Happy Galaxy
by Happy Spaces · Bori S.O (Nagpur), Nagpur
Possession date of Happy Galaxy: 31 July 2027, moved from 15 July 2026 (8 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500052402, and currently active. Its completion date has moved from July 2026 to July 2027: 8 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Happy Galaxy?
How the possession date of Happy Galaxy has moved
15 July 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA01072621653)
Reason the builder gave MahaRERA:
“We, Happy Spaces, are promoter of the project Happy Galaxy, registered under MahaRERA vide registration number P50500052402. Sir the foresaid project was projected to be completed by 15/07/2026 but due to lesser response in bookings and tec…” Read the full reason
“We, Happy Spaces, are promoter of the project Happy Galaxy, registered under MahaRERA vide registration number P50500052402. Sir the foresaid project was projected to be completed by 15/07/2026 but due to lesser response in bookings and technical problems raised in the project the project is now bound to be delayed. The project till date is about 100% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 86 units in the project, we have sold 11 units. Out of which 06 have already given their consent for extension of the proj…”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Happy Galaxy’s extension records on MahaRERA (P50500052402), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Happy Galaxy
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500052402
- Status
- Registered and active
- Builder
- Happy Spaces
- Location
- Bori S.O (Nagpur), Nagpur · 441108
- Project type
- Residential / Group Housing
- Registered on
- 21 Aug 2023
- Completion date at registration
- July 2026
- Latest completion date
- July 2027
- Delay so far
- 8 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 86
- Sold or booked
- 13%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Happy Galaxy, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Happy Galaxy | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Happy Galaxy: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Happy Galaxy every month.
Happy Galaxy: buildings, flats and land, as filed on MahaRERA
- Buildings: Happy Galaxy (12 floors, 86 units)
- Land: 3,579 sq m (about 0.9 acres) · sanctioned built-up 10,785 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Happy Galaxy →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Happy Galaxy: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Happy Galaxy
What is the possession date of Happy Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Happy Galaxy in Bori S.O (Nagpur), Nagpur is 31 July 2027 — 8 months later than 15 July 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Happy Galaxy?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Happy Galaxy's builder has filed on MahaRERA, the official one, is 31 July 2027, already 8 months later than the 15 July 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Happy Galaxy extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Happy Galaxy's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "We, Happy Spaces, are promoter of the project Happy Galaxy, registered under MahaRERA vide registration number P50500052402. Sir the foresaid project was projected to be completed by 15/07/2026 but due to lesser response in bookings and technical problems raised in the project the project is now bound to be delayed. The project till date is about 100% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 86 units in the project, we have sold 11 units. Out of which 06 have already given their consent for extension of the proj…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Happy Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Happy Galaxy in Bori S.O (Nagpur), Nagpur is P50500052402.
Is Happy Galaxy registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Happy Galaxy is registered as P50500052402 and its status is "Registered and active".
What is the construction status of Happy Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), Happy Galaxy's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Happy Galaxy is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Happy Galaxy have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Happy Galaxy safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Happy Galaxy is registered on MahaRERA as P50500052402, its completion date has moved 8 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Happy Galaxy's possession date changes?
The latest dates are on Happy Galaxy's MahaRERA page (P50500052402). GharKundli's Kundli Watch sends a free WhatsApp update on Happy Galaxy every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Happy Galaxy have?
According to GharKundli's check of MahaRERA records (updated October 2026), Happy Galaxy has one building filed: Happy Galaxy with 12 floors and 86 units.
How big is the land of Happy Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), Happy Galaxy stands on 3,579 sq m of land (about 0.9 acres), with 10,785 sq m of sanctioned built-up area.
Where can I read reviews of Happy Galaxy?
Google Maps has reviews of Happy Galaxy written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Happy Galaxy?
Happy Galaxy by Happy Spaces is in Bori S.O (Nagpur), Nagpur (pincode 441108), Maharashtra, and is registered on MahaRERA as P50500052402, per GharKundli's check of MahaRERA records.
How many homes are in Happy Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), Happy Galaxy has 86 homes in 1 tower registered on MahaRERA, and 13% of them are sold or booked.
When was Happy Galaxy registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Happy Galaxy was registered on MahaRERA on 21 August 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Happy Galaxy?
No court cases are listed for Happy Galaxy on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Happy Galaxy?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Happy Spaces, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Happy Galaxy
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nagpur →
Other projects in pincode 441108
- SHREE SAI MANI NAGARI
- CENTRAL COST CITY
- Nivaasa Retreat
- PEAK ORCHARD ESTATE
- SHREE LAXMI VISION CITY
- SWASTIK IMPERIAL
- MAHALAXMI NAGAR 51 ANAYA
- DEV BHUMI
Other projects by Happy Spaces
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.