104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati
by Amravati Housing And Area Development Board Amravati · Akoli, Amravati 444601
What’s in the report? →Possession: 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati (MahaRERA P50300023822) is marked completed on MahaRERA. It has 41 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P50300023822. Status: Completed.
Source: MahaRERA website — records for P50300023822, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50300023822
- Status
- Completed
- Builder
- Amravati Housing And Area Development Board Amravati
- Location
- Akoli, Amravati · 444601
- Project type
- Residential / Group Housing
- Registered on
- 7 Jan 2020
- Completion date at registration
- December 2023
- Latest completion date
- December 2023
- Homes
- 41
- Towers
- 104
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 212A | 100% | 100% | 100% | 100% |
| 222A | 0% | 0% | 0% | 0% |
| 222B | 0% | 0% | 0% | 0% |
| 221A | 0% | 0% | 0% | 0% |
| 221B | 0% | 0% | 0% | 0% |
| 220A | 0% | 0% | 0% | 0% |
| 220B | 0% | 0% | 0% | 0% |
| 219 A | 0% | 0% | 0% | 0% |
| 219B | 0% | 0% | 0% | 0% |
| 218A | 0% | 0% | 0% | 0% |
| 218B | 0% | 0% | 0% | 0% |
| 217A | 0% | 0% | 0% | 0% |
| 217B | 0% | 0% | 0% | 0% |
| 216A | 0% | 0% | 0% | 0% |
| 216B | 0% | 0% | 0% | 0% |
| 212B | 100% | 100% | 100% | 100% |
| 215A | 0% | 0% | 0% | 0% |
| 215B | 0% | 0% | 0% | 0% |
| 214A | 0% | 0% | 0% | 0% |
| 214B | 0% | 0% | 0% | 0% |
| 213A | 100% | 100% | 100% | 100% |
| 213B | 100% | 100% | 100% | 100% |
| 211A | 0% | 0% | 0% | 0% |
| 211B | 0% | 0% | 0% | 0% |
| 210A | 0% | 0% | 0% | 0% |
| 210B | 0% | 0% | 0% | 0% |
| 209A | 0% | 0% | 0% | 0% |
| 209B | 0% | 0% | 0% | 0% |
| 223A | 0% | 0% | 0% | 0% |
| 223B | 0% | 0% | 0% | 0% |
Showing 30 of 104 towers.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati every 1–2 months.
104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati: buildings, flats and land, as filed on MahaRERA
- Buildings: 237A (2 floors) · 237B (2 floors) · 238A (2 floors) · 238B (2 floors)
- Land: 19,498 sq m (about 4.8 acres) · sanctioned built-up 93 sq m · recreational space 38,774 sq m
- Boundaries filed include: Naya Amravati Railway Station, Navasari Ring Road
- Land, as filed: 47,57,58
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati
What is the possession date of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati in Akoli, Amravati is 30 December 2023.
Is the builder's possession date different from the MahaRERA date for 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati's builder has filed on MahaRERA, the official one, is 30 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati in Akoli, Amravati is P50300023822.
Is 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati is registered as P50300023822 and its status is "Completed".
What is the current construction status of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 0% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.
Does 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati is registered on MahaRERA as P50300023822, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati: gharkundli.com/tools/property-cost-calculator
Has 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati completed?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati is marked completed on MahaRERA, and the completion date filed there is 30 December 2023. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati's possession date changes?
The latest dates are on 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati's MahaRERA page (P50300023822). GharKundli's Kundli Watch sends a free WhatsApp update on 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati have?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati has 4 buildings filed: 237A with 2 floors; 237B with 2 floors; 238A with 2 floors; 238B with 2 floors.
How big is the land of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati stands on 19,498 sq m of land (about 4.8 acres), with 93 sq m of sanctioned built-up area and 38,774 sq m of recreational open space.
What are the reviews of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
Google Maps has reviews of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati by Amravati Housing And Area Development Board Amravati is in Akoli, Amravati, pincode 444601, Maharashtra, and is registered on MahaRERA as P50300023822, per GharKundli's check of MahaRERA records. Its boundaries filed there include Naya Amravati Railway Station, Navasari Ring Road. Its land is filed as 47,57,58. GharKundli lists all 69 MahaRERA projects in Amravati (444601).
How many flats are in 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati has 41 homes in 104 towers registered on MahaRERA.
When was 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati was registered on MahaRERA on 7 January 2020. GharKundli did not find a title report on the land on file there.
Does 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati have any legal issues or court cases?
No court cases are listed for 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Amravati Housing And Area Development Board Amravati, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of 104 HIG tenaments on S.N. 47,57,58 at Mouje Akoli, Amravati
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Amravati
- Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG
- Jannat Complex
- Lakshmi Shri Resimercial
- Rachana Srushti Phase II
- Dream Imperia
- Raj Township
- Dubai City
- Green Heights
Other projects by Amravati Housing And Area Development Board Amravati
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.