Vishwakarma prestige phase III
by VISHWAKARMA GRAHNIRMAN PVT LTD · Khanvilkar Petrol Pump, Kolhapur 416002
What’s in the report? →Possession date of Vishwakarma prestige phase III (MahaRERA P53000018413): 14 September 2024, and it has already passed. It has 142 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P53000018413. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P53000018413, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2024) has passed.
What do you want to know about Vishwakarma prestige phase III?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Vishwakarma prestige phase III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53000018413
- Status
- Lapsed (registration period ended)
- Builder
- VISHWAKARMA GRAHNIRMAN PVT LTD
- Location
- Khanvilkar Petrol Pump, Kolhapur · 416002
- Project type
- Others
- Registered on
- 30 Oct 2018
- Completion date at registration
- September 2024
- Latest completion date
- September 2024
- Homes
- 142
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Vishwakarma prestige phase III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VISHWAKARMA PRESTIGE PHASE III | 0% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vishwakarma prestige phase III every 1–2 months.
Vishwakarma prestige phase III: buildings, flats and land, as filed on MahaRERA
- Buildings: VISHWAKARMA PRESTIGE PHASE III (13 floors)
- Land: 4,094 sq m (about 1.0 acres) · sanctioned built-up 7,685 sq m
- Land, as filed: PLOT NO.2 RS NO.103 3 1,2,3
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Vishwakarma prestige phase III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vishwakarma prestige phase III: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vishwakarma prestige phase III
What is the possession date of Vishwakarma prestige phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vishwakarma prestige phase III in Khanvilkar Petrol Pump, Kolhapur is 14 September 2024. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Vishwakarma prestige phase III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vishwakarma prestige phase III's builder has filed on MahaRERA, the official one, is 14 September 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Vishwakarma prestige phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vishwakarma prestige phase III in Khanvilkar Petrol Pump, Kolhapur is P53000018413.
Is Vishwakarma prestige phase III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Vishwakarma prestige phase III is registered as P53000018413 and its status is "Lapsed (registration period ended)".
What is the current construction status of Vishwakarma prestige phase III? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Vishwakarma prestige phase III's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on VISHWAKARMA PRESTIGE PHASE III is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Vishwakarma prestige phase III have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Vishwakarma prestige phase III safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Vishwakarma prestige phase III is registered on MahaRERA as P53000018413, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vishwakarma prestige phase III?
Vishwakarma prestige phase III isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vishwakarma prestige phase III?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vishwakarma prestige phase III: gharkundli.com/tools/property-cost-calculator
Has Vishwakarma prestige phase III received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Vishwakarma prestige phase III isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 14 September 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Vishwakarma prestige phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), Vishwakarma prestige phase III's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (14 September 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Vishwakarma prestige phase III uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Vishwakarma prestige phase III was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vishwakarma prestige phase III's possession date changes?
The latest dates are on Vishwakarma prestige phase III's MahaRERA page (P53000018413). GharKundli's Kundli Watch sends a free WhatsApp update on Vishwakarma prestige phase III every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vishwakarma prestige phase III have?
According to GharKundli's check of MahaRERA records (updated November 2026), Vishwakarma prestige phase III has one building filed: VISHWAKARMA PRESTIGE PHASE III with 13 floors.
How big is the land of Vishwakarma prestige phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), Vishwakarma prestige phase III stands on 4,094 sq m of land (about 1.0 acres), with 7,685 sq m of sanctioned built-up area.
What are the reviews of Vishwakarma prestige phase III?
Google Maps has reviews of Vishwakarma prestige phase III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vishwakarma prestige phase III?
Vishwakarma prestige phase III by VISHWAKARMA GRAHNIRMAN PVT LTD is in Khanvilkar Petrol Pump, Kolhapur, pincode 416002, Maharashtra, and is registered on MahaRERA as P53000018413, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO.2 RS NO.103 3 1,2,3. GharKundli lists all 23 MahaRERA projects in Kolhapur (416002).
How many flats are in Vishwakarma prestige phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), Vishwakarma prestige phase III has 142 homes in 1 tower registered on MahaRERA.
When was Vishwakarma prestige phase III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Vishwakarma prestige phase III was registered on MahaRERA on 30 October 2018. GharKundli did not find a title report on the land on file there.
Does Vishwakarma prestige phase III have any legal issues or court cases?
No court cases are listed for Vishwakarma prestige phase III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Vishwakarma prestige phase III?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VISHWAKARMA GRAHNIRMAN PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of Vishwakarma prestige phase III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Karvir
- Punya Shlok-tower 3
- Krishnae Residency
- Time Square
- Yashshri - Grand Lake Vista
- Mangalam Imperia
- Acharya Shree Vidyasagar
- Sapphire Sky
- Vasant Villas Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.