Vastuvishwa Apartments, Bapatwadi

by RSV Realities · Near Bhu-Vikas Bank, Wardha

Possession date of Vastuvishwa Apartments, Bapatwadi: 5 February 2023, moved from 31 March 2019 (47 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P50400012080. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (February 2023) has passed.

What do you want to know about Vastuvishwa Apartments, Bapatwadi?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Vastuvishwa Apartments, Bapatwadi has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 30 March 2020

    Extended at the builder's request (MahaRERA application EXT50400001545)

    Reason the builder gave MahaRERA:
    “Delay in Completion of the Scheme is Due to Non Availability of Sand(Sand Auction was on hold by State Govt from Sept'18 till 15th of Mar'19). Hence delay in finishing the Work. Application for Completion cum Occupation Certificate could no…” Read the full reason“Delay in Completion of the Scheme is Due to Non Availability of Sand(Sand Auction was on hold by State Govt from Sept'18 till 15th of Mar'19). Hence delay in finishing the Work. Application for Completion cum Occupation Certificate could not Initiated due to this with Town Planner(Nagar Parishad, Wardha).”
  3. 5 August 2022

    Extended at the builder's request (MahaRERA application EXT50400010679)

    Reason the builder gave MahaRERA:
    “Actually the project is completed in all respects ..and the application for occupation certificate was also applied for,.. to the chief officer, municipal council ,Wardha, on 07/02/2020.. but due to the delay on part of M.C, Wardha, and the…” Read the full reason“Actually the project is completed in all respects ..and the application for occupation certificate was also applied for,.. to the chief officer, municipal council ,Wardha, on 07/02/2020.. but due to the delay on part of M.C, Wardha, and the corona virus epidemic, the O,C could not be obtained by us..Hence the extension is requested for a period of at least 6 months or so....”
  4. 5 February 2023

    Revised completion date on MahaRERA

Source: Vastuvishwa Apartments, Bapatwadi’s extension records on MahaRERA (P50400012080), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vastuvishwa Apartments, Bapatwadi

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50400012080
Status
Lapsed (registration period ended)
Builder
RSV Realities
Location
Near Bhu-Vikas Bank, Wardha · 442001
Project type
Others
Registered on
1 Sep 2017
Completion date at registration
March 2019
Latest completion date
February 2023
Delay so far
47 months
Homes
14
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Vastuvishwa Apartments, Bapatwadi, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Vastuvishwa Apartments, Wardha100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vastuvishwa Apartments, Bapatwadi every month.

Vastuvishwa Apartments, Bapatwadi: buildings, flats and land, as filed on MahaRERA

  • Buildings: Vastuvishwa Apartments, Wardha (7 floors)
  • Land: 608 sq m (about 0.2 acres) · sanctioned built-up 783 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Vastuvishwa Apartments, Bapatwadi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vastuvishwa Apartments, Bapatwadi: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Vastuvishwa Apartments, Bapatwadi

What is the possession date of Vastuvishwa Apartments, Bapatwadi?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vastuvishwa Apartments, Bapatwadi in Near Bhu-Vikas Bank, Wardha is 5 February 2023 — 47 months later than 31 March 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Vastuvishwa Apartments, Bapatwadi?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vastuvishwa Apartments, Bapatwadi's builder has filed on MahaRERA, the official one, is 5 February 2023, already 47 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vastuvishwa Apartments, Bapatwadi extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Vastuvishwa Apartments, Bapatwadi's builder applied to MahaRERA to extend the completion date 2 times: to 30 March 2020, giving the reason "Delay in Completion of the Scheme is Due to Non Availability of Sand(Sand Auction was on hold by State Govt from Sept'18 till 15th of Mar'19). Hence delay in finishing the Work. Application for Completion cum Occupation Certificate could not Initiated due to this with Town Planner(Nagar Parishad, Wardha)."; to 5 August 2022, giving the reason "Actually the project is completed in all respects ..and the application for occupation certificate was also applied for,.. to the chief officer, municipal council ,Wardha, on 07/02/2020.. but due to the delay on part of M.C, Wardha, and the corona virus epidemic, the O,C could not be obtained by us..Hence the extension is requested for a period of at least 6 months or so....".

What is the RERA number of Vastuvishwa Apartments, Bapatwadi?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vastuvishwa Apartments, Bapatwadi in Near Bhu-Vikas Bank, Wardha is P50400012080.

Is Vastuvishwa Apartments, Bapatwadi registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vastuvishwa Apartments, Bapatwadi is registered as P50400012080 and its status is "Lapsed (registration period ended)".

What is the construction status of Vastuvishwa Apartments, Bapatwadi?

According to GharKundli's check of MahaRERA records (updated November 2026), Vastuvishwa Apartments, Bapatwadi's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Vastuvishwa Apartments, Wardha is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Vastuvishwa Apartments, Bapatwadi have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Vastuvishwa Apartments, Bapatwadi safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Vastuvishwa Apartments, Bapatwadi is registered on MahaRERA as P50400012080, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 47 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Vastuvishwa Apartments, Bapatwadi's possession date changes?

The latest dates are on Vastuvishwa Apartments, Bapatwadi's MahaRERA page (P50400012080). GharKundli's Kundli Watch sends a free WhatsApp update on Vastuvishwa Apartments, Bapatwadi every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vastuvishwa Apartments, Bapatwadi have?

According to GharKundli's check of MahaRERA records (updated November 2026), Vastuvishwa Apartments, Bapatwadi has one building filed: Vastuvishwa Apartments, Wardha with 7 floors.

How big is the land of Vastuvishwa Apartments, Bapatwadi?

According to GharKundli's check of MahaRERA records (updated November 2026), Vastuvishwa Apartments, Bapatwadi stands on 608 sq m of land (about 0.2 acres), with 783 sq m of sanctioned built-up area.

Where can I read reviews of Vastuvishwa Apartments, Bapatwadi?

Google Maps has reviews of Vastuvishwa Apartments, Bapatwadi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Vastuvishwa Apartments, Bapatwadi?

Vastuvishwa Apartments, Bapatwadi by RSV Realities is in Near Bhu-Vikas Bank, Wardha (pincode 442001), Maharashtra, and is registered on MahaRERA as P50400012080, per GharKundli's check of MahaRERA records.

How many homes are in Vastuvishwa Apartments, Bapatwadi?

According to GharKundli's check of MahaRERA records (updated November 2026), Vastuvishwa Apartments, Bapatwadi has 14 homes in 1 tower registered on MahaRERA.

When was Vastuvishwa Apartments, Bapatwadi registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vastuvishwa Apartments, Bapatwadi was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Vastuvishwa Apartments, Bapatwadi?

No court cases are listed for Vastuvishwa Apartments, Bapatwadi on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Vastuvishwa Apartments, Bapatwadi?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RSV Realities.