by SAI PARADISE DEVELOPERS · Saphale, Palghar

Registered on MahaRERA under P99000030007, and currently active. Its completion date has moved from May 2024 to April 2027, 35 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on PARADISE AVENUE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000030007
Status
Registered and active
Builder
SAI PARADISE DEVELOPERS
Location
Saphale, Palghar · 401102
Project type
Residential / Group Housing
Registered on
20 Jul 2021
Completion date at registration
May 2024
Latest completion date
April 2027
Delay so far
35 months
Homes
36
Sold or booked
44%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

PARADISE AVENUE: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about PARADISE AVENUE

Is PARADISE AVENUE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PARADISE AVENUE is registered as P99000030007 and its status is "Registered and active".

Where is PARADISE AVENUE?

PARADISE AVENUE by SAI PARADISE DEVELOPERS is in Saphale, Palghar (pincode 401102), Maharashtra, and is registered on MahaRERA as P99000030007, per GharKundli's check of MahaRERA records.

When is possession of PARADISE AVENUE due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PARADISE AVENUE in Saphale, Palghar is 30 April 2027 — 35 months later than 31 May 2024, the date given at registration.

Does PARADISE AVENUE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of PARADISE AVENUE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAI PARADISE DEVELOPERS.

Other projects in pincode 401102

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.