Sanjay Balgounda Patil
by SANJAY BALGOUNDA PATIL · Pujari Mala, Kolhapur 416115
What’s in the report? →Possession date of Sanjay Balgounda Patil (MahaRERA P53000018735): 30 March 2022, moved from 31 March 2019 (36 months later), and it has already passed. It has 1 home. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P53000018735. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P53000018735, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (March 2022) has passed.
What do you want to know about Sanjay Balgounda Patil?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sanjay Balgounda Patil has moved
31 March 2019
Completion date given when the project was registered
31 March 2021
Extended at the builder's request (MahaRERA application EXT53000002481)
Reason the builder gave MahaRERA: “WE ARE WORKING THIS PROJECT AS PER CUSTOMER AVAILABLE. WE THINK THAT WE WILL GET CUSTOMER AS PER OUR SCHEDULE BUT DUE TO RECESSION IN MARKET THE CUSTOMER RESPONSE IS VERY POOR. SO WE REQUIRE SOME ADDITIONAL TIME TO COMPLETE THE PROJECT.”
30 March 2022
Revised completion date on MahaRERA
Source: Sanjay Balgounda Patil’s extension records on MahaRERA (P53000018735), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sanjay Balgounda Patil
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53000018735
- Status
- Lapsed (registration period ended)
- Builder
- SANJAY BALGOUNDA PATIL
- Location
- Pujari Mala, Kolhapur · 416115
- Project type
- Residential / Group Housing
- Registered on
- 29 Nov 2018
- Completion date at registration
- March 2019
- Latest completion date
- March 2022
- Delay so far
- 36 months
- Homes
- 1
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sanjay Balgounda Patil, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MALATIMADHAV PRESTIGE | 80% | 90% | 100% | 25% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sanjay Balgounda Patil every 1–2 months.
Sanjay Balgounda Patil: buildings, flats and land, as filed on MahaRERA
- Buildings: MALATIMADHAV PRESTIGE (24 floors)
- Land: 984 sq m (about 0.2 acres) · sanctioned built-up 1,181 sq m
- Land, as filed: 548/1 PLOT NO 2/3/4
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sanjay Balgounda Patil →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sanjay Balgounda Patil: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sanjay Balgounda Patil
What is the possession date of Sanjay Balgounda Patil?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sanjay Balgounda Patil in Pujari Mala, Kolhapur is 30 March 2022 — 36 months later than 31 March 2019, the date given at registration. That date has already passed.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sanjay Balgounda Patil?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sanjay Balgounda Patil's builder has filed on MahaRERA, the official one, is 30 March 2022, already 36 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sanjay Balgounda Patil extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil's builder applied to MahaRERA to extend the completion date once: to 31 March 2021, giving the reason "WE ARE WORKING THIS PROJECT AS PER CUSTOMER AVAILABLE. WE THINK THAT WE WILL GET CUSTOMER AS PER OUR SCHEDULE BUT DUE TO RECESSION IN MARKET THE CUSTOMER RESPONSE IS VERY POOR. SO WE REQUIRE SOME ADDITIONAL TIME TO COMPLETE THE PROJECT.".
What is the RERA number of Sanjay Balgounda Patil?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sanjay Balgounda Patil in Pujari Mala, Kolhapur is P53000018735.
Is Sanjay Balgounda Patil registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil is registered as P53000018735 and its status is "Lapsed (registration period ended)".
What is the current construction status of Sanjay Balgounda Patil? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MALATIMADHAV PRESTIGE is 90% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Sanjay Balgounda Patil have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Sanjay Balgounda Patil safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil is registered on MahaRERA as P53000018735, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sanjay Balgounda Patil?
Sanjay Balgounda Patil isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sanjay Balgounda Patil?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sanjay Balgounda Patil: gharkundli.com/tools/property-cost-calculator
Has Sanjay Balgounda Patil received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 March 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Sanjay Balgounda Patil?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 March 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Sanjay Balgounda Patil uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Sanjay Balgounda Patil was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sanjay Balgounda Patil's possession date changes?
The latest dates are on Sanjay Balgounda Patil's MahaRERA page (P53000018735). GharKundli's Kundli Watch sends a free WhatsApp update on Sanjay Balgounda Patil every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sanjay Balgounda Patil have?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil has one building filed: MALATIMADHAV PRESTIGE with 24 floors.
How big is the land of Sanjay Balgounda Patil?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil stands on 984 sq m of land (about 0.2 acres), with 1,181 sq m of sanctioned built-up area.
What are the reviews of Sanjay Balgounda Patil?
Google Maps has reviews of Sanjay Balgounda Patil written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sanjay Balgounda Patil?
Sanjay Balgounda Patil by SANJAY BALGOUNDA PATIL is in Pujari Mala, Kolhapur, pincode 416115, Maharashtra, and is registered on MahaRERA as P53000018735, per GharKundli's check of MahaRERA records. Its land is filed as 548/1 PLOT NO 2/3/4. GharKundli lists all 59 MahaRERA projects in Ichalkaranji (416115).
How many flats are in Sanjay Balgounda Patil?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil has 1 home in 1 tower registered on MahaRERA.
When was Sanjay Balgounda Patil registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanjay Balgounda Patil was registered on MahaRERA on 29 November 2018. GharKundli did not find a title report on the land on file there.
Does Sanjay Balgounda Patil have any legal issues or court cases?
No court cases are listed for Sanjay Balgounda Patil on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Sanjay Balgounda Patil?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SANJAY BALGOUNDA PATIL.
Check it yourself on MahaRERA
- How to check the possession date of Sanjay Balgounda Patil
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Hatkanangle
- Divine Enclave
- Nisargayan
- Digvijay Heights
- Kamal Kunj
- MG Market Block A
- Shri Ram Residency
- BRK Aura Residency
- Vihanga Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.