Skip to content
GharKundli

DCC Dreamz City Chambers

by DREAMZ-CITY REAL ESTATE PVT LTD · Rallies Plot, AmravatiAlso near Rukhmini Nagar, H. V. Nagar

Possession date of DCC Dreamz City Chambers: 28 February 2027, moved from 31 October 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50300048015, and currently active. Its completion date has moved from October 2025 to February 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about DCC Dreamz City Chambers?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DCC Dreamz City Chambers has moved

  1. 31 October 2025

    Completion date given when the project was registered

  2. 31 October 2026

    Extended at the builder's request (MahaRERA application EA19122518776)

    Reason the builder gave MahaRERA:
    “We, Dreamz­City Real Estate Pvt Ltd, are promoter of the project DCC Dreamz City Chambers, registered under MahaRERA vide registration number P50300048015. Sir the foresaid project was projected to be completed by 31/10/2025 but due to less…” Read the full reason“We, Dreamz­City Real Estate Pvt Ltd, are promoter of the project DCC Dreamz City Chambers, registered under MahaRERA vide registration number P50300048015. Sir the foresaid project was projected to be completed by 31/10/2025 but due to lesser response in bookings and technical problems raised in the project the project is now bound to be delayed. The project till date is about 50% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 180 units in the project, we have sold 35 units. Out of which 23 have already given their co…”
  3. 28 February 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: DCC Dreamz City Chambers’s extension records on MahaRERA (P50300048015), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DCC Dreamz City Chambers

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50300048015
Status
Registered and active
Builder
DREAMZ-CITY REAL ESTATE PVT LTD
Location
Rallies Plot, Amravati · 444601
Project type
Commercial
Registered on
7 Dec 2022
Completion date at registration
October 2025
Latest completion date
February 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
20%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of DCC Dreamz City Chambers, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DCC Dreamz CIty Chambers100%100%100%70%

Commencement certificate (CC), as filed on MahaRERA

  • DCC Dreamz CIty Chambers: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DCC Dreamz City Chambers every month.

DCC Dreamz City Chambers: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of DCC Dreamz City Chambers →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DCC Dreamz City Chambers: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DCC Dreamz City Chambers

What is the possession date of DCC Dreamz City Chambers?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DCC Dreamz City Chambers in Rallies Plot, Amravati is 28 February 2027 — 12 months later than 31 October 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for DCC Dreamz City Chambers?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DCC Dreamz City Chambers's builder has filed on MahaRERA, the official one, is 28 February 2027, already 12 months later than the 31 October 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DCC Dreamz City Chambers extended?

According to GharKundli's check of MahaRERA records (updated October 2026), DCC Dreamz City Chambers's builder applied to MahaRERA to extend the completion date once: to 31 October 2026, giving the reason "We, Dreamz­City Real Estate Pvt Ltd, are promoter of the project DCC Dreamz City Chambers, registered under MahaRERA vide registration number P50300048015. Sir the foresaid project was projected to be completed by 31/10/2025 but due to lesser response in bookings and technical problems raised in the project the project is now bound to be delayed. The project till date is about 50% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 180 units in the project, we have sold 35 units. Out of which 23 have already given their co…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of DCC Dreamz City Chambers?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DCC Dreamz City Chambers in Rallies Plot, Amravati is P50300048015.

Is DCC Dreamz City Chambers registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DCC Dreamz City Chambers is registered as P50300048015 and its status is "Registered and active".

What is the construction status of DCC Dreamz City Chambers?

According to GharKundli's check of MahaRERA records (updated October 2026), DCC Dreamz City Chambers's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DCC Dreamz CIty Chambers is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does DCC Dreamz City Chambers have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is DCC Dreamz City Chambers safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DCC Dreamz City Chambers is registered on MahaRERA as P50300048015, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DCC Dreamz City Chambers's possession date changes?

The latest dates are on DCC Dreamz City Chambers's MahaRERA page (P50300048015). GharKundli's Kundli Watch sends a free WhatsApp update on DCC Dreamz City Chambers every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DCC Dreamz City Chambers have?

According to GharKundli's check of MahaRERA records (updated October 2026), DCC Dreamz City Chambers has one building filed: DCC Dreamz CIty Chambers with 9 floors and 179 units.

How big is the land of DCC Dreamz City Chambers?

According to GharKundli's check of MahaRERA records (updated October 2026), DCC Dreamz City Chambers stands on 1,660 sq m of land (about 0.4 acres), with 5,745 sq m of sanctioned built-up area.

Where can I read reviews of DCC Dreamz City Chambers?

Google Maps has reviews of DCC Dreamz City Chambers written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DCC Dreamz City Chambers?

DCC Dreamz City Chambers by DREAMZ-CITY REAL ESTATE PVT LTD is in Rallies Plot, Amravati (pincode 444601), near Rukhmini Nagar, H. V. Nagar, Maharashtra, and is registered on MahaRERA as P50300048015, per GharKundli's check of MahaRERA records.

How many homes are in DCC Dreamz City Chambers?

According to GharKundli's check of MahaRERA records (updated October 2026), DCC Dreamz City Chambers has 0 homes in 1 tower registered on MahaRERA, and 20% of them are sold or booked.

When was DCC Dreamz City Chambers registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DCC Dreamz City Chambers was registered on MahaRERA on 7 December 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on DCC Dreamz City Chambers?

No court cases are listed for DCC Dreamz City Chambers on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of DCC Dreamz City Chambers?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DREAMZ-CITY REAL ESTATE PVT LTD.

All projects with possession due in 2027 in Amravati →

Other projects in Amravati

All 22 projects in Amravati (444601) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.