GOLDEN PARK

by SHRI OM SAI BUILDERS AND DEVELOPERS · Rui, Nagpur

Registered on MahaRERA under P50500027531, and currently active. Its completion date has moved from June 2024 to April 2027: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on GOLDEN PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500027531
Status
Registered and active
Builder
SHRI OM SAI BUILDERS AND DEVELOPERS
Location
Rui, Nagpur · 441108
Project type
Plotted
Registered on
14 Dec 2020
Completion date at registration
June 2024
Latest completion date
April 2027
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Kundli Watch

GOLDEN PARK: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about GOLDEN PARK

Is GOLDEN PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOLDEN PARK is registered as P50500027531 and its status is "Registered and active".

Where is GOLDEN PARK?

GOLDEN PARK by SHRI OM SAI BUILDERS AND DEVELOPERS is in Rui, Nagpur (pincode 441108), Maharashtra, and is registered on MahaRERA as P50500027531, per GharKundli's check of MahaRERA records.

When is possession of GOLDEN PARK due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GOLDEN PARK in Rui, Nagpur is 30 April 2027 — 30 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Does GOLDEN PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of GOLDEN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRI OM SAI BUILDERS AND DEVELOPERS.

All projects with possession due in 2027 in Nagpur →

Other projects in pincode 441108

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.