OAKWOOD PHASE-1
by JEEVDANI BUILDERS & DEVELOPERS LLP · Nalasopara West, Palghar
Possession: OAKWOOD PHASE-1 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000029645. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about OAKWOOD PHASE-1?
How the possession date of OAKWOOD PHASE-1 has moved
31 May 2022
Completion date given when the project was registered
31 May 2023
Extended at the builder's request (MahaRERA application EXT99000012034)
Reason the builder gave MahaRERA: “The project is delayed due to worldwide Pandemic situation and unforeseen circumstances i.e. non-availability of labour, price increase of raw materials i.e steel ,cement, metals, etc. and lack of customer demand occurred.”
Source: OAKWOOD PHASE-1’s extension records on MahaRERA (P99000029645), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on OAKWOOD PHASE-1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- OAKWOOD PHASE-2P99000029584 · possession 31 Dec 2026
- MahaRERA registration
- P99000029645
- Status
- Completed
- Builder
- JEEVDANI BUILDERS & DEVELOPERS LLP
- Location
- Nalasopara West, Palghar · 401303
- Project type
- Commercial
- Registered on
- 14 Jun 2021
- Completion date at registration
- May 2022
- Latest completion date
- May 2023
- Delay so far
- 12 months
- Homes
- 0
- Sold or booked
- 89%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of OAKWOOD PHASE-1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OAKWOOD-PHASE-1 | 100% | 100% | 60% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- OAKWOOD-PHASE-1: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on OAKWOOD PHASE-1 every month.
OAKWOOD PHASE-1: buildings, flats and land, as filed on MahaRERA
- Buildings: OAKWOOD-PHASE-1 (3 floors, 19 units)
- Land: 3,693 sq m (about 0.9 acres) · sanctioned built-up 2,585 sq m
- Boundaries filed include: 12 Mtr Wide Layout Road
The builder’s record and reviews
Jeevdani Builders & Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 11 months late). No complaints on MahaRERA.
Read Google reviews of OAKWOOD PHASE-1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
OAKWOOD PHASE-1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about OAKWOOD PHASE-1
What is the possession date of OAKWOOD PHASE-1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for OAKWOOD PHASE-1 in Nalasopara West, Palghar is 31 May 2023 — 12 months later than 31 May 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for OAKWOOD PHASE-1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date OAKWOOD PHASE-1's builder has filed on MahaRERA, the official one, is 31 May 2023, already 12 months later than the 31 May 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of OAKWOOD PHASE-1 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), OAKWOOD PHASE-1's builder applied to MahaRERA to extend the completion date once: to 31 May 2023, giving the reason "The project is delayed due to worldwide Pandemic situation and unforeseen circumstances i.e. non-availability of labour, price increase of raw materials i.e steel ,cement, metals, etc. and lack of customer demand occurred.".
What is the RERA number of OAKWOOD PHASE-1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of OAKWOOD PHASE-1 in Nalasopara West, Palghar is P99000029645.
Is OAKWOOD PHASE-1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OAKWOOD PHASE-1 is registered as P99000029645 and its status is "Completed".
What is the construction status of OAKWOOD PHASE-1?
According to GharKundli's check of MahaRERA records (updated November 2026), OAKWOOD PHASE-1's status on MahaRERA is "Completed". As filed by the builder, slab work on OAKWOOD-PHASE-1 is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.
Does OAKWOOD PHASE-1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is OAKWOOD PHASE-1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), OAKWOOD PHASE-1 is registered on MahaRERA as P99000029645, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does OAKWOOD PHASE-1 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: OAKWOOD PHASE-2 (P99000029584, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.
How can I get updates if OAKWOOD PHASE-1's possession date changes?
The latest dates are on OAKWOOD PHASE-1's MahaRERA page (P99000029645). GharKundli's Kundli Watch sends a free WhatsApp update on OAKWOOD PHASE-1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does OAKWOOD PHASE-1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), OAKWOOD PHASE-1 has one building filed: OAKWOOD-PHASE-1 with 3 floors and 19 units.
How big is the land of OAKWOOD PHASE-1?
According to GharKundli's check of MahaRERA records (updated November 2026), OAKWOOD PHASE-1 stands on 3,693 sq m of land (about 0.9 acres), with 2,585 sq m of sanctioned built-up area.
What is the track record of OAKWOOD PHASE-1's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Jeevdani Builders & Developers (a group of 2 linked companies) has 3 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 11 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of OAKWOOD PHASE-1?
Google Maps has reviews of OAKWOOD PHASE-1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is OAKWOOD PHASE-1?
OAKWOOD PHASE-1 by JEEVDANI BUILDERS & DEVELOPERS LLP is in Nalasopara West, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000029645, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 Mtr Wide Layout Road.
How many homes are in OAKWOOD PHASE-1?
According to GharKundli's check of MahaRERA records (updated November 2026), OAKWOOD PHASE-1 has 0 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.
When was OAKWOOD PHASE-1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OAKWOOD PHASE-1 was registered on MahaRERA on 14 June 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on OAKWOOD PHASE-1?
No court cases are listed for OAKWOOD PHASE-1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of OAKWOOD PHASE-1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JEEVDANI BUILDERS & DEVELOPERS LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of OAKWOOD PHASE-1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data