Mangalmurti Residency

by SUMIT SANJAY KORAKE · Dhule 424001

What’s in the report? →

Possession date of Mangalmurti Residency (MahaRERA P49800022364): 5 April 2021, moved from 1 October 2020 (6 months later), and it has already passed. It has 14 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P49800022364. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P49800022364, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (April 2021) has passed.

What do you want to know about Mangalmurti Residency?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Mangalmurti Residency has moved

  1. 1 October 2020

    Completion date given when the project was registered

  2. 5 April 2021

    Extended at the builder's request (MahaRERA application EXT49800008389)

    Reason the builder gave MahaRERA:
    “The extended time is required on account of disruptions caused due to COVID-19 pandemic. This is my first project, and while I have tried my best to complete it on time, certain personal issues and the COVID pandemic together caused the del…” Read the full reason“The extended time is required on account of disruptions caused due to COVID-19 pandemic. This is my first project, and while I have tried my best to complete it on time, certain personal issues and the COVID pandemic together caused the delay. There was acute labour shortage and non-availability of material required for completion. I have already completed most of the work of the building and now it is at the finishing stage. The photographs of the building are attached for ready perusal. I, most humbly, pray to kindly extend the date of completion as aforesaid in such pressing times. I ass…”

Source: Mangalmurti Residency’s extension records on MahaRERA (P49800022364), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mangalmurti Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P49800022364
Status
Lapsed (registration period ended)
Builder
SUMIT SANJAY KORAKE
Location
Dhule · 424001
Project type
Residential / Group Housing
Registered on
16 Sep 2019
Completion date at registration
October 2020
Latest completion date
April 2021
Delay so far
6 months
Homes
14
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Mangalmurti Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MANGALMURTI RESIDENCY20%15%5%10%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mangalmurti Residency every 1–2 months.

Mangalmurti Residency: buildings, flats and land, as filed on MahaRERA

  • Buildings: MANGALMURTI RESIDENCY (8 floors)
  • Land: 457 sq m (about 0.1 acres) · sanctioned built-up 639 sq m
  • Land, as filed: CTS NO 8260, SURVEY NO 483/2, PLOT NO 34
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Mangalmurti Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mangalmurti Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mangalmurti Residency

What is the possession date of Mangalmurti Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mangalmurti Residency in Dhule is 5 April 2021 — 6 months later than 1 October 2020, the date given at registration. That date has already passed.

The date has already moved 6 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Mangalmurti Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mangalmurti Residency's builder has filed on MahaRERA, the official one, is 5 April 2021, already 6 months later than the 1 October 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mangalmurti Residency extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency's builder applied to MahaRERA to extend the completion date once: to 5 April 2021, giving the reason "The extended time is required on account of disruptions caused due to COVID-19 pandemic. This is my first project, and while I have tried my best to complete it on time, certain personal issues and the COVID pandemic together caused the delay. There was acute labour shortage and non-availability of material required for completion. I have already completed most of the work of the building and now it is at the finishing stage. The photographs of the building are attached for ready perusal. I, most humbly, pray to kindly extend the date of completion as aforesaid in such pressing times. I ass…".

What is the RERA number of Mangalmurti Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mangalmurti Residency in Dhule is P49800022364.

Is Mangalmurti Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency is registered as P49800022364 and its status is "Lapsed (registration period ended)".

What is the current construction status of Mangalmurti Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MANGALMURTI RESIDENCY is 15% done and internal work 5%. GharKundli's full report compares construction progress with the deadline.

Does Mangalmurti Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Mangalmurti Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency is registered on MahaRERA as P49800022364, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mangalmurti Residency?

Mangalmurti Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Mangalmurti Residency?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Mangalmurti Residency: gharkundli.com/tools/property-cost-calculator

Has Mangalmurti Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 5 April 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Mangalmurti Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (5 April 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Mangalmurti Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Mangalmurti Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mangalmurti Residency's possession date changes?

The latest dates are on Mangalmurti Residency's MahaRERA page (P49800022364). GharKundli's Kundli Watch sends a free WhatsApp update on Mangalmurti Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mangalmurti Residency have?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency has one building filed: MANGALMURTI RESIDENCY with 8 floors.

How big is the land of Mangalmurti Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency stands on 457 sq m of land (about 0.1 acres), with 639 sq m of sanctioned built-up area.

What are the reviews of Mangalmurti Residency?

Google Maps has reviews of Mangalmurti Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mangalmurti Residency?

Mangalmurti Residency by SUMIT SANJAY KORAKE is in Dhule, pincode 424001, Maharashtra, and is registered on MahaRERA as P49800022364, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 8260, SURVEY NO 483/2, PLOT NO 34. GharKundli lists all 22 MahaRERA projects in Dhule (424001).

How many flats are in Mangalmurti Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency has 14 homes in 1 tower registered on MahaRERA.

When was Mangalmurti Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mangalmurti Residency was registered on MahaRERA on 16 September 2019. GharKundli did not find a title report on the land on file there.

Does Mangalmurti Residency have any legal issues or court cases?

No court cases are listed for Mangalmurti Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Mangalmurti Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SUMIT SANJAY KORAKE.

Other projects in Dhule (424001)

All 22 projects in Dhule (424001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.