Skip to content
GharKundli

VINAY UNIQUE RESIDENCY BLDG NO 7

by JASAMRIT ESTATES PRIVATE LIMITED (Mangalmurti) · Bolinj, Virar West, Palghar

Possession date of VINAY UNIQUE RESIDENCY BLDG NO 7: 5 January 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000031046, and currently active. Its completion date is now January 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about VINAY UNIQUE RESIDENCY BLDG NO 7?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VINAY UNIQUE RESIDENCY BLDG NO 7 has moved

  1. 5 September 2026

    Completion date given when the project was registered

  2. 5 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VINAY UNIQUE RESIDENCY BLDG NO 7’s extension records on MahaRERA (P99000031046), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VINAY UNIQUE RESIDENCY BLDG NO 7

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000031046
Status
Registered and active
Builder
JASAMRIT ESTATES PRIVATE LIMITED
Location
Bolinj, Virar West, Palghar · 401303
Project type
Residential / Group Housing
Registered on
5 Oct 2021
Completion date at registration
September 2026
Latest completion date
January 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
83
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of VINAY UNIQUE RESIDENCY BLDG NO 7, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VINAY UNIQUE RESIDENCY BLDG NO 7 B WING100%100%90%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VINAY UNIQUE RESIDENCY BLDG NO 7 every month.

VINAY UNIQUE RESIDENCY BLDG NO 7: buildings, flats and land, as filed on MahaRERA

  • Buildings: VINAY UNIQUE RESIDENCY BLDG NO 7 B WING (19 floors)
  • Land: 1,237 sq m (about 0.3 acres) · sanctioned built-up 3,439 sq m

The builder’s record and reviews

Jasamrit Estates (a group of 8 linked companies) has 13 projects on MahaRERA since 2021, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 10 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.

Read Google reviews of VINAY UNIQUE RESIDENCY BLDG NO 7 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VINAY UNIQUE RESIDENCY BLDG NO 7: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VINAY UNIQUE RESIDENCY BLDG NO 7

What is the possession date of VINAY UNIQUE RESIDENCY BLDG NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VINAY UNIQUE RESIDENCY BLDG NO 7 in Bolinj, Virar West, Palghar is 5 January 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VINAY UNIQUE RESIDENCY BLDG NO 7?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VINAY UNIQUE RESIDENCY BLDG NO 7's builder has filed on MahaRERA, the official one, is 5 January 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of VINAY UNIQUE RESIDENCY BLDG NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VINAY UNIQUE RESIDENCY BLDG NO 7 in Bolinj, Virar West, Palghar is P99000031046.

Is VINAY UNIQUE RESIDENCY BLDG NO 7 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VINAY UNIQUE RESIDENCY BLDG NO 7 is registered as P99000031046 and its status is "Registered and active".

What is the construction status of VINAY UNIQUE RESIDENCY BLDG NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), VINAY UNIQUE RESIDENCY BLDG NO 7's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VINAY UNIQUE RESIDENCY BLDG NO 7 B WING is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does VINAY UNIQUE RESIDENCY BLDG NO 7 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is VINAY UNIQUE RESIDENCY BLDG NO 7 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), VINAY UNIQUE RESIDENCY BLDG NO 7 is registered on MahaRERA as P99000031046, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VINAY UNIQUE RESIDENCY BLDG NO 7's possession date changes?

The latest dates are on VINAY UNIQUE RESIDENCY BLDG NO 7's MahaRERA page (P99000031046). GharKundli's Kundli Watch sends a free WhatsApp update on VINAY UNIQUE RESIDENCY BLDG NO 7 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VINAY UNIQUE RESIDENCY BLDG NO 7 have?

According to GharKundli's check of MahaRERA records (updated November 2026), VINAY UNIQUE RESIDENCY BLDG NO 7 has one building filed: VINAY UNIQUE RESIDENCY BLDG NO 7 B WING with 19 floors.

How big is the land of VINAY UNIQUE RESIDENCY BLDG NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), VINAY UNIQUE RESIDENCY BLDG NO 7 stands on 1,237 sq m of land (about 0.3 acres), with 3,439 sq m of sanctioned built-up area.

What is the track record of VINAY UNIQUE RESIDENCY BLDG NO 7's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Jasamrit Estates (a group of 8 linked companies) has 13 projects on MahaRERA since 2021, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 10 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VINAY UNIQUE RESIDENCY BLDG NO 7?

Google Maps has reviews of VINAY UNIQUE RESIDENCY BLDG NO 7 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VINAY UNIQUE RESIDENCY BLDG NO 7?

VINAY UNIQUE RESIDENCY BLDG NO 7 by JASAMRIT ESTATES PRIVATE LIMITED (Mangalmurti) is in Bolinj, Virar West, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000031046, per GharKundli's check of MahaRERA records.

How many homes are in VINAY UNIQUE RESIDENCY BLDG NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), VINAY UNIQUE RESIDENCY BLDG NO 7 has 83 homes in 1 tower registered on MahaRERA.

When was VINAY UNIQUE RESIDENCY BLDG NO 7 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VINAY UNIQUE RESIDENCY BLDG NO 7 was registered on MahaRERA on 5 October 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on VINAY UNIQUE RESIDENCY BLDG NO 7?

No court cases are listed for VINAY UNIQUE RESIDENCY BLDG NO 7 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of VINAY UNIQUE RESIDENCY BLDG NO 7?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JASAMRIT ESTATES PRIVATE LIMITED, the company Mangalmurti files this project under, which has 3 other projects registered on MahaRERA.

Other projects in pincode 401303

Other projects by JASAMRIT ESTATES PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.