ALANKAR BUILDING
by PRASHANT CHANDRAKANT VAIDYA · Matunga, MumbaiAlso near Barc, Wadala, Dadar
Registered on MahaRERA under P51900001301. Status: Completed. Its completion date has moved from October 2021 to April 2023, 18 months later.
Source: GharKundli’s check of MahaRERA records, November 2026.
GharKundli’s full report on ALANKAR BUILDING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900001301
- Status
- Completed
- Builder
- PRASHANT CHANDRAKANT VAIDYA
- Location
- Matunga, Mumbai · 400019
- Project type
- Residential / Group Housing
- Registered on
- 27 Jul 2017
- Completion date at registration
- October 2021
- Latest completion date
- April 2023
- Delay so far
- 18 months
- Homes
- 10
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
ALANKAR BUILDING: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ALANKAR BUILDING
Is ALANKAR BUILDING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ALANKAR BUILDING is registered as P51900001301 and its status is "Completed".
Where is ALANKAR BUILDING?
ALANKAR BUILDING by PRASHANT CHANDRAKANT VAIDYA is in Matunga, Mumbai (pincode 400019), near Barc, Wadala, Dadar, Maharashtra, and is registered on MahaRERA as P51900001301, per GharKundli's check of MahaRERA records.
When is possession of ALANKAR BUILDING due?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ALANKAR BUILDING in Matunga, Mumbai is 30 April 2023 — 18 months later than 30 October 2021, the date given at registration.
Does ALANKAR BUILDING have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
How many homes are in ALANKAR BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), ALANKAR BUILDING has 10 homes in 1 tower registered on MahaRERA.
When was ALANKAR BUILDING registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ALANKAR BUILDING was registered on MahaRERA on 27 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ALANKAR BUILDING?
No court cases are listed for ALANKAR BUILDING on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ALANKAR BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRASHANT CHANDRAKANT VAIDYA.