Possession date of VATHARE ELITES: 25 January 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P53000053102, and currently active. Its completion date is now January 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about VATHARE ELITES?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VATHARE ELITES has moved

  1. 25 September 2027

    Completion date given when the project was registered

  2. 25 January 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VATHARE ELITES’s extension records on MahaRERA (P53000053102), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VATHARE ELITES

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53000053102
Status
Registered and active
Builder
JAHIR CHANDSAB SOUDAGAR
Location
Dkte Marathi Medium School Narayan Mala, Kolhapur · 416115
Project type
Residential / Group Housing
Registered on
16 Oct 2023
Completion date at registration
September 2027
Latest completion date
January 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
60
Sold or booked
52%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of VATHARE ELITES, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VATHARE ELITES100%100%95%80%

Commencement certificate (CC), as filed on MahaRERA

  • VATHARE ELITES: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VATHARE ELITES every month.

VATHARE ELITES: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Jahir Chandsab Soudagar has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 1 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of VATHARE ELITES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VATHARE ELITES: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VATHARE ELITES

What is the possession date of VATHARE ELITES?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VATHARE ELITES in Dkte Marathi Medium School Narayan Mala, Kolhapur is 25 January 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VATHARE ELITES?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VATHARE ELITES's builder has filed on MahaRERA, the official one, is 25 January 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of VATHARE ELITES?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VATHARE ELITES in Dkte Marathi Medium School Narayan Mala, Kolhapur is P53000053102.

Is VATHARE ELITES registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VATHARE ELITES is registered as P53000053102 and its status is "Registered and active".

What is the construction status of VATHARE ELITES?

According to GharKundli's check of MahaRERA records (updated November 2026), VATHARE ELITES's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VATHARE ELITES is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does VATHARE ELITES have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is VATHARE ELITES safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), VATHARE ELITES is registered on MahaRERA as P53000053102, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VATHARE ELITES's possession date changes?

The latest dates are on VATHARE ELITES's MahaRERA page (P53000053102). GharKundli's Kundli Watch sends a free WhatsApp update on VATHARE ELITES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VATHARE ELITES have?

According to GharKundli's check of MahaRERA records (updated November 2026), VATHARE ELITES has one building filed: VATHARE ELITES with 5 floors and 60 units.

How big is the land of VATHARE ELITES?

According to GharKundli's check of MahaRERA records (updated November 2026), VATHARE ELITES stands on 1,248 sq m of land (about 0.3 acres), with 3,855 sq m of sanctioned built-up area.

What is the track record of VATHARE ELITES's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Jahir Chandsab Soudagar has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 1 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VATHARE ELITES?

Google Maps has reviews of VATHARE ELITES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VATHARE ELITES?

VATHARE ELITES by JAHIR CHANDSAB SOUDAGAR is in Dkte Marathi Medium School Narayan Mala, Kolhapur (pincode 416115), Maharashtra, and is registered on MahaRERA as P53000053102, per GharKundli's check of MahaRERA records.

How many homes are in VATHARE ELITES?

According to GharKundli's check of MahaRERA records (updated November 2026), VATHARE ELITES has 60 homes in 1 tower registered on MahaRERA, and 52% of them are sold or booked.

When was VATHARE ELITES registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VATHARE ELITES was registered on MahaRERA on 16 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on VATHARE ELITES?

No court cases are listed for VATHARE ELITES on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of VATHARE ELITES?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JAHIR CHANDSAB SOUDAGAR.

All projects with possession due in 2028 in Kolhapur →

Other projects in Hatkanangle

All 36 projects in Ichalkaranji (416115) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.