VILLO 67
by CHOUDHARY BHAISHREE LANDMARKS LLP · Itkheda, Aurangabad
Possession date of VILLO 67: 30 April 2028, moved from 30 March 2026 (21 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500024894, and currently active. Its completion date has moved from March 2026 to April 2028: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VILLO 67?
How the possession date of VILLO 67 has moved
30 March 2026
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA25032620367)
Reason the builder gave MahaRERA:
“The Registered Project comprises row house structures. Only certain finishing works remain pending, and the delay in completion is primarily due to the shortage of adequate labour resources. Therefore, we hereby request an extension of the…” Read the full reason
“The Registered Project comprises row house structures. Only certain finishing works remain pending, and the delay in completion is primarily due to the shortage of adequate labour resources. Therefore, we hereby request an extension of the project completion timeline up to 31-12-2027, thereby revising the proposed completion date to 31-12-2027.”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: VILLO 67’s extension records on MahaRERA (P51500024894), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VILLO 67
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500024894
- Status
- Registered and active
- Builder
- CHOUDHARY BHAISHREE LANDMARKS LLP
- Location
- Itkheda, Aurangabad · 431003
- Project type
- Residential / Group Housing
- Registered on
- 9 Mar 2020
- Completion date at registration
- March 2026
- Latest completion date
- April 2028
- Delay so far
- 21 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 64
- Sold or booked
- 80%
- Towers
- 8
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of VILLO 67, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RH NO A 1 TO 9 | 100% | 100% | 100% | 100% |
| RH NO B 10 TO 17 | 100% | 100% | 100% | 100% |
| RH NO C 18 TO 24 | 100% | 100% | 100% | 100% |
| RH NO D 25 TO 32 | 100% | 100% | 100% | 100% |
| RH NO E 33 TO 40 | 100% | 100% | 100% | 100% |
| RH NO F 41 TO 50 | 100% | 100% | 100% | 100% |
| RH NO G 51 TO 59 | 100% | 100% | 100% | 90% |
| RH NO H 60 TO 67 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- RH NO A 1 TO 9: covers 3 floors
- RH NO B 10 TO 17: covers 3 floors
- RH NO C 18 TO 24: covers 3 floors
- RH NO D 25 TO 32: covers 3 floors
- RH NO E 33 TO 40: covers 3 floors
- RH NO F 41 TO 50: covers 3 floors
- RH NO G 51 TO 59: covers 3 floors
- RH NO H 60 TO 67: covers 3 floors
Latest CC order on MahaRERA: dated 27/12/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VILLO 67 every month.
VILLO 67: buildings, flats and land, as filed on MahaRERA
- Buildings: RH NO A 1 TO 9 (3 floors, 9 units) · RH NO B 10 TO 17 (3 floors, 7 units) · RH NO C 18 TO 24 (3 floors, 6 units) · RH NO D 25 TO 32 (3 floors, 8 units) · RH NO E 33 TO 40 (3 floors, 8 units) · RH NO F 41 TO 50 (3 floors, 9 units) · RH NO G 51 TO 59 (3 floors, 9 units) · RH NO H 60 TO 67 (3 floors, 8 units)
- Car parking: 136 covered
- Land: 12,000 sq m (about 3.0 acres) · sanctioned built-up 10,086 sq m · recreational space 1,100 sq m
- Boundaries filed include: ITKHEDA ROAD
The builder’s record and reviews
Choudhary Bhaishree Landmarks (a group of 2 linked companies) has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 3 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of VILLO 67 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VILLO 67: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VILLO 67
What is the possession date of VILLO 67?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VILLO 67 in Itkheda, Aurangabad is 30 April 2028 — 21 months later than 30 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for VILLO 67?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VILLO 67's builder has filed on MahaRERA, the official one, is 30 April 2028, already 21 months later than the 30 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VILLO 67 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VILLO 67's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "The Registered Project comprises row house structures. Only certain finishing works remain pending, and the delay in completion is primarily due to the shortage of adequate labour resources. Therefore, we hereby request an extension of the project completion timeline up to 31-12-2027, thereby revising the proposed completion date to 31-12-2027.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of VILLO 67?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VILLO 67 in Itkheda, Aurangabad is P51500024894.
Is VILLO 67 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VILLO 67 is registered as P51500024894 and its status is "Registered and active".
What is the construction status of VILLO 67?
According to GharKundli's check of MahaRERA records (updated October 2026), VILLO 67's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does VILLO 67 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is VILLO 67 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VILLO 67 is registered on MahaRERA as P51500024894, its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VILLO 67's possession date changes?
The latest dates are on VILLO 67's MahaRERA page (P51500024894). GharKundli's Kundli Watch sends a free WhatsApp update on VILLO 67 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VILLO 67 have?
According to GharKundli's check of MahaRERA records (updated October 2026), VILLO 67 has 8 buildings filed: RH NO A 1 TO 9 with 3 floors and 9 units; RH NO B 10 TO 17 with 3 floors and 7 units; RH NO C 18 TO 24 with 3 floors and 6 units; RH NO D 25 TO 32 with 3 floors and 8 units; RH NO E 33 TO 40 with 3 floors and 8 units; RH NO F 41 TO 50 with 3 floors and 9 units; and 2 more.
How much parking does VILLO 67 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 136 covered car parking spaces for VILLO 67.
How big is the land of VILLO 67?
According to GharKundli's check of MahaRERA records (updated October 2026), VILLO 67 stands on 12,000 sq m of land (about 3.0 acres), with 10,086 sq m of sanctioned built-up area and 1,100 sq m of recreational open space.
What is the track record of VILLO 67's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Choudhary Bhaishree Landmarks (a group of 2 linked companies) has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of VILLO 67?
Google Maps has reviews of VILLO 67 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VILLO 67?
VILLO 67 by CHOUDHARY BHAISHREE LANDMARKS LLP is in Itkheda, Aurangabad (pincode 431003), Maharashtra, and is registered on MahaRERA as P51500024894, per GharKundli's check of MahaRERA records. Its boundaries filed there include ITKHEDA ROAD.
How many homes are in VILLO 67?
According to GharKundli's check of MahaRERA records (updated October 2026), VILLO 67 has 64 homes in 8 towers registered on MahaRERA, and 80% of them are sold or booked.
When was VILLO 67 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VILLO 67 was registered on MahaRERA on 9 March 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on VILLO 67?
No court cases are listed for VILLO 67 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VILLO 67?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CHOUDHARY BHAISHREE LANDMARKS LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of VILLO 67
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Aurangabad →
Other projects in Itkheda
- PARAM SUVARNVASTU
- RAJ ADITYA
- BELMONT
- UDYOG KALPAK C
- BHUMI ADITI VASTU
- FORTUNE SKYLINE
- DEEPNAND RESIDENCY
- JKON BLISS
Other projects by CHOUDHARY BHAISHREE LANDMARKS LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.