Vasavi 4
by Vasavi Developers · Bramhapuri, Chandrapur
Possession: Vasavi 4 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50900031338. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Vasavi 4?
How the possession date of Vasavi 4 has moved
31 July 2022
Completion date given when the project was registered
31 July 2023
Extended at the builder's request (MahaRERA application EXT50900016538)
Reason the builder gave MahaRERA: “We are waiting for the receipt of occupancy certificate which was applied on 28/06/2022 and we expect to receive it in coming two months. Hence we are applying for Extension till we receive the occupancy certificate.”
31 July 2024
Extended at the builder's request (MahaRERA application EXT50900017289)
Reason the builder gave MahaRERA: “Applied for Occupancy Certificate with the Appropriate Authority. Waiting for Receipt of the same.”
Source: Vasavi 4’s extension records on MahaRERA (P50900031338), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vasavi 4
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50900031338
- Status
- Completed
- Builder
- Vasavi Developers
- Location
- Bramhapuri, Chandrapur · 441206
- Project type
- Others
- Registered on
- 23 Oct 2021
- Completion date at registration
- July 2022
- Latest completion date
- July 2024
- Delay so far
- 24 months
- Homes
- 20
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Vasavi 4, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vasavi 4 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vasavi 4 every month.
Vasavi 4: buildings, flats and land, as filed on MahaRERA
- Buildings: Vasavi 4 (5 floors)
- Land: 657 sq m (about 0.2 acres) · sanctioned built-up 1,469 sq m
- Boundaries filed include: Bramhapuri Chandgaon Road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Vasavi 4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vasavi 4: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vasavi 4
What is the possession date of Vasavi 4?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vasavi 4 in Bramhapuri, Chandrapur is 31 July 2024 — 24 months later than 31 July 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Vasavi 4?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vasavi 4's builder has filed on MahaRERA, the official one, is 31 July 2024, already 24 months later than the 31 July 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vasavi 4 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Vasavi 4's builder applied to MahaRERA to extend the completion date 2 times: to 31 July 2023, giving the reason "We are waiting for the receipt of occupancy certificate which was applied on 28/06/2022 and we expect to receive it in coming two months. Hence we are applying for Extension till we receive the occupancy certificate."; to 31 July 2024, giving the reason "Applied for Occupancy Certificate with the Appropriate Authority. Waiting for Receipt of the same.".
What is the RERA number of Vasavi 4?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vasavi 4 in Bramhapuri, Chandrapur is P50900031338.
Is Vasavi 4 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Vasavi 4 is registered as P50900031338 and its status is "Completed".
What is the construction status of Vasavi 4?
According to GharKundli's check of MahaRERA records (updated November 2026), Vasavi 4's status on MahaRERA is "Completed". As filed by the builder, slab work on Vasavi 4 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Vasavi 4 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Vasavi 4 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Vasavi 4 is registered on MahaRERA as P50900031338, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Vasavi 4's possession date changes?
The latest dates are on Vasavi 4's MahaRERA page (P50900031338). GharKundli's Kundli Watch sends a free WhatsApp update on Vasavi 4 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vasavi 4 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Vasavi 4 has one building filed: Vasavi 4 with 5 floors.
How big is the land of Vasavi 4?
According to GharKundli's check of MahaRERA records (updated November 2026), Vasavi 4 stands on 657 sq m of land (about 0.2 acres), with 1,469 sq m of sanctioned built-up area.
Where can I read reviews of Vasavi 4?
Google Maps has reviews of Vasavi 4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vasavi 4?
Vasavi 4 by Vasavi Developers is in Bramhapuri, Chandrapur (pincode 441206), Maharashtra, and is registered on MahaRERA as P50900031338, per GharKundli's check of MahaRERA records. Its boundaries filed there include Bramhapuri Chandgaon Road.
How many homes are in Vasavi 4?
According to GharKundli's check of MahaRERA records (updated November 2026), Vasavi 4 has 20 homes in 1 tower registered on MahaRERA.
When was Vasavi 4 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Vasavi 4 was registered on MahaRERA on 23 October 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Vasavi 4?
No court cases are listed for Vasavi 4 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Vasavi 4?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Vasavi Developers, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vasavi 4
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 441206
All 21 projects in Bramhapuri (441206) →Other projects by Vasavi Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.