapur →
Other projects in Tarabai Park
All 70 projects in Kolhapur (416003) →Other projects by VARAD DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.