MAHENDRA ABODES
by ANKESH NAVINKUMAR CHORDIYA · Ganesh Colony, Amravati
Possession date of MAHENDRA ABODES: 30 July 2026, moved from 31 March 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P50300051925. Status: Lapsed (registration period ended). Its completion date has moved from March 2025 to July 2026: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about MAHENDRA ABODES?
GharKundli’s full report on MAHENDRA ABODES
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50300051925
- Status
- Lapsed (registration period ended)
- Builder
- ANKESH NAVINKUMAR CHORDIYA
- Location
- Ganesh Colony, Amravati · 444605
- Project type
- Residential / Group Housing
- Registered on
- 13 Jul 2023
- Completion date at registration
- March 2025
- Latest completion date
- July 2026
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 14
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of MAHENDRA ABODES, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MAHENDRA ABODES | 95% | 100% | 90% | 30% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAHENDRA ABODES every month.
MAHENDRA ABODES: buildings, flats and land, as filed on MahaRERA
- Buildings: MAHENDRA ABODES (9 floors)
- Land: 520 sq m (about 0.1 acres) · sanctioned built-up 1,641 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MAHENDRA ABODES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MAHENDRA ABODES: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MAHENDRA ABODES
What is the possession date of MAHENDRA ABODES?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MAHENDRA ABODES in Ganesh Colony, Amravati is 30 July 2026 — 12 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for MAHENDRA ABODES?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MAHENDRA ABODES's builder has filed on MahaRERA, the official one, is 30 July 2026, already 12 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of MAHENDRA ABODES?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MAHENDRA ABODES in Ganesh Colony, Amravati is P50300051925.
Is MAHENDRA ABODES registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA ABODES is registered as P50300051925 and its status is "Lapsed (registration period ended)".
What is the construction status of MAHENDRA ABODES?
According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA ABODES's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MAHENDRA ABODES is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does MAHENDRA ABODES have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is MAHENDRA ABODES safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA ABODES is registered on MahaRERA as P50300051925, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MAHENDRA ABODES's possession date changes?
The latest dates are on MAHENDRA ABODES's MahaRERA page (P50300051925). GharKundli's Kundli Watch sends a free WhatsApp update on MAHENDRA ABODES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MAHENDRA ABODES have?
According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA ABODES has one building filed: MAHENDRA ABODES with 9 floors.
How big is the land of MAHENDRA ABODES?
According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA ABODES stands on 520 sq m of land (about 0.1 acres), with 1,641 sq m of sanctioned built-up area.
Where can I read reviews of MAHENDRA ABODES?
Google Maps has reviews of MAHENDRA ABODES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MAHENDRA ABODES?
MAHENDRA ABODES by ANKESH NAVINKUMAR CHORDIYA is in Ganesh Colony, Amravati (pincode 444605), Maharashtra, and is registered on MahaRERA as P50300051925, per GharKundli's check of MahaRERA records.
How many homes are in MAHENDRA ABODES?
According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA ABODES has 14 homes in 1 tower registered on MahaRERA.
When was MAHENDRA ABODES registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MAHENDRA ABODES was registered on MahaRERA on 13 July 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on MAHENDRA ABODES?
No court cases are listed for MAHENDRA ABODES on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MAHENDRA ABODES?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ANKESH NAVINKUMAR CHORDIYA.
Check it yourself on MahaRERA
- How to check the possession date of MAHENDRA ABODES
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Amravati →
All projects in H. V. Nagar (444605) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.