ANVAYA
by KUMAR MATUNGA PROJECT LLP · Parel, MumbaiAlso near Matunga, Wadala West, Mahim
Possession date of ANVAYA: 13 November 2024, moved from 30 July 2020 (52 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900003676. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (November 2024) has passed.
What do you want to know about ANVAYA?
How the possession date of ANVAYA has moved
30 July 2020
Completion date given when the project was registered
31 January 2022
Extended at the builder's request (MahaRERA application EXT51900009237)
Reason the builder gave MahaRERA:
“The said project was registered on 06/08/2017 for completion upto 31st July 2019. During the tenure of the project many unexpected hurdles arose which extended the proceedings a bit. Some of the hurdles causing the extension are: 1. Delay i…” Read the full reason
“The said project was registered on 06/08/2017 for completion upto 31st July 2019. During the tenure of the project many unexpected hurdles arose which extended the proceedings a bit. Some of the hurdles causing the extension are: 1. Delay in approvals and permissions from regulators 2. Also due to rains, forcemajeure conditions and unexpected events- COVID19 situation occurring during the period work further got delayed 3. Unexpected Financial Conditions 4. Delay in Loan processing by customers (their banks and financials Institutions), etc For the purpose of Extension, we hereby attach res…”30 July 2023
Extended at the builder's request (MahaRERA application EXT51900012457)
Reason the builder gave MahaRERA: “Construction work is 100% complete. We have applied for Occupation Certificate and fire NoC.”
13 November 2024
Extended at the builder's request (MahaRERA application EA21082502409)
Reason the builder gave MahaRERA: “Getting Occupancy Certificate took time from the respective department. Already recived Full OC dated 13/11/2024.”
Source: ANVAYA’s extension records on MahaRERA (P51900003676), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ANVAYA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900003676
- Status
- Lapsed (registration period ended)
- Builder
- KUMAR MATUNGA PROJECT LLP
- Location
- Parel, Mumbai · 400019
- Project type
- Others
- Registered on
- 6 Aug 2017
- Completion date at registration
- July 2020
- Latest completion date
- November 2024
- Delay so far
- 52 months
- Homes
- 22
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ANVAYA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ANVAYA | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- ANVAYA: covers 19th floor including LMR & OHT
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANVAYA every month.
ANVAYA: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 589 – 1,598 | 20 |
| 1 BHK | 438 – 470 | 2 |
| Shops | 4,611 | 1 |
- Buildings: ANVAYA (28 floors, 23 units)
- Land: 571 sq m (about 0.1 acres) · sanctioned built-up 2,234 sq m
- Boundaries filed include: 50 FT TELANG ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ANVAYA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ANVAYA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ANVAYA
What is the possession date of ANVAYA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANVAYA in Parel, Mumbai is 13 November 2024 — 52 months later than 30 July 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for ANVAYA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ANVAYA's builder has filed on MahaRERA, the official one, is 13 November 2024, already 52 months later than the 30 July 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ANVAYA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ANVAYA's builder applied to MahaRERA to extend the completion date 3 times: to 31 January 2022, giving the reason "The said project was registered on 06/08/2017 for completion upto 31st July 2019. During the tenure of the project many unexpected hurdles arose which extended the proceedings a bit. Some of the hurdles causing the extension are: 1. Delay in approvals and permissions from regulators 2. Also due to rains, forcemajeure conditions and unexpected events- COVID19 situation occurring during the period work further got delayed 3. Unexpected Financial Conditions 4. Delay in Loan processing by customers (their banks and financials Institutions), etc For the purpose of Extension, we hereby attach res…"; to 30 July 2023, giving the reason "Construction work is 100% complete. We have applied for Occupation Certificate and fire NoC."; to 13 November 2024, giving the reason "Getting Occupancy Certificate took time from the respective department. Already recived Full OC dated 13/11/2024.".
What is the RERA number of ANVAYA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ANVAYA in Parel, Mumbai is P51900003676.
Is ANVAYA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANVAYA is registered as P51900003676 and its status is "Lapsed (registration period ended)".
What is the construction status of ANVAYA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANVAYA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ANVAYA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does ANVAYA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ANVAYA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ANVAYA is registered on MahaRERA as P51900003676, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 52 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ANVAYA's possession date changes?
The latest dates are on ANVAYA's MahaRERA page (P51900003676). GharKundli's Kundli Watch sends a free WhatsApp update on ANVAYA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ANVAYA have?
According to GharKundli's check of MahaRERA records (updated October 2026), ANVAYA has one building filed: ANVAYA with 28 floors and 23 units.
What are the flat sizes (carpet area) in ANVAYA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ANVAYA: 2 BHK: 589 to 1598 sq ft carpet (20 homes); 1 BHK: 438 to 470 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of ANVAYA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANVAYA stands on 571 sq m of land (about 0.1 acres), with 2,234 sq m of sanctioned built-up area.
Where can I read reviews of ANVAYA?
Google Maps has reviews of ANVAYA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ANVAYA?
ANVAYA by KUMAR MATUNGA PROJECT LLP is in Parel, Mumbai (pincode 400019), near Matunga, Wadala West, Mahim, Maharashtra, and is registered on MahaRERA as P51900003676, per GharKundli's check of MahaRERA records. Its boundaries filed there include 50 FT TELANG ROAD.
How many homes are in ANVAYA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANVAYA has 22 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was ANVAYA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANVAYA was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ANVAYA?
No court cases are listed for ANVAYA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ANVAYA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KUMAR MATUNGA PROJECT LLP.
Check it yourself on MahaRERA
- How to check the possession date of ANVAYA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Parel
- Pristine Heights
- Lifescapes Glory
- RAJKAMAL PARK
- MARUTI PALATIAL
- Pearl Heights
- Lodha Parel Project
- DHARTI HEIGHTS
- Ruparel Ariana
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.