Patel palms
by ABDUL SAMI PATEL · Chhatrapati Sambhajinagar (MH), Aurangabad
Possession date of Patel palms: 30 September 2025, moved from 30 December 2020 (57 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51500008294. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (September 2025) has passed.
What do you want to know about Patel palms?
How the possession date of Patel palms has moved
30 December 2020
Completion date given when the project was registered
31 March 2025
Extended at the builder's request (MahaRERA application EXT51500011700)
Reason the builder gave MahaRERA: “Lack of Demand and Change by Authority Order.”
30 September 2025
Revised completion date on MahaRERA
Source: Patel palms’s extension records on MahaRERA (P51500008294), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Patel palms
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500008294
- Status
- Lapsed (registration period ended)
- Builder
- ABDUL SAMI PATEL
- Location
- Chhatrapati Sambhajinagar (MH), Aurangabad · 431001
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- September 2025
- Delay so far
- 57 months
- Homes
- 53
- Sold or booked
- 41%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Patel palms, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A1-A8 | 100% | 100% | 100% | 100% |
| A9-A13 | 0% | 0% | 0% | 0% |
| Apartment A | 100% | 100% | 100% | 100% |
| Apartment B | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- A1-A8: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Patel palms every month.
Patel palms: buildings, flats and land, as filed on MahaRERA
- Buildings: A1-A8 (2 floors, 8 units) · A9-A13 (3 floors, 5 units) · Apartment A (6 floors, 20 units) · Apartment B (6 floors, 20 units)
- Car parking: 16 covered, 37 open
- Land: 3,900 sq m (about 1.0 acres) · sanctioned built-up 2,917 sq m · recreational space 983 sq m
- Boundaries filed include: Aurangabad to Jalgaon road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Patel palms →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Patel palms: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Patel palms
What is the possession date of Patel palms?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Patel palms in Chhatrapati Sambhajinagar (MH), Aurangabad is 30 September 2025 — 57 months later than 30 December 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Patel palms?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Patel palms's builder has filed on MahaRERA, the official one, is 30 September 2025, already 57 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Patel palms extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel palms's builder applied to MahaRERA to extend the completion date once: to 31 March 2025, giving the reason "Lack of Demand and Change by Authority Order.".
What is the RERA number of Patel palms?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Patel palms in Chhatrapati Sambhajinagar (MH), Aurangabad is P51500008294.
Is Patel palms registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel palms is registered as P51500008294 and its status is "Lapsed (registration period ended)".
What is the construction status of Patel palms?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel palms's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does Patel palms have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Patel palms safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel palms is registered on MahaRERA as P51500008294, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 57 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Patel palms's possession date changes?
The latest dates are on Patel palms's MahaRERA page (P51500008294). GharKundli's Kundli Watch sends a free WhatsApp update on Patel palms every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Patel palms have?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel palms has 4 buildings filed: A1-A8 with 2 floors and 8 units; A9-A13 with 3 floors and 5 units; Apartment A with 6 floors and 20 units; Apartment B with 6 floors and 20 units.
How much parking does Patel palms have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 16 covered and 37 open car parking spaces for Patel palms.
How big is the land of Patel palms?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel palms stands on 3,900 sq m of land (about 1.0 acres), with 2,917 sq m of sanctioned built-up area and 983 sq m of recreational open space.
Where can I read reviews of Patel palms?
Google Maps has reviews of Patel palms written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Patel palms?
Patel palms by ABDUL SAMI PATEL is in Chhatrapati Sambhajinagar (MH), Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500008294, per GharKundli's check of MahaRERA records. Its boundaries filed there include Aurangabad to Jalgaon road.
How many homes are in Patel palms?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel palms has 53 homes in 4 towers registered on MahaRERA, and 41% of them are sold or booked.
When was Patel palms registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Patel palms was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Patel palms?
No court cases are listed for Patel palms on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Patel palms?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ABDUL SAMI PATEL.
Check it yourself on MahaRERA
- How to check the possession date of Patel palms
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 431001
- SHRIRAM RESIDENCY
- Hira Park
- Kalyani Park Phase II
- SALASAR BLISS
- KRUSHNA ULTIMA
- JAI NILAYA BUILDING B
- Shanta Apartment Swanand Realties
- PRASSANA HIGH CLASS CITY PHASE - I
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.