Skip to content
GharKundli

PEAK ORCHARD ESTATE

by H R ASSOCIATES · Vela Harichandra, Nagpur

Possession date of PEAK ORCHARD ESTATE: 30 July 2027, moved from 31 March 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500054813, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about PEAK ORCHARD ESTATE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PEAK ORCHARD ESTATE has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 30 March 2027

    Extended at the builder's request (MahaRERA application EA01042620531)

    Reason the builder gave MahaRERA: “GARDEN WORK PENDING”
  3. 30 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PEAK ORCHARD ESTATE’s extension records on MahaRERA (P50500054813), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PEAK ORCHARD ESTATE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500054813
Status
Registered and active
Builder
H R ASSOCIATES
Location
Vela Harichandra, Nagpur · 441108
Project type
Plotted
Registered on
12 Feb 2024
Completion date at registration
March 2026
Latest completion date
July 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

PEAK ORCHARD ESTATE: buildings, flats and land, as filed on MahaRERA

  • Land: 18,501 sq m (about 4.6 acres) · recreational space 1,850 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PEAK ORCHARD ESTATE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PEAK ORCHARD ESTATE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PEAK ORCHARD ESTATE

What is the possession date of PEAK ORCHARD ESTATE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PEAK ORCHARD ESTATE in Vela Harichandra, Nagpur is 30 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PEAK ORCHARD ESTATE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PEAK ORCHARD ESTATE's builder has filed on MahaRERA, the official one, is 30 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PEAK ORCHARD ESTATE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PEAK ORCHARD ESTATE's builder applied to MahaRERA to extend the completion date once: to 30 March 2027, giving the reason "GARDEN WORK PENDING". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of PEAK ORCHARD ESTATE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PEAK ORCHARD ESTATE in Vela Harichandra, Nagpur is P50500054813.

Is PEAK ORCHARD ESTATE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PEAK ORCHARD ESTATE is registered as P50500054813 and its status is "Registered and active".

What is the construction status of PEAK ORCHARD ESTATE?

According to GharKundli's check of MahaRERA records (updated October 2026), PEAK ORCHARD ESTATE's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does PEAK ORCHARD ESTATE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is PEAK ORCHARD ESTATE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PEAK ORCHARD ESTATE is registered on MahaRERA as P50500054813, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PEAK ORCHARD ESTATE's possession date changes?

The latest dates are on PEAK ORCHARD ESTATE's MahaRERA page (P50500054813). GharKundli's Kundli Watch sends a free WhatsApp update on PEAK ORCHARD ESTATE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of PEAK ORCHARD ESTATE?

According to GharKundli's check of MahaRERA records (updated October 2026), PEAK ORCHARD ESTATE stands on 18,501 sq m of land (about 4.6 acres) and 1,850 sq m of recreational open space.

Where can I read reviews of PEAK ORCHARD ESTATE?

Google Maps has reviews of PEAK ORCHARD ESTATE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PEAK ORCHARD ESTATE?

PEAK ORCHARD ESTATE by H R ASSOCIATES is in Vela Harichandra, Nagpur (pincode 441108), Maharashtra, and is registered on MahaRERA as P50500054813, per GharKundli's check of MahaRERA records.

When was PEAK ORCHARD ESTATE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PEAK ORCHARD ESTATE was registered on MahaRERA on 12 February 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on PEAK ORCHARD ESTATE?

No court cases are listed for PEAK ORCHARD ESTATE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of PEAK ORCHARD ESTATE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is H R ASSOCIATES.

All projects with possession due in 2027 in Nagpur →

Other projects in Nagpur (Rural)

All 307 projects in Bori (441108) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.