Sunshine Complex
by Aditi Developers · Makane Village, Palghar
Possession date of Sunshine Complex: 30 June 2027, moved from 30 December 2023 (42 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000019854, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sunshine Complex?
How the possession date of Sunshine Complex has moved
30 December 2023
Completion date given when the project was registered
30 June 2024
Extended at the builder's request (MahaRERA application EXT99000018641)
Reason the builder gave MahaRERA: “Due to COVID-19 Restrictions, we were behind on time. But we trying our best to complete the project. Kindly consider our request of an extension of the Date of completion.”
30 June 2025
Extended at the builder's request (MahaRERA application EXT99000024788)
Reason the builder gave MahaRERA:
“we are requesting you to grant 12 Months extension for date of completion of the project, as there is time taking by Appropriate authority in issuing the final Occupation Certificate (OC) and also there are some inventories which are still…” Read the full reason
“we are requesting you to grant 12 Months extension for date of completion of the project, as there is time taking by Appropriate authority in issuing the final Occupation Certificate (OC) and also there are some inventories which are still unsold, so for the Registration of Unsold inventory we requesting to the MAHA Rera Authority to grant our RERA registration by one year i.e. 30/06/2025.”30 June 2026
Extended at the builder's request (MahaRERA application EA28062501831)
Reason the builder gave MahaRERA:
“Upon submission of our application for the Occupancy Certificate to the Office of the District Collector, Palghar, we were informed that a valid RERA Registration Certificate is a mandatory prerequisite. Specifically, the certificate must b…” Read the full reason
“Upon submission of our application for the Occupancy Certificate to the Office of the District Collector, Palghar, we were informed that a valid RERA Registration Certificate is a mandatory prerequisite. Specifically, the certificate must be valid and effective as of the date of the application for the Occupancy Certificate. At present, the validity of our existing RERA Registration Certificate has lapsed. Accordingly, we have initiated the process for obtaining an extension of the RERA Registration Certificate through MAHARERA. We are diligently complying with the procedural requirements a…”30 June 2027
Extended at the builder's request (MahaRERA application EA22072621826)
Reason the builder gave MahaRERA:
“Existing War Situation The Promoter respectfully submits that the delay in completion of the project within the originally declared completion timeline was caused due to circumstances beyond the control of the Promoter. During the execution…” Read the full reason
“Existing War Situation The Promoter respectfully submits that the delay in completion of the project within the originally declared completion timeline was caused due to circumstances beyond the control of the Promoter. During the execution of the project, the prevailing war-related situation and its consequential impact on the economy and supply chain adversely affected the construction industry. Owing to these unforeseen circumstances, there was a severe shortage of construction materials, disruptions in the procurement and transportation of essential building materials, and a significant…”
Source: Sunshine Complex’s extension records on MahaRERA (P99000019854), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sunshine Complex
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000019854
- Status
- Registered and active
- Builder
- Aditi Developers
- Location
- Makane Village, Palghar · 401102
- Project type
- Residential / Group Housing
- Registered on
- 5 Mar 2019
- Completion date at registration
- December 2023
- Latest completion date
- June 2027
- Delay so far
- 42 months
- Homes
- 48
- Sold or booked
- 58%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Sunshine Complex, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A2 - Swajit Apartment 4 | 100% | 100% | 100% | 100% |
| B - Sapna Apartment 5 | 100% | 100% | 100% | 100% |
| C - Laxmi Apartment 6 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- A2 - Swajit Apartment 4: covers 4 floors
- B - Sapna Apartment 5: covers 4 floors
- C - Laxmi Apartment 6: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sunshine Complex every month.
