CENTRAL COST CITY
by M/S 4 PILLARS ORANGE (Ozen) · Kharsoli Village Road, Nagpur
Possession date of CENTRAL COST CITY: 30 April 2032, moved from 31 December 2025 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500049172, and currently active. Its completion date has moved from December 2025 to April 2032: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about CENTRAL COST CITY?
How the possession date of CENTRAL COST CITY has moved
31 December 2025
Completion date given when the project was registered
31 December 2031
Extended at the builder's request (MahaRERA application EA19022619902)
Reason the builder gave MahaRERA:
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of…” Read the full reason
“Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…”30 April 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: CENTRAL COST CITY’s extension records on MahaRERA (P50500049172), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CENTRAL COST CITY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500049172
- Status
- Registered and active
- Builder
- M/S 4 PILLARS ORANGE
- Location
- Kharsoli Village Road, Nagpur · 441108
- Project type
- Plotted
- Registered on
- 3 Feb 2023
- Completion date at registration
- December 2025
- Latest completion date
- April 2032
- Delay so far
- 72 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
CENTRAL COST CITY: buildings, flats and land, as filed on MahaRERA
- Land: 31,843 sq m (about 7.9 acres) · sanctioned built-up 1 sq m · recreational space 7,044 sq m
The builder’s record and reviews
Ozen Buildcon (a group of 4 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 5 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA.
Read Google reviews of CENTRAL COST CITY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CENTRAL COST CITY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CENTRAL COST CITY
What is the possession date of CENTRAL COST CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CENTRAL COST CITY in Kharsoli Village Road, Nagpur is 30 April 2032 — 72 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for CENTRAL COST CITY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CENTRAL COST CITY's builder has filed on MahaRERA, the official one, is 30 April 2032, already 72 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CENTRAL COST CITY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), CENTRAL COST CITY's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "Shortage of Funds due to low demand: The real estate project, situated in a remote area, has faced significant challenges due to limited customer bookings, resulting in a lower-than-anticipated response from prospective buyers. This lack of adequate buyer interest adversely impacted the financial inflow required for the timely completion of the project, as the anticipated funding from customer bookings could not be realized. Despite these challenges, the promoters have demonstrated unwavering commitment to the project's completion by arranging the necessary funds through the liquidation of…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of CENTRAL COST CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CENTRAL COST CITY in Kharsoli Village Road, Nagpur is P50500049172.
Is CENTRAL COST CITY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CENTRAL COST CITY is registered as P50500049172 and its status is "Registered and active".
What is the construction status of CENTRAL COST CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), CENTRAL COST CITY's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does CENTRAL COST CITY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is CENTRAL COST CITY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), CENTRAL COST CITY is registered on MahaRERA as P50500049172, its completion date has moved 72 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if CENTRAL COST CITY's possession date changes?
The latest dates are on CENTRAL COST CITY's MahaRERA page (P50500049172). GharKundli's Kundli Watch sends a free WhatsApp update on CENTRAL COST CITY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of CENTRAL COST CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), CENTRAL COST CITY stands on 31,843 sq m of land (about 7.9 acres), with 1 sq m of sanctioned built-up area and 7,044 sq m of recreational open space.
What is the track record of CENTRAL COST CITY's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ozen Buildcon (a group of 4 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 5 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of CENTRAL COST CITY?
Google Maps has reviews of CENTRAL COST CITY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CENTRAL COST CITY?
CENTRAL COST CITY by M/S 4 PILLARS ORANGE (Ozen) is in Kharsoli Village Road, Nagpur (pincode 441108), Maharashtra, and is registered on MahaRERA as P50500049172, per GharKundli's check of MahaRERA records.
When was CENTRAL COST CITY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CENTRAL COST CITY was registered on MahaRERA on 3 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on CENTRAL COST CITY?
No court cases are listed for CENTRAL COST CITY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of CENTRAL COST CITY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S 4 PILLARS ORANGE, the company Ozen files this project under.
Check it yourself on MahaRERA
- How to check the possession date of CENTRAL COST CITY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 441108
- SHREE SAI MANI NAGARI
- Nivaasa Retreat
- Happy Galaxy
- PEAK ORCHARD ESTATE
- SHREE LAXMI VISION CITY
- SWASTIK IMPERIAL
- MAHALAXMI NAGAR 51 ANAYA
- DEV BHUMI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.