Padmanabh Vastushilp
by PADMANABH BUILDERS AND DEVELOPERS · Satara Parisar, Aurangabad 431001Registered on MahaRERA as “VASTUSHILP”
What’s in the report? →Possession date of Padmanabh Vastushilp (MahaRERA P51500016112): 30 June 2023, moved from 30 June 2021 (24 months later), and it has already passed. It has 94 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500016112. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51500016112, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2023) has passed.
What do you want to know about Padmanabh Vastushilp?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Padmanabh Vastushilp has moved
30 June 2021
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT51500010635)
Reason the builder gave MahaRERA: “DELAY DUE TO NON AVAILABILITY OF MATERIAL AND LABOUR BECAUSE OF COVID-19 AND DELAY IN OBTAINING REVISED PERMISSION Required extension til 31st Dec 2022”
30 June 2023
Revised completion date on MahaRERA
Source: Padmanabh Vastushilp’s extension records on MahaRERA (P51500016112), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Padmanabh Vastushilp
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500016112
- Status
- Lapsed (registration period ended)
- Builder
- PADMANABH BUILDERS AND DEVELOPERS
- Location
- Satara Parisar, Aurangabad · 431001
- Project type
- Residential / Group Housing
- Registered on
- 17 Apr 2018
- Completion date at registration
- June 2021
- Latest completion date
- June 2023
- Delay so far
- 24 months
- Homes
- 94
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Padmanabh Vastushilp, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 100% | 100% | 100% |
| BUILDING B | 100% | 100% | 50% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Padmanabh Vastushilp every 1–2 months.
Padmanabh Vastushilp: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (5 floors) · BUILDING B (5 floors)
- Land: 2,666 sq m (about 0.7 acres) · sanctioned built-up 3,956 sq m · recreational space 267 sq m
- Boundaries filed include: DEOLAI TO AURANGABAD ROAD
- Land, as filed: GUT NO 136, SATARA
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Padmanabh Vastushilp →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Padmanabh Vastushilp: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Padmanabh Vastushilp
What is the possession date of Padmanabh Vastushilp?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Padmanabh Vastushilp in Satara Parisar, Aurangabad is 30 June 2023 — 24 months later than 30 June 2021, the date given at registration. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Padmanabh Vastushilp?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Padmanabh Vastushilp's builder has filed on MahaRERA, the official one, is 30 June 2023, already 24 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Padmanabh Vastushilp extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp's builder applied to MahaRERA to extend the completion date once: to 31 December 2022, giving the reason "DELAY DUE TO NON AVAILABILITY OF MATERIAL AND LABOUR BECAUSE OF COVID-19 AND DELAY IN OBTAINING REVISED PERMISSION Required extension til 31st Dec 2022".
What is the RERA number of Padmanabh Vastushilp?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Padmanabh Vastushilp in Satara Parisar, Aurangabad is P51500016112.
Is Padmanabh Vastushilp registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp is registered as P51500016112 and its status is "Lapsed (registration period ended)".
What is the current construction status of Padmanabh Vastushilp? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Padmanabh Vastushilp have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Padmanabh Vastushilp safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp is registered on MahaRERA as P51500016112, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Padmanabh Vastushilp?
Padmanabh Vastushilp isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Padmanabh Vastushilp?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Padmanabh Vastushilp: gharkundli.com/tools/property-cost-calculator
Has Padmanabh Vastushilp received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Padmanabh Vastushilp?
According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Padmanabh Vastushilp uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Padmanabh Vastushilp was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Padmanabh Vastushilp's possession date changes?
The latest dates are on Padmanabh Vastushilp's MahaRERA page (P51500016112). GharKundli's Kundli Watch sends a free WhatsApp update on Padmanabh Vastushilp every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Padmanabh Vastushilp have?
According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp has 2 buildings filed: BUILDING A with 5 floors; BUILDING B with 5 floors.
How big is the land of Padmanabh Vastushilp?
According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp stands on 2,666 sq m of land (about 0.7 acres), with 3,956 sq m of sanctioned built-up area and 267 sq m of recreational open space.
What are the reviews of Padmanabh Vastushilp?
Google Maps has reviews of Padmanabh Vastushilp written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Padmanabh Vastushilp?
Padmanabh Vastushilp by PADMANABH BUILDERS AND DEVELOPERS is in Satara Parisar, Aurangabad, pincode 431001, Maharashtra, and is registered on MahaRERA as P51500016112, per GharKundli's check of MahaRERA records. Its boundaries filed there include DEOLAI TO AURANGABAD ROAD. Its land is filed as GUT NO 136, SATARA. GharKundli lists all 396 MahaRERA projects in Chhatrapati Sambhajinagar (431001).
How many flats are in Padmanabh Vastushilp?
According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp has 94 homes in 2 towers registered on MahaRERA.
When was Padmanabh Vastushilp registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Padmanabh Vastushilp was registered on MahaRERA on 17 April 2018. GharKundli did not find a title report on the land on file there.
Does Padmanabh Vastushilp have any legal issues or court cases?
No court cases are listed for Padmanabh Vastushilp on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Padmanabh Vastushilp?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PADMANABH BUILDERS AND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Padmanabh Vastushilp
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Chhatrapati Sambhajinagar (431001)
- Parshwa Heights
- Hrim Ssky City Phase IV
- Sara Saphire PH - II
- Sara Saphire PH - I
- Brahma Park
- P-9 Villas
- 18 Laxmi Elites
- Signature 27
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.