Sunshine Complex: buildings, flats and land, as filed on MahaRERA
- Buildings: A2 - Swajit Apartment 4 (6 floors, 14 units) · B - Sapna Apartment 5 (6 floors, 20 units) · C - Laxmi Apartment 6 (6 floors, 14 units)
- Car parking: 12 covered
- Land: 4,140 sq m (about 1.0 acres) · sanctioned built-up 1,755 sq m · recreational space 415 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sunshine Complex →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sunshine Complex: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sunshine Complex
What is the possession date of Sunshine Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sunshine Complex in Makane Village, Palghar is 30 June 2027 — 42 months later than 30 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Sunshine Complex?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sunshine Complex's builder has filed on MahaRERA, the official one, is 30 June 2027, already 42 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sunshine Complex extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunshine Complex's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2024, giving the reason "Due to COVID-19 Restrictions, we were behind on time. But we trying our best to complete the project. Kindly consider our request of an extension of the Date of completion."; to 30 June 2025, giving the reason "we are requesting you to grant 12 Months extension for date of completion of the project, as there is time taking by Appropriate authority in issuing the final Occupation Certificate (OC) and also there are some inventories which are still unsold, so for the Registration of Unsold inventory we requesting to the MAHA Rera Authority to grant our RERA registration by one year i.e. 30/06/2025."; to 30 June 2026, giving the reason "Upon submission of our application for the Occupancy Certificate to the Office of the District Collector, Palghar, we were informed that a valid RERA Registration Certificate is a mandatory prerequisite. Specifically, the certificate must be valid and effective as of the date of the application for the Occupancy Certificate. At present, the validity of our existing RERA Registration Certificate has lapsed. Accordingly, we have initiated the process for obtaining an extension of the RERA Registration Certificate through MAHARERA. We are diligently complying with the procedural requirements a…"; to 30 June 2027, giving the reason "Existing War Situation The Promoter respectfully submits that the delay in completion of the project within the originally declared completion timeline was caused due to circumstances beyond the control of the Promoter. During the execution of the project, the prevailing war-related situation and its consequential impact on the economy and supply chain adversely affected the construction industry. Owing to these unforeseen circumstances, there was a severe shortage of construction materials, disruptions in the procurement and transportation of essential building materials, and a significant…".
What is the RERA number of Sunshine Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sunshine Complex in Makane Village, Palghar is P99000019854.
Is Sunshine Complex registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunshine Complex is registered as P99000019854 and its status is "Registered and active".
What is the construction status of Sunshine Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunshine Complex's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Sunshine Complex have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sunshine Complex safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunshine Complex is registered on MahaRERA as P99000019854, its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sunshine Complex's possession date changes?
The latest dates are on Sunshine Complex's MahaRERA page (P99000019854). GharKundli's Kundli Watch sends a free WhatsApp update on Sunshine Complex every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sunshine Complex have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunshine Complex has 3 buildings filed: A2 - Swajit Apartment 4 with 6 floors and 14 units; B - Sapna Apartment 5 with 6 floors and 20 units; C - Laxmi Apartment 6 with 6 floors and 14 units.
How much parking does Sunshine Complex have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered car parking spaces for Sunshine Complex.
How big is the land of Sunshine Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunshine Complex stands on 4,140 sq m of land (about 1.0 acres), with 1,755 sq m of sanctioned built-up area and 415 sq m of recreational open space.
Where can I read reviews of Sunshine Complex?
Google Maps has reviews of Sunshine Complex written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sunshine Complex?
Sunshine Complex by Aditi Developers is in Makane Village, Palghar (pincode 401102), Maharashtra, and is registered on MahaRERA as P99000019854, per GharKundli's check of MahaRERA records.
How many homes are in Sunshine Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunshine Complex has 48 homes in 3 towers registered on MahaRERA, and 58% of them are sold or booked.
When was Sunshine Complex registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunshine Complex was registered on MahaRERA on 5 March 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Sunshine Complex?
No court cases are listed for Sunshine Complex on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sunshine Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aditi Developers, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sunshine Complex
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Palghar
- VASTU IMPRESSA B-WING
- Elite Residency
- V SQUARE ARCADE
- Rubicon Shinde Heritage
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Other projects by Aditi Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.