SAI BAN

by BKT Group · Sundarwadi, Aurangabad

Possession: SAI BAN is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500010316. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SAI BAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI BAN has moved

  1. 31 December 2017

    Completion date given when the project was registered

  2. 30 September 2018

    Extended at the builder's request (MahaRERA application EXT51500000048)

    Reason the builder gave MahaRERA: “Applied for completion but completion certificate not yet received”
  3. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51500017406)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 57.78% allottees for purpose of extension of RERA registration period of the said project.”

Source: SAI BAN’s extension records on MahaRERA (P51500010316), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI BAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500010316
Status
Completed
Builder
BKT Group
Location
Sundarwadi, Aurangabad · 431001
Project type
Residential / Group Housing
Registered on
24 Aug 2017
Completion date at registration
December 2017
Latest completion date
March 2025
Delay so far
87 months
Homes
78
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SAI BAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
abc100%100%100%100%
DE100%100%100%100%
FG100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI BAN every month.

SAI BAN: buildings, flats and land, as filed on MahaRERA

  • Buildings: abc (5 floors) · DE (5 floors) · FG (5 floors)
  • Land: 6,000 sq m (about 1.5 acres) · sanctioned built-up 4,500 sq m · recreational space 600 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI BAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI BAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI BAN

What is the possession date of SAI BAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI BAN in Sundarwadi, Aurangabad is 31 March 2025 — 87 months later than 31 December 2017, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAI BAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI BAN's builder has filed on MahaRERA, the official one, is 31 March 2025, already 87 months later than the 31 December 2017 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI BAN extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BAN's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2018, giving the reason "Applied for completion but completion certificate not yet received"; to 31 March 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 57.78% allottees for purpose of extension of RERA registration period of the said project.".

What is the RERA number of SAI BAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI BAN in Sundarwadi, Aurangabad is P51500010316.

Is SAI BAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BAN is registered as P51500010316 and its status is "Completed".

What is the construction status of SAI BAN?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BAN's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does SAI BAN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAI BAN safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BAN is registered on MahaRERA as P51500010316, its MahaRERA status is "Completed", its completion date has moved 87 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI BAN's possession date changes?

The latest dates are on SAI BAN's MahaRERA page (P51500010316). GharKundli's Kundli Watch sends a free WhatsApp update on SAI BAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI BAN have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BAN has 3 buildings filed: abc with 5 floors; DE with 5 floors; FG with 5 floors.

How big is the land of SAI BAN?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BAN stands on 6,000 sq m of land (about 1.5 acres), with 4,500 sq m of sanctioned built-up area and 600 sq m of recreational open space.

Where can I read reviews of SAI BAN?

Google Maps has reviews of SAI BAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI BAN?

SAI BAN by BKT Group is in Sundarwadi, Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500010316, per GharKundli's check of MahaRERA records.

How many homes are in SAI BAN?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BAN has 78 homes in 3 towers registered on MahaRERA.

When was SAI BAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI BAN was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI BAN?

No court cases are listed for SAI BAN on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAI BAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BKT Group.