GULRAJ PARADISE

by M/S RELIABLE CONSTRUCTION · Matunga, MumbaiAlso near Mahim, Dharavi

Possession date of GULRAJ PARADISE: 30 September 2026, moved from 30 June 2021 (63 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800004371. Status: Lapsed (registration period ended). 18 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (September 2026) has passed.

What do you want to know about GULRAJ PARADISE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GULRAJ PARADISE has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800008692)

    Reason the builder gave MahaRERA:
    “DUE TO VERY SLUGGISH REAL ESTATE MARKET AND VERY POOR SALE OF FLATS AND EXTREMELY POOR FUND FLOW OF PROJECT, WE WOULD NOT BE ABLE TO COMPLETE THE PROJECT IN TIME. THEREFORE WE WOULD LIKE TO REQUEST YOU TO PLEASE GRANT US EXTENSION FOR FURTH…” Read the full reason“DUE TO VERY SLUGGISH REAL ESTATE MARKET AND VERY POOR SALE OF FLATS AND EXTREMELY POOR FUND FLOW OF PROJECT, WE WOULD NOT BE ABLE TO COMPLETE THE PROJECT IN TIME. THEREFORE WE WOULD LIKE TO REQUEST YOU TO PLEASE GRANT US EXTENSION FOR FURTHER 12 MONTHS.”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800013484)

    Reason the builder gave MahaRERA:
    “DUE TO VERY SLUGGISH REAL ESTATE MARKET AND VERY POOR SALE OF FLATS AND EXTREMELY POOR FUND FLOW OF PROJECT, WE WOULD NOT BE ABLE TO COMPLETE THE PROJECT IN TIME. THEREFORE WE WOULD LIKE TO REQUEST YOU TO PLEASE GRANT US EXTENSION FOR FURTH…” Read the full reason“DUE TO VERY SLUGGISH REAL ESTATE MARKET AND VERY POOR SALE OF FLATS AND EXTREMELY POOR FUND FLOW OF PROJECT, WE WOULD NOT BE ABLE TO COMPLETE THE PROJECT IN TIME. THEREFORE WE WOULD LIKE TO REQUEST YOU TO PLEASE GRANT US EXTENSION FOR FURTHER TILL 31/12/2023”
  4. 30 September 2024

    Extended at the builder's request (MahaRERA application EXT51800018366)

    Reason the builder gave MahaRERA: “DUE TO COVID 19 NOT ABLE TO COMPELTION PROJECT PLEASE GRANT US EXTENSION TILL 30/09/2024”
  5. 30 September 2025

    Extended at the builder's request (MahaRERA application EXT51800028385)

    Reason the builder gave MahaRERA: “Due to shortage of material and labor we are not able to complete project please grant us extension till 30/09/2025”
  6. 30 September 2026

    Extended at the builder's request (MahaRERA application EA09012619380)

    Reason the builder gave MahaRERA:
    “Due to shortage of raw material and labour there was delay in project completion. The payments from allottees were irregular due to which the cash flow was affected which in turn resulted in delay of the project. There were issues whereby t…” Read the full reason“Due to shortage of raw material and labour there was delay in project completion. The payments from allottees were irregular due to which the cash flow was affected which in turn resulted in delay of the project. There were issues whereby the slum tenant restricted us from entering the site and completing the project on time. Due to the above mentioned reasons there was delay in project completion”

Source: GULRAJ PARADISE’s extension records on MahaRERA (P51800004371), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GULRAJ PARADISE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 18 complaints, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004371
Status
Lapsed (registration period ended)
Builder
M/S RELIABLE CONSTRUCTION
Location
Matunga, Mumbai · 400019
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
June 2021
Latest completion date
September 2026
Delay so far
63 months
Homes
27
Sold or booked
69%
Towers
2
Complaints on MahaRERA
18
Court cases listed
0
Title report on file
Not found

Construction progress of GULRAJ PARADISE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GULRAJ PARADISE WING A B C D - SALE100%91.67%91.3%0%
RATNAMAL TOWER100%91.67%91.3%0%

Commencement certificate (CC), as filed on MahaRERA

  • GULRAJ PARADISE WING A B C D - SALE: covers 12 uppur floor
  • RATNAMAL TOWER: covers 12 upper floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GULRAJ PARADISE every month.

GULRAJ PARADISE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK339 – 36027
Shops30 – 3508
  • Buildings: GULRAJ PARADISE WING A B C D - SALE (25 floors, 16 units) · RATNAMAL TOWER (17 floors, 19 units)
  • Land: 5,693 sq m (about 1.4 acres) · sanctioned built-up 22,166 sq m · recreational space 417 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Reliable Construction (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 lapsed. 49 complaints on MahaRERA across 2 projects.

