ORANGE CITY PARK II
by MAITREYA DEVELOPERS · Yerkheda, Nagpur
Possession: ORANGE CITY PARK II is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500017849. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about ORANGE CITY PARK II?
How the possession date of ORANGE CITY PARK II has moved
1 February 2022
Completion date given when the project was registered
1 February 2023
Extended at the builder's request (MahaRERA application EXT50500011478)
Reason the builder gave MahaRERA:
“There is a revision in Building Plans and as a result 7 additional flats will be constructed. The necessary sanction from Development Authority viz. NMRDA is obtained, copy of which is attached herewith. Hence additional time required for c…” Read the full reason
“There is a revision in Building Plans and as a result 7 additional flats will be constructed. The necessary sanction from Development Authority viz. NMRDA is obtained, copy of which is attached herewith. Hence additional time required for completing additional execution as per revised Sanction Plan.”
Source: ORANGE CITY PARK II’s extension records on MahaRERA (P50500017849), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ORANGE CITY PARK II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- ORANGE CITY PARK IIIP50500023595 · possession 26 Sep 2025
- MahaRERA registration
- P50500017849
- Status
- Completed
- Builder
- MAITREYA DEVELOPERS
- Location
- Yerkheda, Nagpur · 441002
- Project type
- Residential / Group Housing
- Registered on
- 24 Sep 2018
- Completion date at registration
- February 2022
- Latest completion date
- February 2023
- Delay so far
- 12 months
- Homes
- 84
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of ORANGE CITY PARK II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DEFFODIL | 100% | 100% | 100% | 100% |
| ERICA | 100% | 100% | 100% | 100% |
| FREESIA | 100% | 100% | 100% | 100% |
| GARDENIA | 100% | 100% | 100% | 100% |
| HIBISCUS | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ORANGE CITY PARK II every month.
ORANGE CITY PARK II: buildings, flats and land, as filed on MahaRERA
- Buildings: DEFFODIL (6 floors) · ERICA (6 floors) · FREESIA (6 floors) · GARDENIA (6 floors) · HIBISCUS (6 floors)
- Land: 3,345 sq m (about 0.8 acres) · sanctioned built-up 4,659 sq m
- Boundaries filed include: NATIONAL HIGHWAY NO 7, LOKVIHAR ORANGE CITY PARK I
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ORANGE CITY PARK II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ORANGE CITY PARK II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ORANGE CITY PARK II
What is the possession date of ORANGE CITY PARK II?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ORANGE CITY PARK II in Yerkheda, Nagpur is 1 February 2023 — 12 months later than 1 February 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ORANGE CITY PARK II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ORANGE CITY PARK II's builder has filed on MahaRERA, the official one, is 1 February 2023, already 12 months later than the 1 February 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ORANGE CITY PARK II extended?
According to GharKundli's check of MahaRERA records (updated November 2026), ORANGE CITY PARK II's builder applied to MahaRERA to extend the completion date once: to 1 February 2023, giving the reason "There is a revision in Building Plans and as a result 7 additional flats will be constructed. The necessary sanction from Development Authority viz. NMRDA is obtained, copy of which is attached herewith. Hence additional time required for completing additional execution as per revised Sanction Plan.".
What is the RERA number of ORANGE CITY PARK II?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ORANGE CITY PARK II in Yerkheda, Nagpur is P50500017849.
Is ORANGE CITY PARK II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ORANGE CITY PARK II is registered as P50500017849 and its status is "Completed".
What is the construction status of ORANGE CITY PARK II?
According to GharKundli's check of MahaRERA records (updated November 2026), ORANGE CITY PARK II's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does ORANGE CITY PARK II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is ORANGE CITY PARK II safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ORANGE CITY PARK II is registered on MahaRERA as P50500017849, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does ORANGE CITY PARK II have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: ORANGE CITY PARK III (P50500023595, possession 26 Sep 2025). Check that your agreement names the registration of your own wing.
How can I get updates if ORANGE CITY PARK II's possession date changes?
The latest dates are on ORANGE CITY PARK II's MahaRERA page (P50500017849). GharKundli's Kundli Watch sends a free WhatsApp update on ORANGE CITY PARK II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ORANGE CITY PARK II have?
According to GharKundli's check of MahaRERA records (updated November 2026), ORANGE CITY PARK II has 5 buildings filed: DEFFODIL with 6 floors; ERICA with 6 floors; FREESIA with 6 floors; GARDENIA with 6 floors; HIBISCUS with 6 floors.
How big is the land of ORANGE CITY PARK II?
According to GharKundli's check of MahaRERA records (updated November 2026), ORANGE CITY PARK II stands on 3,345 sq m of land (about 0.8 acres), with 4,659 sq m of sanctioned built-up area.
Where can I read reviews of ORANGE CITY PARK II?
Google Maps has reviews of ORANGE CITY PARK II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ORANGE CITY PARK II?
ORANGE CITY PARK II by MAITREYA DEVELOPERS is in Yerkheda, Nagpur (pincode 441002), Maharashtra, and is registered on MahaRERA as P50500017849, per GharKundli's check of MahaRERA records. Its boundaries filed there include NATIONAL HIGHWAY NO 7, LOKVIHAR ORANGE CITY PARK I.
How many homes are in ORANGE CITY PARK II?
According to GharKundli's check of MahaRERA records (updated November 2026), ORANGE CITY PARK II has 84 homes in 5 towers registered on MahaRERA.
When was ORANGE CITY PARK II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ORANGE CITY PARK II was registered on MahaRERA on 24 September 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on ORANGE CITY PARK II?
No court cases are listed for ORANGE CITY PARK II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ORANGE CITY PARK II?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAITREYA DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ORANGE CITY PARK II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kamptee
Other projects by MAITREYA DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.