VASTU IMPRESSA B-WING

by Pradeep Prabhakar Patil · Makane Village, Palghar

Possession date of VASTU IMPRESSA B-WING: 30 October 2027, moved from 30 September 2024 (33 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000028045, and currently active. Its completion date has moved from September 2024 to October 2027: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VASTU IMPRESSA B-WING?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VASTU IMPRESSA B-WING has moved

  1. 30 September 2024

    Completion date given when the project was registered

  2. 29 September 2025

    Extended at the builder's request (MahaRERA application EXT99000024970)

    Reason the builder gave MahaRERA:
    “The primary reason for the delay has been a shortage of labor and contractor resources, which significantly impacted our overall progress and timeline. In addition, unforeseen supply chain disruptions have affected the availability of criti…” Read the full reason“The primary reason for the delay has been a shortage of labor and contractor resources, which significantly impacted our overall progress and timeline. In addition, unforeseen supply chain disruptions have affected the availability of critical materials, further complicating our efforts to stay on schedule. These challenges impacted our progress and timeline. We have secured additional labor and engaged reliable contractors, which will allow us to accelerate the remaining work.”
  3. 30 June 2027

    Extended at the builder's request (MahaRERA application EA31122519185)

    Reason the builder gave MahaRERA:
    “We respectfully request an extension for the project registration due to unavoidable financial constraints arising from the fact that major units of the project have been unsold till date. The absence of sales has resulted in insufficient c…” Read the full reason“We respectfully request an extension for the project registration due to unavoidable financial constraints arising from the fact that major units of the project have been unsold till date. The absence of sales has resulted in insufficient cash inflow, which has directly impacted the availability of working capital required for timely project construction. To ensure that the project is completed as per approved plans and quality standards, we require additional time to stabilize finances, secure alternative funding, and resume construction activities at full pace. We assure the Authority tha…”
  4. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VASTU IMPRESSA B-WING’s extension records on MahaRERA (P99000028045), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VASTU IMPRESSA B-WING

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000028045
Status
Registered and active
Builder
Pradeep Prabhakar Patil
Location
Makane Village, Palghar · 401102
Project type
Residential / Group Housing
Registered on
26 Jan 2021
Completion date at registration
September 2024
Latest completion date
October 2027
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
19
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of VASTU IMPRESSA B-WING, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Vastu Impressa B-Wing100%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • Vastu Impressa B-Wing: covers 5 (G+4)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VASTU IMPRESSA B-WING every month.

VASTU IMPRESSA B-WING: buildings, flats and land, as filed on MahaRERA

  • Buildings: Vastu Impressa B-Wing (5 floors, 19 units)
  • Land: 1,200 sq m (about 0.3 acres) · sanctioned built-up 642 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of VASTU IMPRESSA B-WING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VASTU IMPRESSA B-WING: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VASTU IMPRESSA B-WING

What is the possession date of VASTU IMPRESSA B-WING?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VASTU IMPRESSA B-WING in Makane Village, Palghar is 30 October 2027 — 33 months later than 30 September 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VASTU IMPRESSA B-WING?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VASTU IMPRESSA B-WING's builder has filed on MahaRERA, the official one, is 30 October 2027, already 33 months later than the 30 September 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VASTU IMPRESSA B-WING extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VASTU IMPRESSA B-WING's builder applied to MahaRERA to extend the completion date 2 times: to 29 September 2025, giving the reason "The primary reason for the delay has been a shortage of labor and contractor resources, which significantly impacted our overall progress and timeline. In addition, unforeseen supply chain disruptions have affected the availability of critical materials, further complicating our efforts to stay on schedule. These challenges impacted our progress and timeline. We have secured additional labor and engaged reliable contractors, which will allow us to accelerate the remaining work."; to 30 June 2027, giving the reason "We respectfully request an extension for the project registration due to unavoidable financial constraints arising from the fact that major units of the project have been unsold till date. The absence of sales has resulted in insufficient cash inflow, which has directly impacted the availability of working capital required for timely project construction. To ensure that the project is completed as per approved plans and quality standards, we require additional time to stabilize finances, secure alternative funding, and resume construction activities at full pace. We assure the Authority tha…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VASTU IMPRESSA B-WING?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VASTU IMPRESSA B-WING in Makane Village, Palghar is P99000028045.

Is VASTU IMPRESSA B-WING registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VASTU IMPRESSA B-WING is registered as P99000028045 and its status is "Registered and active".

What is the construction status of VASTU IMPRESSA B-WING?

According to GharKundli's check of MahaRERA records (updated October 2026), VASTU IMPRESSA B-WING's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vastu Impressa B-Wing is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does VASTU IMPRESSA B-WING have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is VASTU IMPRESSA B-WING safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VASTU IMPRESSA B-WING is registered on MahaRERA as P99000028045, its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VASTU IMPRESSA B-WING's possession date changes?

The latest dates are on VASTU IMPRESSA B-WING's MahaRERA page (P99000028045). GharKundli's Kundli Watch sends a free WhatsApp update on VASTU IMPRESSA B-WING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VASTU IMPRESSA B-WING have?

According to GharKundli's check of MahaRERA records (updated October 2026), VASTU IMPRESSA B-WING has one building filed: Vastu Impressa B-Wing with 5 floors and 19 units.

How big is the land of VASTU IMPRESSA B-WING?

According to GharKundli's check of MahaRERA records (updated October 2026), VASTU IMPRESSA B-WING stands on 1,200 sq m of land (about 0.3 acres), with 642 sq m of sanctioned built-up area.

Where can I read reviews of VASTU IMPRESSA B-WING?

Google Maps has reviews of VASTU IMPRESSA B-WING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VASTU IMPRESSA B-WING?

VASTU IMPRESSA B-WING by Pradeep Prabhakar Patil is in Makane Village, Palghar (pincode 401102), Maharashtra, and is registered on MahaRERA as P99000028045, per GharKundli's check of MahaRERA records.

How many homes are in VASTU IMPRESSA B-WING?

According to GharKundli's check of MahaRERA records (updated October 2026), VASTU IMPRESSA B-WING has 19 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was VASTU IMPRESSA B-WING registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VASTU IMPRESSA B-WING was registered on MahaRERA on 26 January 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on VASTU IMPRESSA B-WING?

No court cases are listed for VASTU IMPRESSA B-WING on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of VASTU IMPRESSA B-WING?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pradeep Prabhakar Patil.

All projects with possession due in 2027 in Palghar →

Other projects in Palghar

All 90 projects in Umbarpada (401102) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.