Possession: Signare is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900003280. Status: Completed.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Signare?
How the possession date of Signare has moved
31 July 2022
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EA20052621041)
Reason the builder gave MahaRERA: “The project is fully completed, and we have obtained the Full Occupancy Certificate, as we need to apply for Project Closure, we are advised to take and extension and hence to close the project on the RERA portal.”
Source: Signare’s extension records on MahaRERA (P51900003280), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Signare
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900003280
- Status
- Completed
- Builder
- Tejukaya Buildcon
- Location
- Matunga, Mumbai · 400019
- Project type
- Others
- Registered on
- 5 Aug 2017
- Completion date at registration
- July 2022
- Latest completion date
- September 2026
- Delay so far
- 50 months
- Homes
- 15
- Sold or booked
- 67%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Signare, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Signare | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Signare: covers FULL CC is issued up to top of 19th floor + LMR +OHT
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Signare every month.
Signare: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 805 – 838 | 11 |
| 3 BHK | 1,212 – 1,296 | 2 |
| 1 BHK | 747 | 1 |
| 1 Room Kitchen | 313 | 1 |
- Buildings: Signare (25 floors, 15 units)
- Car parking: 1 covered
- Land: 600 sq m (about 0.1 acres) · sanctioned built-up 2,071 sq m
- Boundaries filed include: Dr Babasaheb Ambedkar Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Tejukaya Realty (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 18 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Signare →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Signare: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Signare
What is the possession date of Signare?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Signare in Matunga, Mumbai is 30 September 2026 — 50 months later than 31 July 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Signare?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Signare's builder has filed on MahaRERA, the official one, is 30 September 2026, already 50 months later than the 31 July 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Signare extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Signare's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "The project is fully completed, and we have obtained the Full Occupancy Certificate, as we need to apply for Project Closure, we are advised to take and extension and hence to close the project on the RERA portal.".
What is the RERA number of Signare?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Signare in Matunga, Mumbai is P51900003280.
Is Signare registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Signare is registered as P51900003280 and its status is "Completed".
What is the construction status of Signare?
According to GharKundli's check of MahaRERA records (updated October 2026), Signare's status on MahaRERA is "Completed". As filed by the builder, slab work on Signare is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Signare have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Signare safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Signare is registered on MahaRERA as P51900003280, its MahaRERA status is "Completed", its completion date has moved 50 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Signare's possession date changes?
The latest dates are on Signare's MahaRERA page (P51900003280). GharKundli's Kundli Watch sends a free WhatsApp update on Signare every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Signare have?
According to GharKundli's check of MahaRERA records (updated October 2026), Signare has one building filed: Signare with 25 floors and 15 units.
What are the flat sizes (carpet area) in Signare?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Signare: 2 BHK: 805 to 838 sq ft carpet (11 homes); 3 BHK: 1212 to 1296 sq ft carpet (2 homes); 1 BHK: 747 sq ft carpet (1 homes); 1 Room Kitchen: 313 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Signare have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for Signare.
How big is the land of Signare?
According to GharKundli's check of MahaRERA records (updated October 2026), Signare stands on 600 sq m of land (about 0.1 acres), with 2,071 sq m of sanctioned built-up area.
What is the track record of Signare's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Tejukaya Realty (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 18 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Signare?
Google Maps has reviews of Signare written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Signare?
Signare by Tejukaya Buildcon is in Matunga, Mumbai (pincode 400019), near Dadar East, Wadala west, Hindu Colony, Maharashtra, and is registered on MahaRERA as P51900003280, per GharKundli's check of MahaRERA records. Its boundaries filed there include Dr Babasaheb Ambedkar Road.
How many homes are in Signare?
According to GharKundli's check of MahaRERA records (updated October 2026), Signare has 15 homes in 1 tower registered on MahaRERA, and 67% of them are sold or booked.
When was Signare registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Signare was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Signare?
No court cases are listed for Signare on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Signare?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Tejukaya Buildcon.
Check it yourself on MahaRERA
- How to check the possession date of Signare
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400019
- ANVAYA
- Sheetal Sapphire
- JADE AVENUE-Residential Wing
- RIGVED WINDSONG
- Paramount
- BELLWETHER CASCADE
- OM BUILDING CO-OPERATIVE HOUSING SOCIETY LIMITED
- GULRAJ PARADISE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.