Read Google reviews of GULRAJ PARADISE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GULRAJ PARADISE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GULRAJ PARADISE

What is the possession date of GULRAJ PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GULRAJ PARADISE in Matunga, Mumbai is 30 September 2026 — 63 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for GULRAJ PARADISE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GULRAJ PARADISE's builder has filed on MahaRERA, the official one, is 30 September 2026, already 63 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GULRAJ PARADISE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GULRAJ PARADISE's builder applied to MahaRERA to extend the completion date 5 times: to 30 June 2022, giving the reason "DUE TO VERY SLUGGISH REAL ESTATE MARKET AND VERY POOR SALE OF FLATS AND EXTREMELY POOR FUND FLOW OF PROJECT, WE WOULD NOT BE ABLE TO COMPLETE THE PROJECT IN TIME. THEREFORE WE WOULD LIKE TO REQUEST YOU TO PLEASE GRANT US EXTENSION FOR FURTHER 12 MONTHS."; to 31 December 2023, giving the reason "DUE TO VERY SLUGGISH REAL ESTATE MARKET AND VERY POOR SALE OF FLATS AND EXTREMELY POOR FUND FLOW OF PROJECT, WE WOULD NOT BE ABLE TO COMPLETE THE PROJECT IN TIME. THEREFORE WE WOULD LIKE TO REQUEST YOU TO PLEASE GRANT US EXTENSION FOR FURTHER TILL 31/12/2023"; to 30 September 2024, giving the reason "DUE TO COVID 19 NOT ABLE TO COMPELTION PROJECT PLEASE GRANT US EXTENSION TILL 30/09/2024"; to 30 September 2025, giving the reason "Due to shortage of material and labor we are not able to complete project please grant us extension till 30/09/2025"; to 30 September 2026, giving the reason "Due to shortage of raw material and labour there was delay in project completion. The payments from allottees were irregular due to which the cash flow was affected which in turn resulted in delay of the project. There were issues whereby the slum tenant restricted us from entering the site and completing the project on time. Due to the above mentioned reasons there was delay in project completion".

What is the RERA number of GULRAJ PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GULRAJ PARADISE in Matunga, Mumbai is P51800004371.

Is GULRAJ PARADISE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GULRAJ PARADISE is registered as P51800004371 and its status is "Lapsed (registration period ended)".

What is the construction status of GULRAJ PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), GULRAJ PARADISE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 91.67% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does GULRAJ PARADISE have complaints on MahaRERA?

18 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is GULRAJ PARADISE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GULRAJ PARADISE is registered on MahaRERA as P51800004371, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 63 months since registration and 18 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GULRAJ PARADISE's possession date changes?

The latest dates are on GULRAJ PARADISE's MahaRERA page (P51800004371). GharKundli's Kundli Watch sends a free WhatsApp update on GULRAJ PARADISE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GULRAJ PARADISE have?

According to GharKundli's check of MahaRERA records (updated October 2026), GULRAJ PARADISE has 2 buildings filed: GULRAJ PARADISE WING A B C D - SALE with 25 floors and 16 units; RATNAMAL TOWER with 17 floors and 19 units.

What are the flat sizes (carpet area) in GULRAJ PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for GULRAJ PARADISE: 1 BHK: 339 to 360 sq ft carpet (27 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of GULRAJ PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), GULRAJ PARADISE stands on 5,693 sq m of land (about 1.4 acres), with 22,166 sq m of sanctioned built-up area and 417 sq m of recreational open space.

What is the track record of GULRAJ PARADISE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Reliable Construction (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 lapsed. 49 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of GULRAJ PARADISE?

Google Maps has reviews of GULRAJ PARADISE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 18 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GULRAJ PARADISE?

GULRAJ PARADISE by M/S RELIABLE CONSTRUCTION is in Matunga, Mumbai (pincode 400019), near Mahim, Dharavi, Maharashtra, and is registered on MahaRERA as P51800004371, per GharKundli's check of MahaRERA records.

How many homes are in GULRAJ PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), GULRAJ PARADISE has 27 homes in 2 towers registered on MahaRERA, and 69% of them are sold or booked.

When was GULRAJ PARADISE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GULRAJ PARADISE was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on GULRAJ PARADISE?

No court cases are listed for GULRAJ PARADISE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of GULRAJ PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S RELIABLE CONSTRUCTION.

All projects with possession due in 2026 in Mumbai City →

Other projects in pincode 400019

All 104 projects in Matunga (400019) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.