Vivanta Infinity Private Limited
by VIVANTA INFINITY PRIVATE LIMITED · Biyani Square, Camp, Amravati
Possession date of Vivanta Infinity Private Limited: 30 January 2027, moved from 31 March 2025 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50300031314, and currently active. Its completion date has moved from March 2025 to January 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Vivanta Infinity Private Limited?
How the possession date of Vivanta Infinity Private Limited has moved
31 March 2025
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EXT50300027674)
Reason the builder gave MahaRERA: “Due to some unavoidable reasons we are unable to complete our project within time. So we request you to kindly accept our request and extend the date of completion. Thank you.”
30 September 2026
Extended at the builder's request (MahaRERA application EA25022620013)
Reason the builder gave MahaRERA: “The absence of key technical supervisors led to a slowdown in maintaining the required quality standards, forcing a pause in execution to ensure safety compliance.”
30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vivanta Infinity Private Limited’s extension records on MahaRERA (P50300031314), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vivanta Infinity Private Limited
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50300031314
- Status
- Registered and active
- Builder
- VIVANTA INFINITY PRIVATE LIMITED
- Location
- Biyani Square, Camp, Amravati · 444602
- Project type
- Others
- Registered on
- 15 Oct 2021
- Completion date at registration
- March 2025
- Latest completion date
- January 2027
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 135
- Sold or booked
- 65%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Vivanta Infinity Private Limited, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vivanta The Infinity | 95% | 95% | 80% | 25% |
| Vivanta The Camp | 95% | 95% | 85% | 25% |
Commencement certificate (CC), as filed on MahaRERA
- Vivanta The Infinity: covers 14 floors
- Vivanta The Camp: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vivanta Infinity Private Limited every month.
Vivanta Infinity Private Limited: buildings, flats and land, as filed on MahaRERA
- Buildings: Vivanta The Infinity (14 floors, 124 units) · Vivanta The Camp (13 floors, 73 units)
- Car parking: 92 covered
- Land: 4,422 sq m (about 1.1 acres) · sanctioned built-up 23,766 sq m · recreational space 531 sq m
- Boundaries filed include: Collector office to University road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Vivanta Infinity Private Limited →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vivanta Infinity Private Limited: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vivanta Infinity Private Limited
What is the possession date of Vivanta Infinity Private Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vivanta Infinity Private Limited in Biyani Square, Camp, Amravati is 30 January 2027 — 18 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Vivanta Infinity Private Limited?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vivanta Infinity Private Limited's builder has filed on MahaRERA, the official one, is 30 January 2027, already 18 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vivanta Infinity Private Limited extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vivanta Infinity Private Limited's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "Due to some unavoidable reasons we are unable to complete our project within time. So we request you to kindly accept our request and extend the date of completion. Thank you."; to 30 September 2026, giving the reason "The absence of key technical supervisors led to a slowdown in maintaining the required quality standards, forcing a pause in execution to ensure safety compliance.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vivanta Infinity Private Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vivanta Infinity Private Limited in Biyani Square, Camp, Amravati is P50300031314.
Is Vivanta Infinity Private Limited registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vivanta Infinity Private Limited is registered as P50300031314 and its status is "Registered and active".
What is the construction status of Vivanta Infinity Private Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), Vivanta Infinity Private Limited's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 95% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Vivanta Infinity Private Limited have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vivanta Infinity Private Limited safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vivanta Infinity Private Limited is registered on MahaRERA as P50300031314, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Vivanta Infinity Private Limited's possession date changes?
The latest dates are on Vivanta Infinity Private Limited's MahaRERA page (P50300031314). GharKundli's Kundli Watch sends a free WhatsApp update on Vivanta Infinity Private Limited every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vivanta Infinity Private Limited have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vivanta Infinity Private Limited has 2 buildings filed: Vivanta The Infinity with 14 floors and 124 units; Vivanta The Camp with 13 floors and 73 units.
How much parking does Vivanta Infinity Private Limited have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 92 covered car parking spaces for Vivanta Infinity Private Limited.
How big is the land of Vivanta Infinity Private Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), Vivanta Infinity Private Limited stands on 4,422 sq m of land (about 1.1 acres), with 23,766 sq m of sanctioned built-up area and 531 sq m of recreational open space.
Where can I read reviews of Vivanta Infinity Private Limited?
Google Maps has reviews of Vivanta Infinity Private Limited written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vivanta Infinity Private Limited?
Vivanta Infinity Private Limited by VIVANTA INFINITY PRIVATE LIMITED is in Biyani Square, Camp, Amravati (pincode 444602), Maharashtra, and is registered on MahaRERA as P50300031314, per GharKundli's check of MahaRERA records. Its boundaries filed there include Collector office to University road.
How many homes are in Vivanta Infinity Private Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), Vivanta Infinity Private Limited has 135 homes in 2 towers registered on MahaRERA, and 65% of them are sold or booked.
When was Vivanta Infinity Private Limited registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vivanta Infinity Private Limited was registered on MahaRERA on 15 October 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Vivanta Infinity Private Limited?
No court cases are listed for Vivanta Infinity Private Limited on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Vivanta Infinity Private Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VIVANTA INFINITY PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of Vivanta Infinity Private Limited
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Amravati →
Other projects in Amravati
- JANNAT COMPLEX
- LAKSHMI SHRI RESIMERCIAL
- RACHANA SRUSHTI PHASE II
- Dream Imperia
- RAJ TOWNSHIP
- DUBAI CITY
- Green Heights
- Midas Enclave
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.