Dreamaland Business Park Phase No IV

by M/S DREAMZ INFRASTRUCTURE · Rallies Plot, Amravati 444901

What’s in the report? →

Possession date of Dreamaland Business Park Phase No IV (MahaRERA P50300004109): 30 June 2021, moved from 31 March 2021 (3 months later), and it has already passed. It has 394 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P50300004109. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P50300004109, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2021) has passed.

What do you want to know about Dreamaland Business Park Phase No IV?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Dreamaland Business Park Phase No IV has moved

  1. 31 March 2021

    Completion date given when the project was registered

  2. 30 June 2021

    Revised completion date on MahaRERA

Source: Dreamaland Business Park Phase No IV’s extension records on MahaRERA (P50300004109), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Dreamaland Business Park Phase No IV

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50300004109
Status
Lapsed (registration period ended)
Builder
M/S DREAMZ INFRASTRUCTURE
Location
Rallies Plot, Amravati · 444901
Project type
Commercial
Registered on
8 Aug 2017
Completion date at registration
March 2021
Latest completion date
June 2021
Delay so far
3 months
Homes
394
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Dreamaland Business Park Phase No IV, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B580%10%100%50%
B6100%0%100%100%
B70%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dreamaland Business Park Phase No IV every 1–2 months.

Dreamaland Business Park Phase No IV: buildings, flats and land, as filed on MahaRERA

  • Buildings: B5 (4 floors) · B6 (4 floors) · B7 (4 floors)
  • Land: 24,759 sq m (about 6.1 acres) · sanctioned built-up 18,453 sq m · recreational space 3,185 sq m
  • Land, as filed: 87,88,119,119 p,113,134,135,138,139,140,142 144 p
  • Map: Get directions

The builder’s record and reviews

Dreamz Infrastructure (a group of 3 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 10 months); 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Dreamaland Business Park Phase No IV →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Dreamaland Business Park Phase No IV: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Dreamaland Business Park Phase No IV

What is the possession date of Dreamaland Business Park Phase No IV?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Dreamaland Business Park Phase No IV in Rallies Plot, Amravati is 30 June 2021 — 3 months later than 31 March 2021, the date given at registration. That date has already passed.

The date has already moved 3 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Dreamaland Business Park Phase No IV?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Dreamaland Business Park Phase No IV's builder has filed on MahaRERA, the official one, is 30 June 2021, already 3 months later than the 31 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Dreamaland Business Park Phase No IV?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Dreamaland Business Park Phase No IV in Rallies Plot, Amravati is P50300004109.

Is Dreamaland Business Park Phase No IV registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreamaland Business Park Phase No IV is registered as P50300004109 and its status is "Lapsed (registration period ended)".

What is the current construction status of Dreamaland Business Park Phase No IV? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreamaland Business Park Phase No IV's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 10% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Dreamaland Business Park Phase No IV have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Dreamaland Business Park Phase No IV safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreamaland Business Park Phase No IV is registered on MahaRERA as P50300004109, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 3 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Dreamaland Business Park Phase No IV?

Dreamaland Business Park Phase No IV isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Dreamaland Business Park Phase No IV?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Dreamaland Business Park Phase No IV: gharkundli.com/tools/property-cost-calculator

Has Dreamaland Business Park Phase No IV received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Dreamaland Business Park Phase No IV isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Dreamaland Business Park Phase No IV?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreamaland Business Park Phase No IV's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Dreamaland Business Park Phase No IV uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Dreamaland Business Park Phase No IV was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Dreamaland Business Park Phase No IV's possession date changes?

The latest dates are on Dreamaland Business Park Phase No IV's MahaRERA page (P50300004109). GharKundli's Kundli Watch sends a free WhatsApp update on Dreamaland Business Park Phase No IV every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Dreamaland Business Park Phase No IV have?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreamaland Business Park Phase No IV has 3 buildings filed: B5 with 4 floors; B6 with 4 floors; B7 with 4 floors.

How big is the land of Dreamaland Business Park Phase No IV?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreamaland Business Park Phase No IV stands on 24,759 sq m of land (about 6.1 acres), with 18,453 sq m of sanctioned built-up area and 3,185 sq m of recreational open space.

What is the track record of Dreamaland Business Park Phase No IV's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreamz Infrastructure (a group of 3 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 10 months); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Dreamaland Business Park Phase No IV?

Google Maps has reviews of Dreamaland Business Park Phase No IV written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Dreamaland Business Park Phase No IV?

Dreamaland Business Park Phase No IV by M/S DREAMZ INFRASTRUCTURE is in Rallies Plot, Amravati, pincode 444901, Maharashtra, and is registered on MahaRERA as P50300004109, per GharKundli's check of MahaRERA records. Its land is filed as 87,88,119,119 p,113,134,135,138,139,140,142 144 p. GharKundli lists all 11 MahaRERA projects in Rallies Plot (444901).

How many flats are in Dreamaland Business Park Phase No IV?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreamaland Business Park Phase No IV has 394 homes in 3 towers registered on MahaRERA.

When was Dreamaland Business Park Phase No IV registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dreamaland Business Park Phase No IV was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.

Does Dreamaland Business Park Phase No IV have any legal issues or court cases?

No court cases are listed for Dreamaland Business Park Phase No IV on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Dreamaland Business Park Phase No IV?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S DREAMZ INFRASTRUCTURE, which has 4 other projects registered on MahaRERA.

Other projects in Rallies Plot (444901)

All 11 projects in Rallies Plot (444901) →

Other projects by M/S DREAMZ INFRASTRUCTURE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.