Possession date of DWARKA: 31 July 2027, moved from 31 March 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50100054998, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about DWARKA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DWARKA has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA04082622011)

    Reason the builder gave MahaRERA: “The reason for extension is due to financial and family problem that we could not completed the project in given time. But know we are in track to complete the project in extended time frame.”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: DWARKA’s extension records on MahaRERA (P50100054998), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DWARKA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50100054998
Status
Registered and active
Builder
BALAJI BUILDCON
Location
Akola · 444001
Project type
Residential / Group Housing
Registered on
26 Feb 2024
Completion date at registration
March 2026
Latest completion date
July 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
12
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
10

Construction progress of DWARKA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RESIDENTIAL BUILDING100%100%80%20%

Commencement certificate (CC), as filed on MahaRERA

  • RESIDENTIAL BUILDING: covers 7 floors

Latest CC order on MahaRERA: dated 04/09/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DWARKA every month.

DWARKA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Balaji Buildcon (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA.

Read Google reviews of DWARKA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DWARKA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DWARKA

What is the possession date of DWARKA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DWARKA in Akola is 31 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for DWARKA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DWARKA's builder has filed on MahaRERA, the official one, is 31 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DWARKA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), DWARKA's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The reason for extension is due to financial and family problem that we could not completed the project in given time. But know we are in track to complete the project in extended time frame.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of DWARKA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DWARKA in Akola is P50100054998.

Is DWARKA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DWARKA is registered as P50100054998 and its status is "Registered and active".

What is the construction status of DWARKA?

According to GharKundli's check of MahaRERA records (updated October 2026), DWARKA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RESIDENTIAL BUILDING is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does DWARKA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is DWARKA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DWARKA is registered on MahaRERA as P50100054998, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DWARKA's possession date changes?

The latest dates are on DWARKA's MahaRERA page (P50100054998). GharKundli's Kundli Watch sends a free WhatsApp update on DWARKA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DWARKA have?

According to GharKundli's check of MahaRERA records (updated October 2026), DWARKA has one building filed: RESIDENTIAL BUILDING with 7 floors and 12 units.

How much parking does DWARKA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered car parking spaces for DWARKA.

How big is the land of DWARKA?

According to GharKundli's check of MahaRERA records (updated October 2026), DWARKA stands on 770 sq m of land (about 0.2 acres), with 2,370 sq m of sanctioned built-up area.

What is the track record of DWARKA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Buildcon (a group of 2 linked companies) has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 3 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of DWARKA?

Google Maps has reviews of DWARKA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DWARKA?

DWARKA by BALAJI BUILDCON is in Akola (pincode 444001), Maharashtra, and is registered on MahaRERA as P50100054998, per GharKundli's check of MahaRERA records.

How many homes are in DWARKA?

According to GharKundli's check of MahaRERA records (updated October 2026), DWARKA has 12 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was DWARKA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DWARKA was registered on MahaRERA on 26 February 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on DWARKA?

No court cases are listed for DWARKA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of DWARKA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BALAJI BUILDCON, which has 10 other projects registered on MahaRERA.

All projects with possession due in 2027 in Akola →

Other projects in pincode 444001

All 44 projects in Akola (444001) →

Other projects by BALAJI BUILDCON

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.