SILVER GREEN
by ACRES DEVELOPERS · Borivali Wast, Palghar
Possession date of SILVER GREEN: 31 December 2026, moved from 31 July 2022 (53 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000007490, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SILVER GREEN?
How the possession date of SILVER GREEN has moved
31 July 2022
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA25032620374)
Reason the builder gave MahaRERA:
“Respected Sir/Madam. We are writing to formally request an extension of the completion timeline for the above-mentioned project due to certain unavoidable circumstances that have impacted the project's progress. Despite our best efforts to…” Read the full reason
“Respected Sir/Madam. We are writing to formally request an extension of the completion timeline for the above-mentioned project due to certain unavoidable circumstances that have impacted the project's progress. Despite our best efforts to adhere to the initial schedule, the following challenges have caused delays: Phase-Wise Construction and Sequential Completion Strategy: As part of our phase-wise construction plan, priority was given to the completion of Building Nos. 2 and 3. for which we successfully obtained the Occupancy Certificate (O.C.). Construction of Building No. 1 (Wings A and…”
Source: SILVER GREEN’s extension records on MahaRERA (P99000007490), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SILVER GREEN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000007490
- Status
- Registered and active
- Builder
- ACRES DEVELOPERS
- Location
- Borivali Wast, Palghar · 401102
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- July 2022
- Latest completion date
- December 2026
- Delay so far
- 53 months
- Homes
- 107
- Sold or booked
- 86%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of SILVER GREEN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 1 | 100% | 100% | 75% | 0% |
| BUILDING NO 2 | 100% | 100% | 75% | 0% |
| BUILDING NO 3 | 100% | 100% | 75% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 1: covers GROUND + 3 HABITABLE FLOORS
- BUILDING NO 2: covers GROUND + 3 HABITABLE FLOORS
- BUILDING NO 3: covers GROUND + 3 HABITABLE FLOORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SILVER GREEN every month.
SILVER GREEN: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 1 (5 floors, 22 units) · BUILDING NO 2 (5 floors, 41 units) · BUILDING NO 3 (5 floors, 44 units)
- Land: 9,774 sq m (about 2.4 acres) · sanctioned built-up 6,744 sq m
- Boundaries filed include: INTERNAL LAYOUT ROAD
The builder’s record and reviews
Acres Developers (a group of 4 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 39 months late). No complaints on MahaRERA.
Read Google reviews of SILVER GREEN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SILVER GREEN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SILVER GREEN
What is the possession date of SILVER GREEN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SILVER GREEN in Borivali Wast, Palghar is 31 December 2026 — 53 months later than 31 July 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SILVER GREEN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SILVER GREEN's builder has filed on MahaRERA, the official one, is 31 December 2026, already 53 months later than the 31 July 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SILVER GREEN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SILVER GREEN's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Respected Sir/Madam. We are writing to formally request an extension of the completion timeline for the above-mentioned project due to certain unavoidable circumstances that have impacted the project's progress. Despite our best efforts to adhere to the initial schedule, the following challenges have caused delays: Phase-Wise Construction and Sequential Completion Strategy: As part of our phase-wise construction plan, priority was given to the completion of Building Nos. 2 and 3. for which we successfully obtained the Occupancy Certificate (O.C.). Construction of Building No. 1 (Wings A and…".
What is the RERA number of SILVER GREEN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SILVER GREEN in Borivali Wast, Palghar is P99000007490.
Is SILVER GREEN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SILVER GREEN is registered as P99000007490 and its status is "Registered and active".
What is the construction status of SILVER GREEN?
According to GharKundli's check of MahaRERA records (updated October 2026), SILVER GREEN's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SILVER GREEN have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SILVER GREEN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SILVER GREEN is registered on MahaRERA as P99000007490, its completion date has moved 53 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SILVER GREEN's possession date changes?
The latest dates are on SILVER GREEN's MahaRERA page (P99000007490). GharKundli's Kundli Watch sends a free WhatsApp update on SILVER GREEN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SILVER GREEN have?
According to GharKundli's check of MahaRERA records (updated October 2026), SILVER GREEN has 3 buildings filed: BUILDING NO 1 with 5 floors and 22 units; BUILDING NO 2 with 5 floors and 41 units; BUILDING NO 3 with 5 floors and 44 units.
How big is the land of SILVER GREEN?
According to GharKundli's check of MahaRERA records (updated October 2026), SILVER GREEN stands on 9,774 sq m of land (about 2.4 acres), with 6,744 sq m of sanctioned built-up area.
What is the track record of SILVER GREEN's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Acres Developers (a group of 4 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 39 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SILVER GREEN?
Google Maps has reviews of SILVER GREEN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SILVER GREEN?
SILVER GREEN by ACRES DEVELOPERS is in Borivali Wast, Palghar (pincode 401102), Maharashtra, and is registered on MahaRERA as P99000007490, per GharKundli's check of MahaRERA records. Its boundaries filed there include INTERNAL LAYOUT ROAD.
How many homes are in SILVER GREEN?
According to GharKundli's check of MahaRERA records (updated October 2026), SILVER GREEN has 107 homes in 3 towers registered on MahaRERA, and 86% of them are sold or booked.
When was SILVER GREEN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SILVER GREEN was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SILVER GREEN?
No court cases are listed for SILVER GREEN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SILVER GREEN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ACRES DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SILVER GREEN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Palghar →
Other projects in Palghar
- Sunshine Complex
- Elite Residency
- Rubicon Shinde Heritage
- V SQUARE ARCADE
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Other projects by ACRES DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.