Possession date of KRUSHNAI HEIGHTS: 15 December 2025, moved from 31 December 2024 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P50300046902. Status: De-Registered.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about KRUSHNAI HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KRUSHNAI HEIGHTS has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 15 December 2025

    Extended at the builder's request (MahaRERA application EXT50300025911)

    Reason the builder gave MahaRERA:
    “WE KINDLY REQUEST AN EXTENTION OF THE COMPLETION DATE OF KRUSHNAI HEIGHTS DUE TO FOLLOWING REASONS Shortage of Key Raw Materials:1]The unavailability of specific red bricks and Wardha river sand due to supply chain disruptions directly affe…” Read the full reason“WE KINDLY REQUEST AN EXTENTION OF THE COMPLETION DATE OF KRUSHNAI HEIGHTS DUE TO FOLLOWING REASONS Shortage of Key Raw Materials:1]The unavailability of specific red bricks and Wardha river sand due to supply chain disruptions directly affected construction progress.2]The materials required for structural work and finishing were delayed, causing a cascading effect on the project schedule.3]Skilled Labor Shortage Due to Elections:4]The Lok Sabha and Vidhan Sabha elections led to a temporary migration of skilled labor, affecting critical work like finishing, plumbing, and electrical installat…”

Source: KRUSHNAI HEIGHTS’s extension records on MahaRERA (P50300046902), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KRUSHNAI HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50300046902
Status
De-Registered
Builder
URJA INFRASTRUCTURE
Location
Sai Nagar, Amravati · 444607
Project type
Residential / Group Housing
Registered on
16 Sep 2022
Completion date at registration
December 2024
Latest completion date
December 2025
Delay so far
12 months
Homes
15
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of KRUSHNAI HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KRUSHNAI HEIGHTS100%100%90%80%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KRUSHNAI HEIGHTS every month.

KRUSHNAI HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: KRUSHNAI HEIGHTS (5 floors)
  • Land: 334 sq m (about 0.1 acres) · sanctioned built-up 367 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KRUSHNAI HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KRUSHNAI HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KRUSHNAI HEIGHTS

What is the possession date of KRUSHNAI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KRUSHNAI HEIGHTS in Sai Nagar, Amravati is 15 December 2025 — 12 months later than 31 December 2024, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for KRUSHNAI HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KRUSHNAI HEIGHTS's builder has filed on MahaRERA, the official one, is 15 December 2025, already 12 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KRUSHNAI HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNAI HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 15 December 2025, giving the reason "WE KINDLY REQUEST AN EXTENTION OF THE COMPLETION DATE OF KRUSHNAI HEIGHTS DUE TO FOLLOWING REASONS Shortage of Key Raw Materials:1]The unavailability of specific red bricks and Wardha river sand due to supply chain disruptions directly affected construction progress.2]The materials required for structural work and finishing were delayed, causing a cascading effect on the project schedule.3]Skilled Labor Shortage Due to Elections:4]The Lok Sabha and Vidhan Sabha elections led to a temporary migration of skilled labor, affecting critical work like finishing, plumbing, and electrical installat…".

What is the RERA number of KRUSHNAI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KRUSHNAI HEIGHTS in Sai Nagar, Amravati is P50300046902.

Is KRUSHNAI HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNAI HEIGHTS is registered as P50300046902 and its status is "De-Registered". On MahaRERA's own list: Deregistered by MahaRERA. MahaRERA has deregistered this project by order. Builders often apply for this themselves when a project doesn't go ahead -- read the order before paying anything.

What is the construction status of KRUSHNAI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNAI HEIGHTS's status on MahaRERA is "De-Registered". As filed by the builder, slab work on KRUSHNAI HEIGHTS is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does KRUSHNAI HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is KRUSHNAI HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNAI HEIGHTS is registered on MahaRERA as P50300046902, its MahaRERA status is "De-Registered", its completion date has moved 12 months since registration, no complaints are listed against it and it is on MahaRERA's list "Deregistered by MahaRERA". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KRUSHNAI HEIGHTS's possession date changes?

The latest dates are on KRUSHNAI HEIGHTS's MahaRERA page (P50300046902). GharKundli's Kundli Watch sends a free WhatsApp update on KRUSHNAI HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KRUSHNAI HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNAI HEIGHTS has one building filed: KRUSHNAI HEIGHTS with 5 floors.

How big is the land of KRUSHNAI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNAI HEIGHTS stands on 334 sq m of land (about 0.1 acres), with 367 sq m of sanctioned built-up area.

Where can I read reviews of KRUSHNAI HEIGHTS?

Google Maps has reviews of KRUSHNAI HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KRUSHNAI HEIGHTS?

KRUSHNAI HEIGHTS by URJA INFRASTRUCTURE is in Sai Nagar, Amravati (pincode 444607), Maharashtra, and is registered on MahaRERA as P50300046902, per GharKundli's check of MahaRERA records.

How many homes are in KRUSHNAI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNAI HEIGHTS has 15 homes in 1 tower registered on MahaRERA.

When was KRUSHNAI HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRUSHNAI HEIGHTS was registered on MahaRERA on 16 September 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on KRUSHNAI HEIGHTS?

No court cases are listed for KRUSHNAI HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of KRUSHNAI HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is URJA INFRASTRUCTURE.

Other projects in pincode 444607

All 20 projects in Sai Nagar (444607) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.