BLDG NO 1

by M/s AMEYA BUILDERS & PROPERTY DEVELOPERS · Mayekar Wadi, Palghar

Possession date of BLDG NO 1: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000046786, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about BLDG NO 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BLDG NO 1 has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: BLDG NO 1’s extension records on MahaRERA (P99000046786), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BLDG NO 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000046786
Status
Registered and active
Builder
M/s AMEYA BUILDERS & PROPERTY DEVELOPERS
Location
Mayekar Wadi, Palghar · 401303
Project type
Others
Registered on
10 Sep 2022
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
90
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of BLDG NO 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
10%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • 1: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BLDG NO 1 every month.

BLDG NO 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: 1 (16 floors, 110 units)
  • Land: 3,050 sq m (about 0.8 acres) · sanctioned built-up 10,332 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of BLDG NO 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BLDG NO 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BLDG NO 1

What is the possession date of BLDG NO 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BLDG NO 1 in Mayekar Wadi, Palghar is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for BLDG NO 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BLDG NO 1's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of BLDG NO 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BLDG NO 1 in Mayekar Wadi, Palghar is P99000046786.

Is BLDG NO 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BLDG NO 1 is registered as P99000046786 and its status is "Registered and active".

What is the construction status of BLDG NO 1?

According to GharKundli's check of MahaRERA records (updated November 2026), BLDG NO 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 1 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does BLDG NO 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is BLDG NO 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BLDG NO 1 is registered on MahaRERA as P99000046786, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BLDG NO 1's possession date changes?

The latest dates are on BLDG NO 1's MahaRERA page (P99000046786). GharKundli's Kundli Watch sends a free WhatsApp update on BLDG NO 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BLDG NO 1 have?

According to GharKundli's check of MahaRERA records (updated November 2026), BLDG NO 1 has one building filed: 1 with 16 floors and 110 units.

How big is the land of BLDG NO 1?

According to GharKundli's check of MahaRERA records (updated November 2026), BLDG NO 1 stands on 3,050 sq m of land (about 0.8 acres), with 10,332 sq m of sanctioned built-up area.

Where can I read reviews of BLDG NO 1?

Google Maps has reviews of BLDG NO 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BLDG NO 1?

BLDG NO 1 by M/s AMEYA BUILDERS & PROPERTY DEVELOPERS is in Mayekar Wadi, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000046786, per GharKundli's check of MahaRERA records.

How many homes are in BLDG NO 1?

According to GharKundli's check of MahaRERA records (updated November 2026), BLDG NO 1 has 90 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was BLDG NO 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BLDG NO 1 was registered on MahaRERA on 10 September 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on BLDG NO 1?

No court cases are listed for BLDG NO 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of BLDG NO 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/s AMEYA BUILDERS & PROPERTY DEVELOPERS, which has 4 other projects registered on MahaRERA.

Other projects in Vasai

Other projects by M/s AMEYA BUILDERS & PROPERTY DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.