GAURI NANDAN APARTMENT

by PATIL MAHAJAN · Mouje Satare, JalgaonAlso near Bhusawal

Possession date of GAURI NANDAN APARTMENT: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1130002600438, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about GAURI NANDAN APARTMENT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GAURI NANDAN APARTMENT has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GAURI NANDAN APARTMENT’s extension records on MahaRERA (PM1130002600438), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GAURI NANDAN APARTMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1130002600438
Status
Registered and active
Builder
PATIL MAHAJAN
Location
Mouje Satare, Jalgaon · 425201
Project type
Mixed
Registered on
15 May 2026
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
30
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of GAURI NANDAN APARTMENT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GAURI NANDAN APARTMENT100%11%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • GAURI NANDAN APARTMENT: covers 6 floors

Latest CC order on MahaRERA: dated 25/02/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAURI NANDAN APARTMENT every month.

GAURI NANDAN APARTMENT: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GAURI NANDAN APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GAURI NANDAN APARTMENT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GAURI NANDAN APARTMENT

What is the possession date of GAURI NANDAN APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GAURI NANDAN APARTMENT in Mouje Satare, Jalgaon is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GAURI NANDAN APARTMENT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GAURI NANDAN APARTMENT's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of GAURI NANDAN APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GAURI NANDAN APARTMENT in Mouje Satare, Jalgaon is PM1130002600438.

Is GAURI NANDAN APARTMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURI NANDAN APARTMENT is registered as PM1130002600438 and its status is "Registered and active".

What is the construction status of GAURI NANDAN APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURI NANDAN APARTMENT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GAURI NANDAN APARTMENT is 11% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does GAURI NANDAN APARTMENT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is GAURI NANDAN APARTMENT safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURI NANDAN APARTMENT is registered on MahaRERA as PM1130002600438, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GAURI NANDAN APARTMENT's possession date changes?

The latest dates are on GAURI NANDAN APARTMENT's MahaRERA page (PM1130002600438). GharKundli's Kundli Watch sends a free WhatsApp update on GAURI NANDAN APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GAURI NANDAN APARTMENT have?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURI NANDAN APARTMENT has one building filed: GAURI NANDAN APARTMENT with 6 floors and 38 units.

How much parking does GAURI NANDAN APARTMENT have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 7 covered car parking spaces for GAURI NANDAN APARTMENT.

How big is the land of GAURI NANDAN APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURI NANDAN APARTMENT stands on 1,046 sq m of land (about 0.3 acres), with 2,320 sq m of sanctioned built-up area.

Where can I read reviews of GAURI NANDAN APARTMENT?

Google Maps has reviews of GAURI NANDAN APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GAURI NANDAN APARTMENT?

GAURI NANDAN APARTMENT by PATIL MAHAJAN is in Mouje Satare, Jalgaon (pincode 425201), near Bhusawal, Maharashtra, and is registered on MahaRERA as PM1130002600438, per GharKundli's check of MahaRERA records.

How many homes are in GAURI NANDAN APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURI NANDAN APARTMENT has 30 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was GAURI NANDAN APARTMENT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GAURI NANDAN APARTMENT was registered on MahaRERA on 15 May 2026. GharKundli did not find a title report on the land on file there.

Are there court cases on GAURI NANDAN APARTMENT?

No court cases are listed for GAURI NANDAN APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of GAURI NANDAN APARTMENT?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PATIL MAHAJAN, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2029 in Jalgaon →

Other projects in Bhusawal

All 6 projects in Bhusawal (425201) →

Other projects by PATIL MAHAJAN

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.