MANTHAN PARK

by UNITED BUILDCON · Nanded

Possession date of MANTHAN PARK: 31 July 2029, moved from 30 September 2022 (78 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51100026409, and currently active. Its completion date has moved from September 2022 to July 2029: 78 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MANTHAN PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MANTHAN PARK has moved

  1. 30 September 2022

    Completion date given when the project was registered

  2. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51100012620)

    Reason the builder gave MahaRERA: “WE HAVE FACED LABOUR PROBLEM DUE TO CORONA AND RAIN. WE HAVE NOT ACCEPTED ANY BOOKING TILL DATE AS WE WERE NOT SURE ABOUT THE MARKET DUE TO COVID. NOW WE ARE READY TO ACCEPT BOOKING AND COMPLETE THE PROJECT WITHIN PROPOSED TIME LIMIT.”
  3. 31 March 2029

    Extended at the builder's request (MahaRERA application EXT51100028099)

    Reason the builder gave MahaRERA:
    “The delay in completion of the Manthan Park project (RERA Reg. No. P51100026409) occurred due to multiple unforeseen and uncontrollable circumstances, including the delayed receipt of the Commencement Certificate for Buildings VAISHNAVI (C1…” Read the full reason“The delay in completion of the Manthan Park project (RERA Reg. No. P51100026409) occurred due to multiple unforeseen and uncontrollable circumstances, including the delayed receipt of the Commencement Certificate for Buildings VAISHNAVI (C1 & C2) and YASH (D1 & D2), which was issued only on 08.01.2024 due to regulatory changes under the UDCPR that required revised FSI calculations, plan modifications, and re-approvals. The project was further affected by legal litigation related to the project land, during which construction activities had to be paused or slowed to maintain legal compliance…”
  4. 31 July 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MANTHAN PARK’s extension records on MahaRERA (P51100026409), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MANTHAN PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the July 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51100026409
Status
Registered and active
Builder
UNITED BUILDCON
Location
Nanded · 431601
Project type
Residential / Group Housing
Registered on
17 Sep 2020
Completion date at registration
September 2022
Latest completion date
July 2029
Delay so far
78 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
174
Sold or booked
68%
Towers
4
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of MANTHAN PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BHAGYASHREE100%100%100%100%
PRAGATI100%100%100%100%
VAISHANVI100%100%100%20%
YASH100%100%50%10%

Commencement certificate (CC), as filed on MahaRERA

  • BHAGYASHREE: covers 6 floors
  • PRAGATI: covers 6 floors
  • VAISHANVI: covers 7 floors
  • YASH: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MANTHAN PARK every month.

MANTHAN PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: BHAGYASHREE (7 floors, 40 units) · PRAGATI (7 floors, 40 units) · VAISHANVI (7 floors, 47 units) · YASH (7 floors, 47 units)
  • Land: 8,000 sq m (about 2.0 acres) · sanctioned built-up 10,206 sq m · recreational space 800 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MANTHAN PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MANTHAN PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MANTHAN PARK

What is the possession date of MANTHAN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MANTHAN PARK in Nanded is 31 July 2029 — 78 months later than 30 September 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MANTHAN PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MANTHAN PARK's builder has filed on MahaRERA, the official one, is 31 July 2029, already 78 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MANTHAN PARK extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN PARK's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2025, giving the reason "WE HAVE FACED LABOUR PROBLEM DUE TO CORONA AND RAIN. WE HAVE NOT ACCEPTED ANY BOOKING TILL DATE AS WE WERE NOT SURE ABOUT THE MARKET DUE TO COVID. NOW WE ARE READY TO ACCEPT BOOKING AND COMPLETE THE PROJECT WITHIN PROPOSED TIME LIMIT."; to 31 March 2029, giving the reason "The delay in completion of the Manthan Park project (RERA Reg. No. P51100026409) occurred due to multiple unforeseen and uncontrollable circumstances, including the delayed receipt of the Commencement Certificate for Buildings VAISHNAVI (C1 & C2) and YASH (D1 & D2), which was issued only on 08.01.2024 due to regulatory changes under the UDCPR that required revised FSI calculations, plan modifications, and re-approvals. The project was further affected by legal litigation related to the project land, during which construction activities had to be paused or slowed to maintain legal compliance…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MANTHAN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MANTHAN PARK in Nanded is P51100026409.

Is MANTHAN PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN PARK is registered as P51100026409 and its status is "Registered and active".

What is the construction status of MANTHAN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does MANTHAN PARK have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MANTHAN PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN PARK is registered on MahaRERA as P51100026409, its completion date has moved 78 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MANTHAN PARK's possession date changes?

The latest dates are on MANTHAN PARK's MahaRERA page (P51100026409). GharKundli's Kundli Watch sends a free WhatsApp update on MANTHAN PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MANTHAN PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN PARK has 4 buildings filed: BHAGYASHREE with 7 floors and 40 units; PRAGATI with 7 floors and 40 units; VAISHANVI with 7 floors and 47 units; YASH with 7 floors and 47 units.

How big is the land of MANTHAN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN PARK stands on 8,000 sq m of land (about 2.0 acres), with 10,206 sq m of sanctioned built-up area and 800 sq m of recreational open space.

Where can I read reviews of MANTHAN PARK?

Google Maps has reviews of MANTHAN PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MANTHAN PARK?

MANTHAN PARK by UNITED BUILDCON is in Nanded (pincode 431601), Maharashtra, and is registered on MahaRERA as P51100026409, per GharKundli's check of MahaRERA records.

How many homes are in MANTHAN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN PARK has 174 homes in 4 towers registered on MahaRERA, and 68% of them are sold or booked.

When was MANTHAN PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN PARK was registered on MahaRERA on 17 September 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on MANTHAN PARK?

No court cases are listed for MANTHAN PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MANTHAN PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is UNITED BUILDCON, which has 1 other project registered on MahaRERA.

All projects with possession due in 2029 in Nanded →

Other projects in Nanded

All 7 projects in Nanded (431601) →

Other projects by UNITED BUILDCON

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.