Possession date of Aurangabad Industrial Trade Centreaitc - (MahaRERA P51500020619): 30 March 2024, and it has already passed. It has 46 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500020619. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51500020619, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (March 2024) has passed.

What do you want to know about Aurangabad Industrial Trade Centreaitc -?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Aurangabad Industrial Trade Centreaitc -

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500020619
Status
Lapsed (registration period ended)
Builder
AURANGABAD INDUSTRIAL TRADE CENTRE PRIVATE LIMITED
Location
Chikalthana MIDC, Aurangabad · 431001
Project type
Mixed
Registered on
26 Apr 2019
Completion date at registration
March 2024
Latest completion date
March 2024
Homes
46
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Aurangabad Industrial Trade Centreaitc -, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AURANGABAD INDUSTRIAL TRADE CENTRE AITC0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aurangabad Industrial Trade Centreaitc - every 1–2 months.

Aurangabad Industrial Trade Centreaitc -: buildings, flats and land, as filed on MahaRERA

  • Buildings: AURANGABAD INDUSTRIAL TRADE CENTRE AITC (2 floors)
  • Land: 1,128 sq m (about 0.3 acres) · sanctioned built-up 1,128 sq m
  • Boundaries filed include: MIDC ROAD 20 MTR WIDE, MIDC ROAD 6 MTR WIDE
  • Land, as filed: P-85
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Aurangabad Industrial Trade Centreaitc - →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aurangabad Industrial Trade Centreaitc -: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aurangabad Industrial Trade Centreaitc -

What is the possession date of Aurangabad Industrial Trade Centreaitc -?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aurangabad Industrial Trade Centreaitc - in Chikalthana MIDC, Aurangabad is 30 March 2024. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Aurangabad Industrial Trade Centreaitc -?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aurangabad Industrial Trade Centreaitc -'s builder has filed on MahaRERA, the official one, is 30 March 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Aurangabad Industrial Trade Centreaitc -?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aurangabad Industrial Trade Centreaitc - in Chikalthana MIDC, Aurangabad is P51500020619.

Is Aurangabad Industrial Trade Centreaitc - registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aurangabad Industrial Trade Centreaitc - is registered as P51500020619 and its status is "Lapsed (registration period ended)".

What is the current construction status of Aurangabad Industrial Trade Centreaitc -? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Aurangabad Industrial Trade Centreaitc -'s status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on AURANGABAD INDUSTRIAL TRADE CENTRE AITC is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Aurangabad Industrial Trade Centreaitc - have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Aurangabad Industrial Trade Centreaitc - safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Aurangabad Industrial Trade Centreaitc - is registered on MahaRERA as P51500020619, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aurangabad Industrial Trade Centreaitc -?

Aurangabad Industrial Trade Centreaitc - isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aurangabad Industrial Trade Centreaitc -?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aurangabad Industrial Trade Centreaitc -: gharkundli.com/tools/property-cost-calculator

Has Aurangabad Industrial Trade Centreaitc - received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Aurangabad Industrial Trade Centreaitc - isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 March 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Aurangabad Industrial Trade Centreaitc -?

According to GharKundli's check of MahaRERA records (updated November 2026), Aurangabad Industrial Trade Centreaitc -'s registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 March 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Aurangabad Industrial Trade Centreaitc - uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Aurangabad Industrial Trade Centreaitc - was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aurangabad Industrial Trade Centreaitc -'s possession date changes?

The latest dates are on Aurangabad Industrial Trade Centreaitc -'s MahaRERA page (P51500020619). GharKundli's Kundli Watch sends a free WhatsApp update on Aurangabad Industrial Trade Centreaitc - every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aurangabad Industrial Trade Centreaitc - have?

According to GharKundli's check of MahaRERA records (updated November 2026), Aurangabad Industrial Trade Centreaitc - has one building filed: AURANGABAD INDUSTRIAL TRADE CENTRE AITC with 2 floors.

How big is the land of Aurangabad Industrial Trade Centreaitc -?

According to GharKundli's check of MahaRERA records (updated November 2026), Aurangabad Industrial Trade Centreaitc - stands on 1,128 sq m of land (about 0.3 acres), with 1,128 sq m of sanctioned built-up area.

What are the reviews of Aurangabad Industrial Trade Centreaitc -?

Google Maps has reviews of Aurangabad Industrial Trade Centreaitc - written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aurangabad Industrial Trade Centreaitc -?

Aurangabad Industrial Trade Centreaitc - by AURANGABAD INDUSTRIAL TRADE CENTRE PRIVATE LIMITED is in Chikalthana MIDC, Aurangabad, pincode 431001, Maharashtra, and is registered on MahaRERA as P51500020619, per GharKundli's check of MahaRERA records. Its boundaries filed there include MIDC ROAD 20 MTR WIDE, MIDC ROAD 6 MTR WIDE. Its land is filed as P-85. GharKundli lists all 396 MahaRERA projects in Chhatrapati Sambhajinagar (431001).

How many flats are in Aurangabad Industrial Trade Centreaitc -?

According to GharKundli's check of MahaRERA records (updated November 2026), Aurangabad Industrial Trade Centreaitc - has 46 homes in 1 tower registered on MahaRERA.

When was Aurangabad Industrial Trade Centreaitc - registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aurangabad Industrial Trade Centreaitc - was registered on MahaRERA on 26 April 2019. GharKundli did not find a title report on the land on file there.

Does Aurangabad Industrial Trade Centreaitc - have any legal issues or court cases?

No court cases are listed for Aurangabad Industrial Trade Centreaitc - on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Aurangabad Industrial Trade Centreaitc -?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AURANGABAD INDUSTRIAL TRADE CENTRE PRIVATE LIMITED.

Other projects in Aurangabad

All 396 projects in Chhatrapati Sambhajinagar (431001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.