Possession date of KRISHNA SUMAN: 30 January 2027, moved from 30 June 2026 (3 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51400077311, and currently active. Its completion date has moved from June 2026 to January 2027: 3 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about KRISHNA SUMAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KRISHNA SUMAN has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 September 2026

    Extended at the builder's request (MahaRERA application EA18072621790)

    Reason the builder gave MahaRERA: “Delay in Supply of Vitrified Tiles due to Irregular Gas supply to tiles factories in Morbi”
  3. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: KRISHNA SUMAN’s extension records on MahaRERA (P51400077311), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KRISHNA SUMAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51400077311
Status
Registered and active
Builder
Krishna Suman
Location
Suman Residency, Jalna · 431203
Project type
Residential / Group Housing
Registered on
6 Aug 2024
Completion date at registration
June 2026
Latest completion date
January 2027
Delay so far
3 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
56
Sold or booked
11%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of KRISHNA SUMAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A100%100%80%0%
B100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • A: covers 8 floors
  • B: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KRISHNA SUMAN every month.

KRISHNA SUMAN: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Krishna Heights (a group of 3 linked companies) has 4 projects on MahaRERA since 2024, this one included. Of the 3 GharKundli has checked: 3 still being built, 1 past the promised date. No complaints on MahaRERA.

Read Google reviews of KRISHNA SUMAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KRISHNA SUMAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KRISHNA SUMAN

What is the possession date of KRISHNA SUMAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KRISHNA SUMAN in Suman Residency, Jalna is 30 January 2027 — 3 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for KRISHNA SUMAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KRISHNA SUMAN's builder has filed on MahaRERA, the official one, is 30 January 2027, already 3 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KRISHNA SUMAN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SUMAN's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "Delay in Supply of Vitrified Tiles due to Irregular Gas supply to tiles factories in Morbi". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of KRISHNA SUMAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KRISHNA SUMAN in Suman Residency, Jalna is P51400077311.

Is KRISHNA SUMAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SUMAN is registered as P51400077311 and its status is "Registered and active".

What is the construction status of KRISHNA SUMAN?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SUMAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does KRISHNA SUMAN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is KRISHNA SUMAN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SUMAN is registered on MahaRERA as P51400077311, its completion date has moved 3 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KRISHNA SUMAN's possession date changes?

The latest dates are on KRISHNA SUMAN's MahaRERA page (P51400077311). GharKundli's Kundli Watch sends a free WhatsApp update on KRISHNA SUMAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KRISHNA SUMAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SUMAN has 2 buildings filed: A with 8 floors and 36 units; B with 7 floors and 20 units.

How big is the land of KRISHNA SUMAN?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SUMAN stands on 2,923 sq m of land (about 0.7 acres), with 7,310 sq m of sanctioned built-up area.

What is the track record of KRISHNA SUMAN's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishna Heights (a group of 3 linked companies) has 4 projects on MahaRERA since 2024, this one included. Of the 3 GharKundli has checked: 3 still being built, 1 past the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of KRISHNA SUMAN?

Google Maps has reviews of KRISHNA SUMAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KRISHNA SUMAN?

KRISHNA SUMAN by Krishna Suman is in Suman Residency, Jalna (pincode 431203), Maharashtra, and is registered on MahaRERA as P51400077311, per GharKundli's check of MahaRERA records.

How many homes are in KRISHNA SUMAN?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SUMAN has 56 homes in 2 towers registered on MahaRERA, and 11% of them are sold or booked.

When was KRISHNA SUMAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA SUMAN was registered on MahaRERA on 6 August 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on KRISHNA SUMAN?

No court cases are listed for KRISHNA SUMAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of KRISHNA SUMAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Krishna Suman.

All projects with possession due in 2027 in Jalna →

Other projects in Jalna

All 19 projects in Jalna (431203) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.