Kundalwal RAGA ALTIS Phase II
by KUNDALWAL AND GROUP · Padampura, Aurangabad 431001Registered on MahaRERA as “RAGA ALTIS Phase II”
What’s in the report? →Possession date of Kundalwal RAGA ALTIS Phase II (MahaRERA P51500006535): 30 May 2022, moved from 5 November 2020 (18 months later), and it has already passed. It has 62 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500006535. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51500006535, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (May 2022) has passed.
What do you want to know about Kundalwal RAGA ALTIS Phase II?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Kundalwal RAGA ALTIS Phase II has moved
5 November 2020
Completion date given when the project was registered
30 November 2021
Extended at the builder's request (MahaRERA application EXT51500006195)
Reason the builder gave MahaRERA: “Low Demand and COVID19”
30 May 2022
Revised completion date on MahaRERA
Source: Kundalwal RAGA ALTIS Phase II’s extension records on MahaRERA (P51500006535), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kundalwal RAGA ALTIS Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Raga Altis IIIP51500024119 · possession 30 Jul 2027
- RAGA ALTIS Phase IP51500005691 · possession 5 Nov 2020
- MahaRERA registration
- P51500006535
- Status
- Lapsed (registration period ended)
- Builder
- KUNDALWAL AND GROUP
- Location
- Padampura, Aurangabad · 431001
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- November 2020
- Latest completion date
- May 2022
- Delay so far
- 18 months
- Homes
- 62
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Kundalwal RAGA ALTIS Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| D - BUILDING | 100% | 40% | 5% | 0% |
| E 4, 5 - BUILDING | 100% | 100% | 100% | 90% |
| F - BUILDING | 0% | 0% | 0% | 0% |
| E 1 2 3 - BUILDING | 100% | 100% | 100% | 100% |
| C - BUILDING | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kundalwal RAGA ALTIS Phase II every 1–2 months.
Kundalwal RAGA ALTIS Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: D - BUILDING (9 floors) · E 4, 5 - BUILDING (2 floors) · F - BUILDING (9 floors) · E 1 2 3 - BUILDING (2 floors) · C - BUILDING (9 floors)
- Land: 3,319 sq m (about 0.8 acres) · sanctioned built-up 3,650 sq m
- Boundaries filed include: 12 METER SERVICE ROAD
- Land, as filed: GUT NO 66 67
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Kundalwal RAGA ALTIS Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kundalwal RAGA ALTIS Phase II: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Kundalwal RAGA ALTIS Phase II
What is the possession date of Kundalwal RAGA ALTIS Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kundalwal RAGA ALTIS Phase II in Padampura, Aurangabad is 30 May 2022 — 18 months later than 5 November 2020, the date given at registration. That date has already passed.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Kundalwal RAGA ALTIS Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kundalwal RAGA ALTIS Phase II's builder has filed on MahaRERA, the official one, is 30 May 2022, already 18 months later than the 5 November 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kundalwal RAGA ALTIS Phase II extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II's builder applied to MahaRERA to extend the completion date once: to 30 November 2021, giving the reason "Low Demand and COVID19".
What is the RERA number of Kundalwal RAGA ALTIS Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kundalwal RAGA ALTIS Phase II in Padampura, Aurangabad is P51500006535.
Is Kundalwal RAGA ALTIS Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II is registered as P51500006535 and its status is "Lapsed (registration period ended)".
What is the current construction status of Kundalwal RAGA ALTIS Phase II? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Kundalwal RAGA ALTIS Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Kundalwal RAGA ALTIS Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II is registered on MahaRERA as P51500006535, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Kundalwal RAGA ALTIS Phase II?
Kundalwal RAGA ALTIS Phase II isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Kundalwal RAGA ALTIS Phase II?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Kundalwal RAGA ALTIS Phase II: gharkundli.com/tools/property-cost-calculator
Has Kundalwal RAGA ALTIS Phase II received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 May 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Kundalwal RAGA ALTIS Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 May 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Kundalwal RAGA ALTIS Phase II uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Kundalwal RAGA ALTIS Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Kundalwal RAGA ALTIS Phase II have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Raga Altis III (P51500024119, possession 30 Jul 2027); RAGA ALTIS Phase I (P51500005691, possession 5 Nov 2020). Check that your agreement names the registration of your own wing.
How can I get updates if Kundalwal RAGA ALTIS Phase II's possession date changes?
The latest dates are on Kundalwal RAGA ALTIS Phase II's MahaRERA page (P51500006535). GharKundli's Kundli Watch sends a free WhatsApp update on Kundalwal RAGA ALTIS Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kundalwal RAGA ALTIS Phase II have?
According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II has 5 buildings filed: D - BUILDING with 9 floors; E 4, 5 - BUILDING with 2 floors; F - BUILDING with 9 floors; E 1 2 3 - BUILDING with 2 floors; C - BUILDING with 9 floors.
How big is the land of Kundalwal RAGA ALTIS Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II stands on 3,319 sq m of land (about 0.8 acres), with 3,650 sq m of sanctioned built-up area.
What are the reviews of Kundalwal RAGA ALTIS Phase II?
Google Maps has reviews of Kundalwal RAGA ALTIS Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Kundalwal RAGA ALTIS Phase II?
Kundalwal RAGA ALTIS Phase II by KUNDALWAL AND GROUP is in Padampura, Aurangabad, pincode 431001, Maharashtra, and is registered on MahaRERA as P51500006535, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 METER SERVICE ROAD. Its land is filed as GUT NO 66 67. GharKundli lists all 396 MahaRERA projects in Chhatrapati Sambhajinagar (431001).
How many flats are in Kundalwal RAGA ALTIS Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II has 62 homes in 5 towers registered on MahaRERA.
When was Kundalwal RAGA ALTIS Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kundalwal RAGA ALTIS Phase II was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Does Kundalwal RAGA ALTIS Phase II have any legal issues or court cases?
No court cases are listed for Kundalwal RAGA ALTIS Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Kundalwal RAGA ALTIS Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KUNDALWAL AND GROUP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kundalwal RAGA ALTIS Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Chhatrapati Sambhajinagar (431001)
All 396 projects in Chhatrapati Sambhajinagar (431001) →Other projects by KUNDALWAL AND GROUP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.