PARIVAR RESIDENCY

by PARIVAR DEVELOPERS · Saphale West, Palghar

Possession date of PARIVAR RESIDENCY: 30 October 2027, moved from 30 November 2023 (43 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000025455, and currently active. Its completion date has moved from November 2023 to October 2027: 43 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about PARIVAR RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PARIVAR RESIDENCY has moved

  1. 30 November 2023

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT99000017959)

    Reason the builder gave MahaRERA: “THE PROJECT IS BEING EXTENDED DUE TO COVID DUE TO WHICH THERE WAS A SLOW DOWN IN CONSTRUCTION SERVICE.”
  3. 30 June 2027

    Extended at the builder's request (MahaRERA application EA23062621489)

    Reason the builder gave MahaRERA: “FINISHING WORK REGARDING EXTERNAL SERVICES / SITE DEVELOPEMENT WORKS ARE PENDING AND DUE TO BE COMPLETED SOON. OCCUPANCY CERTIFICATE IS ALSO EXPECTED TO BE RECEIVED BY 30/06/2027.”
  4. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PARIVAR RESIDENCY’s extension records on MahaRERA (P99000025455), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PARIVAR RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000025455
Status
Registered and active
Builder
PARIVAR DEVELOPERS
Location
Saphale West, Palghar · 401102
Project type
Residential / Group Housing
Registered on
3 Jun 2020
Completion date at registration
November 2023
Latest completion date
October 2027
Delay so far
43 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
101
Sold or booked
66%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of PARIVAR RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%100%100%50%
WING B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • WING A: covers 7 floors
  • WING B: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARIVAR RESIDENCY every month.

PARIVAR RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A (7 floors, 67 units) · WING B (5 floors, 39 units)
  • Car parking: 39 open
  • Land: 2,860 sq m (about 0.7 acres) · sanctioned built-up 5,005 sq m · recreational space 277 sq m
  • Boundaries filed include: VILLAGE ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PARIVAR RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PARIVAR RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PARIVAR RESIDENCY

What is the possession date of PARIVAR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PARIVAR RESIDENCY in Saphale West, Palghar is 30 October 2027 — 43 months later than 30 November 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PARIVAR RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PARIVAR RESIDENCY's builder has filed on MahaRERA, the official one, is 30 October 2027, already 43 months later than the 30 November 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PARIVAR RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PARIVAR RESIDENCY's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "THE PROJECT IS BEING EXTENDED DUE TO COVID DUE TO WHICH THERE WAS A SLOW DOWN IN CONSTRUCTION SERVICE."; to 30 June 2027, giving the reason "FINISHING WORK REGARDING EXTERNAL SERVICES / SITE DEVELOPEMENT WORKS ARE PENDING AND DUE TO BE COMPLETED SOON. OCCUPANCY CERTIFICATE IS ALSO EXPECTED TO BE RECEIVED BY 30/06/2027.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of PARIVAR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PARIVAR RESIDENCY in Saphale West, Palghar is P99000025455.

Is PARIVAR RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PARIVAR RESIDENCY is registered as P99000025455 and its status is "Registered and active".

What is the construction status of PARIVAR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), PARIVAR RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does PARIVAR RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is PARIVAR RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PARIVAR RESIDENCY is registered on MahaRERA as P99000025455, its completion date has moved 43 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PARIVAR RESIDENCY's possession date changes?

The latest dates are on PARIVAR RESIDENCY's MahaRERA page (P99000025455). GharKundli's Kundli Watch sends a free WhatsApp update on PARIVAR RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PARIVAR RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), PARIVAR RESIDENCY has 2 buildings filed: WING A with 7 floors and 67 units; WING B with 5 floors and 39 units.

How much parking does PARIVAR RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 39 open car parking spaces for PARIVAR RESIDENCY.

How big is the land of PARIVAR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), PARIVAR RESIDENCY stands on 2,860 sq m of land (about 0.7 acres), with 5,005 sq m of sanctioned built-up area and 277 sq m of recreational open space.

Where can I read reviews of PARIVAR RESIDENCY?

Google Maps has reviews of PARIVAR RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PARIVAR RESIDENCY?

PARIVAR RESIDENCY by PARIVAR DEVELOPERS is in Saphale West, Palghar (pincode 401102), Maharashtra, and is registered on MahaRERA as P99000025455, per GharKundli's check of MahaRERA records. Its boundaries filed there include VILLAGE ROAD.

How many homes are in PARIVAR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), PARIVAR RESIDENCY has 101 homes in 2 towers registered on MahaRERA, and 66% of them are sold or booked.

When was PARIVAR RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PARIVAR RESIDENCY was registered on MahaRERA on 3 June 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on PARIVAR RESIDENCY?

No court cases are listed for PARIVAR RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of PARIVAR RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PARIVAR DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Palghar →

Other projects in Saphale West

All 94 projects in Umbarpada (401102) →

Other projects by PARIVAR DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.