Infrastructures Dreamheight-2
by D H INFRASTRUCTURES · Medical Square, Wardha 442102Registered on MahaRERA as “DREAMHEIGHT-2”
What’s in the report? →Possession date of Infrastructures Dreamheight-2 (MahaRERA P50400014356): 30 September 2020, moved from 30 March 2019 (18 months later), and it has already passed. It has 14 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P50400014356. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P50400014356, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2020) has passed.
What do you want to know about Infrastructures Dreamheight-2?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Infrastructures Dreamheight-2 has moved
30 March 2019
Completion date given when the project was registered
31 March 2020
Extended at the builder's request (MahaRERA application EXT50400001663)
Reason the builder gave MahaRERA: “Due to labour problems, Non availability of sand.”
30 September 2020
Revised completion date on MahaRERA
Source: Infrastructures Dreamheight-2’s extension records on MahaRERA (P50400014356), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Infrastructures Dreamheight-2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50400014356
- Status
- Lapsed (registration period ended)
- Builder
- D H INFRASTRUCTURES
- Location
- Medical Square, Wardha · 442102
- Project type
- Residential / Group Housing
- Registered on
- 24 Nov 2017
- Completion date at registration
- March 2019
- Latest completion date
- September 2020
- Delay so far
- 18 months
- Homes
- 14
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Infrastructures Dreamheight-2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DREAMHEIGHT-2 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Infrastructures Dreamheight-2 every 1–2 months.
Infrastructures Dreamheight-2: buildings, flats and land, as filed on MahaRERA
- Buildings: DREAMHEIGHT-2 (6 floors)
- Land: 557 sq m (about 0.1 acres) · sanctioned built-up 669 sq m · recreational space 363 sq m
- Boundaries filed include: LAYOUT ROAD
- Land, as filed: PLOT NO 45 AND 50
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Infrastructures Dreamheight-2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Infrastructures Dreamheight-2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Infrastructures Dreamheight-2
What is the possession date of Infrastructures Dreamheight-2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Infrastructures Dreamheight-2 in Medical Square, Wardha is 30 September 2020 — 18 months later than 30 March 2019, the date given at registration. That date has already passed.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Infrastructures Dreamheight-2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Infrastructures Dreamheight-2's builder has filed on MahaRERA, the official one, is 30 September 2020, already 18 months later than the 30 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Infrastructures Dreamheight-2 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2's builder applied to MahaRERA to extend the completion date once: to 31 March 2020, giving the reason "Due to labour problems, Non availability of sand.".
What is the RERA number of Infrastructures Dreamheight-2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Infrastructures Dreamheight-2 in Medical Square, Wardha is P50400014356.
Is Infrastructures Dreamheight-2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2 is registered as P50400014356 and its status is "Lapsed (registration period ended)".
What is the current construction status of Infrastructures Dreamheight-2? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on DREAMHEIGHT-2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Infrastructures Dreamheight-2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Infrastructures Dreamheight-2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2 is registered on MahaRERA as P50400014356, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Infrastructures Dreamheight-2?
Infrastructures Dreamheight-2 isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Infrastructures Dreamheight-2?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Infrastructures Dreamheight-2: gharkundli.com/tools/property-cost-calculator
Has Infrastructures Dreamheight-2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2 isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Infrastructures Dreamheight-2?
According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Infrastructures Dreamheight-2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Infrastructures Dreamheight-2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Infrastructures Dreamheight-2's possession date changes?
The latest dates are on Infrastructures Dreamheight-2's MahaRERA page (P50400014356). GharKundli's Kundli Watch sends a free WhatsApp update on Infrastructures Dreamheight-2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Infrastructures Dreamheight-2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2 has one building filed: DREAMHEIGHT-2 with 6 floors.
How big is the land of Infrastructures Dreamheight-2?
According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2 stands on 557 sq m of land (about 0.1 acres), with 669 sq m of sanctioned built-up area and 363 sq m of recreational open space.
What are the reviews of Infrastructures Dreamheight-2?
Google Maps has reviews of Infrastructures Dreamheight-2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Infrastructures Dreamheight-2?
Infrastructures Dreamheight-2 by D H INFRASTRUCTURES is in Medical Square, Wardha, pincode 442102, Maharashtra, and is registered on MahaRERA as P50400014356, per GharKundli's check of MahaRERA records. Its boundaries filed there include LAYOUT ROAD. Its land is filed as PLOT NO 45 AND 50. GharKundli lists all 2 MahaRERA projects in Sewagram (442102).
How many flats are in Infrastructures Dreamheight-2?
According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2 has 14 homes in 1 tower registered on MahaRERA.
When was Infrastructures Dreamheight-2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Infrastructures Dreamheight-2 was registered on MahaRERA on 24 November 2017. GharKundli did not find a title report on the land on file there.
Does Infrastructures Dreamheight-2 have any legal issues or court cases?
No court cases are listed for Infrastructures Dreamheight-2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Infrastructures Dreamheight-2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is D H INFRASTRUCTURES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Infrastructures Dreamheight-2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Wardha
- Vyankatesh City 4
- Shreem Vistara
- Majestic Residency
- Vibhavari Enclave
- Gajanan Leela 7
- Keystone Elevate-tower C1
- City Center
- DHP Town-wing D
Other projects by D H INFRASTRUCTURES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.