by ASHTIN INDIA PVT LTD · Jiwba Nana Jadhav Park, KolhapurAlso near Survey Nagar, Kalamba, Sane Guruji Vasahat

Possession date of DRONAGIRI: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P53000034477, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about DRONAGIRI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DRONAGIRI has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: DRONAGIRI’s extension records on MahaRERA (P53000034477), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DRONAGIRI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53000034477
Status
Registered and active
Builder
ASHTIN INDIA PVT LTD
Location
Jiwba Nana Jadhav Park, Kolhapur · 416012
Project type
Others
Registered on
11 Apr 2022
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
112
Sold or booked
89%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of DRONAGIRI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DRONAGIRI100%95%95%70%

Commencement certificate (CC), as filed on MahaRERA

  • DRONAGIRI: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DRONAGIRI every month.

DRONAGIRI: buildings, flats and land, as filed on MahaRERA

  • Buildings: DRONAGIRI (10 floors, 126 units)
  • Car parking: 85 covered, 19 open
  • Land: 2,000 sq m (about 0.5 acres) · recreational space 317 sq m
  • Boundaries filed include: 12 MTS ROAD, 6 MTS ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of DRONAGIRI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DRONAGIRI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DRONAGIRI

What is the possession date of DRONAGIRI?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DRONAGIRI in Jiwba Nana Jadhav Park, Kolhapur is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for DRONAGIRI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DRONAGIRI's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of DRONAGIRI?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DRONAGIRI in Jiwba Nana Jadhav Park, Kolhapur is P53000034477.

Is DRONAGIRI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DRONAGIRI is registered as P53000034477 and its status is "Registered and active".

What is the construction status of DRONAGIRI?

According to GharKundli's check of MahaRERA records (updated November 2026), DRONAGIRI's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DRONAGIRI is 95% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does DRONAGIRI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is DRONAGIRI safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), DRONAGIRI is registered on MahaRERA as P53000034477, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DRONAGIRI's possession date changes?

The latest dates are on DRONAGIRI's MahaRERA page (P53000034477). GharKundli's Kundli Watch sends a free WhatsApp update on DRONAGIRI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DRONAGIRI have?

According to GharKundli's check of MahaRERA records (updated November 2026), DRONAGIRI has one building filed: DRONAGIRI with 10 floors and 126 units.

How much parking does DRONAGIRI have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 85 covered and 19 open car parking spaces for DRONAGIRI.

How big is the land of DRONAGIRI?

According to GharKundli's check of MahaRERA records (updated November 2026), DRONAGIRI stands on 2,000 sq m of land (about 0.5 acres) and 317 sq m of recreational open space.

Where can I read reviews of DRONAGIRI?

Google Maps has reviews of DRONAGIRI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DRONAGIRI?

DRONAGIRI by ASHTIN INDIA PVT LTD is in Jiwba Nana Jadhav Park, Kolhapur (pincode 416012), near Survey Nagar, Kalamba, Sane Guruji Vasahat, Maharashtra, and is registered on MahaRERA as P53000034477, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 MTS ROAD, 6 MTS ROAD.

How many homes are in DRONAGIRI?

According to GharKundli's check of MahaRERA records (updated November 2026), DRONAGIRI has 112 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.

When was DRONAGIRI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), DRONAGIRI was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on DRONAGIRI?

No court cases are listed for DRONAGIRI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of DRONAGIRI?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ASHTIN INDIA PVT LTD, which has 1 other project registered on MahaRERA.