Skip to content
GharKundli

VASUDHA VIHAR

by RAJENDRA VASANTRAO KHANKARI · Ashok Nagar, Dhule

Possession: VASUDHA VIHAR is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P49800013520. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about VASUDHA VIHAR?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VASUDHA VIHAR has moved

  1. 15 January 2021

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT49800016541)

    Reason the builder gave MahaRERA: “COMPLETION CERTIFICATE RECEIVED LATE”

Source: VASUDHA VIHAR’s extension records on MahaRERA (P49800013520), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VASUDHA VIHAR

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P49800013520
Status
Completed
Builder
RAJENDRA VASANTRAO KHANKARI
Location
Ashok Nagar, Dhule · 424001
Project type
Residential / Group Housing
Registered on
9 Oct 2017
Completion date at registration
January 2021
Latest completion date
June 2023
Delay so far
29 months
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of VASUDHA VIHAR, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VASUDHA VIHAR100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VASUDHA VIHAR every month.

VASUDHA VIHAR: buildings, flats and land, as filed on MahaRERA

  • Buildings: VASUDHA VIHAR (5 floors)
  • Land: 474 sq m (about 0.1 acres) · sanctioned built-up 661 sq m
  • Boundaries filed include: COLONY ROAD

The builder’s record and reviews

Rajendra Vasantrao Khankari has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 20 months); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of VASUDHA VIHAR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VASUDHA VIHAR: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VASUDHA VIHAR

What is the possession date of VASUDHA VIHAR?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VASUDHA VIHAR in Ashok Nagar, Dhule is 30 June 2023 — 29 months later than 15 January 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for VASUDHA VIHAR?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VASUDHA VIHAR's builder has filed on MahaRERA, the official one, is 30 June 2023, already 29 months later than the 15 January 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VASUDHA VIHAR extended?

According to GharKundli's check of MahaRERA records (updated November 2026), VASUDHA VIHAR's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "COMPLETION CERTIFICATE RECEIVED LATE".

What is the RERA number of VASUDHA VIHAR?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VASUDHA VIHAR in Ashok Nagar, Dhule is P49800013520.

Is VASUDHA VIHAR registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VASUDHA VIHAR is registered as P49800013520 and its status is "Completed".

What is the construction status of VASUDHA VIHAR?

According to GharKundli's check of MahaRERA records (updated November 2026), VASUDHA VIHAR's status on MahaRERA is "Completed". As filed by the builder, slab work on VASUDHA VIHAR is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does VASUDHA VIHAR have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is VASUDHA VIHAR safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), VASUDHA VIHAR is registered on MahaRERA as P49800013520, its MahaRERA status is "Completed", its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VASUDHA VIHAR's possession date changes?

The latest dates are on VASUDHA VIHAR's MahaRERA page (P49800013520). GharKundli's Kundli Watch sends a free WhatsApp update on VASUDHA VIHAR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VASUDHA VIHAR have?

According to GharKundli's check of MahaRERA records (updated November 2026), VASUDHA VIHAR has one building filed: VASUDHA VIHAR with 5 floors.

How big is the land of VASUDHA VIHAR?

According to GharKundli's check of MahaRERA records (updated November 2026), VASUDHA VIHAR stands on 474 sq m of land (about 0.1 acres), with 661 sq m of sanctioned built-up area.

What is the track record of VASUDHA VIHAR's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Rajendra Vasantrao Khankari has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 20 months); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VASUDHA VIHAR?

Google Maps has reviews of VASUDHA VIHAR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VASUDHA VIHAR?

VASUDHA VIHAR by RAJENDRA VASANTRAO KHANKARI is in Ashok Nagar, Dhule (pincode 424001), Maharashtra, and is registered on MahaRERA as P49800013520, per GharKundli's check of MahaRERA records. Its boundaries filed there include COLONY ROAD.

How many homes are in VASUDHA VIHAR?

According to GharKundli's check of MahaRERA records (updated November 2026), VASUDHA VIHAR has 16 homes in 1 tower registered on MahaRERA.

When was VASUDHA VIHAR registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VASUDHA VIHAR was registered on MahaRERA on 9 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on VASUDHA VIHAR?

No court cases are listed for VASUDHA VIHAR on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of VASUDHA VIHAR?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAJENDRA VASANTRAO KHANKARI, which has 2 other projects registered on MahaRERA.

Other projects in Dhule

All 10 projects in Dhule (424001) →

Other projects by RAJENDRA VASANTRAO KHANKARI

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.