by RUDRA CONSTRUCTIONS · Satara Parisar, AurangabadAlso near War, Deohara, Kaler

Possession date of SAEE TOWN: 30 April 2029, moved from 20 January 2026 (35 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500035187, and currently active. Its completion date has moved from January 2026 to April 2029: 35 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAEE TOWN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAEE TOWN has moved

  1. 20 January 2026

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA24032620357)

    Reason the builder gave MahaRERA:
    “We, Rudra Constructions, are promoter of the project Saee Town, registered under MahaRERA vide registration number P51500035187. Sir the foresaid project was projected to be completed by 20/01/2026 but due to road construction & pipeline co…” Read the full reason“We, Rudra Constructions, are promoter of the project Saee Town, registered under MahaRERA vide registration number P51500035187. Sir the foresaid project was projected to be completed by 20/01/2026 but due to road construction & pipeline construction of the area approach road has been damaged problems raised in the project the project is now bound to be delayed. The project till date is about 50.48% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 39 units in the project, we have sold 10 units. Out of which 08 have alre…”
  3. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAEE TOWN’s extension records on MahaRERA (P51500035187), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAEE TOWN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500035187
Status
Registered and active
Builder
RUDRA CONSTRUCTIONS
Location
Satara Parisar, Aurangabad · 431010
Project type
Residential / Group Housing
Registered on
10 May 2022
Completion date at registration
January 2026
Latest completion date
April 2029
Delay so far
35 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
39
Sold or booked
38%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SAEE TOWN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ROW HOUSE70%60%60%60%

Commencement certificate (CC), as filed on MahaRERA

  • ROW HOUSE: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAEE TOWN every month.

SAEE TOWN: buildings, flats and land, as filed on MahaRERA

  • Buildings: ROW HOUSE (4 floors, 39 units)
  • Land: 3,265 sq m (about 0.8 acres) · sanctioned built-up 4,217 sq m · recreational space 326 sq m
  • Boundaries filed include: 9 METER VIDE ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAEE TOWN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAEE TOWN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAEE TOWN

What is the possession date of SAEE TOWN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAEE TOWN in Satara Parisar, Aurangabad is 30 April 2029 — 35 months later than 20 January 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SAEE TOWN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAEE TOWN's builder has filed on MahaRERA, the official one, is 30 April 2029, already 35 months later than the 20 January 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAEE TOWN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAEE TOWN's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "We, Rudra Constructions, are promoter of the project Saee Town, registered under MahaRERA vide registration number P51500035187. Sir the foresaid project was projected to be completed by 20/01/2026 but due to road construction & pipeline construction of the area approach road has been damaged problems raised in the project the project is now bound to be delayed. The project till date is about 50.48% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 39 units in the project, we have sold 10 units. Out of which 08 have alre…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SAEE TOWN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAEE TOWN in Satara Parisar, Aurangabad is P51500035187.

Is SAEE TOWN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAEE TOWN is registered as P51500035187 and its status is "Registered and active".

What is the construction status of SAEE TOWN?

According to GharKundli's check of MahaRERA records (updated October 2026), SAEE TOWN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ROW HOUSE is 60% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does SAEE TOWN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SAEE TOWN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAEE TOWN is registered on MahaRERA as P51500035187, its completion date has moved 35 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAEE TOWN's possession date changes?

The latest dates are on SAEE TOWN's MahaRERA page (P51500035187). GharKundli's Kundli Watch sends a free WhatsApp update on SAEE TOWN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAEE TOWN have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAEE TOWN has one building filed: ROW HOUSE with 4 floors and 39 units.

How big is the land of SAEE TOWN?

According to GharKundli's check of MahaRERA records (updated October 2026), SAEE TOWN stands on 3,265 sq m of land (about 0.8 acres), with 4,217 sq m of sanctioned built-up area and 326 sq m of recreational open space.

Where can I read reviews of SAEE TOWN?

Google Maps has reviews of SAEE TOWN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAEE TOWN?

SAEE TOWN by RUDRA CONSTRUCTIONS is in Satara Parisar, Aurangabad (pincode 431010), near War, Deohara, Kaler, Maharashtra, and is registered on MahaRERA as P51500035187, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 METER VIDE ROAD.

How many homes are in SAEE TOWN?

According to GharKundli's check of MahaRERA records (updated October 2026), SAEE TOWN has 39 homes in 1 tower registered on MahaRERA, and 38% of them are sold or booked.

When was SAEE TOWN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAEE TOWN was registered on MahaRERA on 10 May 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SAEE TOWN?

No court cases are listed for SAEE TOWN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAEE TOWN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RUDRA CONSTRUCTIONS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2029 in Aurangabad →

Other projects in pincode 431010

All 24 projects in Satara Parisar (431010) →

Other projects by RUDRA CONSTRUCTIONS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.