RUSTOMJEE CROWN -PHASE II
by REAL GEM BUILDTECH PRIVATE LIMITED · Prabhadevi, MumbaiAlso near Lower Parel, Dadar West, Worli
Possession date of RUSTOMJEE CROWN -PHASE II: 29 October 2027, moved from 30 December 2023 (42 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900006367, and currently active. Its completion date has moved from December 2023 to October 2027: 42 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 31 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about RUSTOMJEE CROWN -PHASE II?
How the possession date of RUSTOMJEE CROWN -PHASE II has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51900011120)
Reason the builder gave MahaRERA:
“Due to the several difficulties encountered by our project contractors owing to the difficulties posed due to the covid - 19 pandemic situation including restrictions on travel , transport and delivery of material and goods, curfew related…” Read the full reason
“Due to the several difficulties encountered by our project contractors owing to the difficulties posed due to the covid - 19 pandemic situation including restrictions on travel , transport and delivery of material and goods, curfew related restrictions that impacted process of making and procuring the requisite approvals and sanctions from concerned authorities, the working hours of various industries and commute to work places , they may not be able to meet the previously estimated timelines for completing work of Facade, internal furnishing and lift installation, which is likely to affect…”29 December 2025
Extended at the builder's request (MahaRERA application EXT51900024309)
Reason the builder gave MahaRERA:
“(1) The Project comprises of Tower C consisting of Grd flr + 3 Basement + 65 floors. The further CC for the said Project has been issued on 6.06.2024 for upto top of 65th (pt.) floor. The issuance of further CC was dependent on handing over…” Read the full reason
“(1) The Project comprises of Tower C consisting of Grd flr + 3 Basement + 65 floors. The further CC for the said Project has been issued on 6.06.2024 for upto top of 65th (pt.) floor. The issuance of further CC was dependent on handing over of Public Parking Lot (PPL) to the MCGM. The work of PPL was delayed on account of pandemic and various other issues. The supply chains and logistics were adversely affected, as a result of which there was shortage of construction material, mass labour shortage, import shipment delays which impacted the projected timelines for construction. (2)Upon compl…”29 June 2026
Extended at the builder's request (MahaRERA application EA15122518679)
Reason the builder gave MahaRERA:
“The Promoter has completed the super structure of the said Real Estate Project which includes the external façade work and internal works in the said Real Estate Project are also nearing completion. However, due to certain circumstances and…” Read the full reason
“The Promoter has completed the super structure of the said Real Estate Project which includes the external façade work and internal works in the said Real Estate Project are also nearing completion. However, due to certain circumstances and events beyond the control of the Promoter, including the dynamic geopolitical tensions which have severely impacted the prices and the supply chain of the materials and goods needed for the construction and completion of the said Real Estate Project, the changes and amendments to various applicable statutory rules, regulations and governmental notificati…”29 June 2027
Extended at the builder's request (MahaRERA application EA12062621330)
Reason the builder gave MahaRERA:
“Based on the explanatory note, the following concise **Reason for Delay (within 2500 characters)** can be used in the MahaRERA Extension Application: The completion of the balance work of the project has been delayed due to circumstances be…” Read the full reason
“Based on the explanatory note, the following concise **Reason for Delay (within 2500 characters)** can be used in the MahaRERA Extension Application: The completion of the balance work of the project has been delayed due to circumstances beyond the reasonable control of the Promoter. Although substantial construction of the project has been completed and a Part Occupation Cum Building Completion Certificate dated 30th December 2025 has already been obtained for 322 residential units, certain balance works pertaining to the remaining 26 residential units are yet to be completed. The project,…”29 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: RUSTOMJEE CROWN -PHASE II’s extension records on MahaRERA (P51900006367), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RUSTOMJEE CROWN -PHASE II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 31 complaints and 5 court cases, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- RUSTOMJEE CROWN - PHASE IP51900003268 · possession 30 Dec 2024
- MahaRERA registration
- P51900006367
- Status
- Registered and active
- Builder
- REAL GEM BUILDTECH PRIVATE LIMITED
- Location
- Prabhadevi, Mumbai · 400025
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- October 2027
- Delay so far
- 42 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 348
- Sold or booked
- 80%
- Towers
- 1
- Complaints on MahaRERA
- 31
- Court cases listed
- 5
- Appeals at the tribunal
- 13
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of RUSTOMJEE CROWN -PHASE II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower C | 100% | 100% | 92.7% | 92.08% |
Commencement certificate (CC), as filed on MahaRERA
- Tower C: covers 69 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RUSTOMJEE CROWN -PHASE II every month.
RUSTOMJEE CROWN -PHASE II: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,335 – 1,586 | 251 |
| 4 BHK | 1,581 – 1,586 | 97 |
- Buildings: Tower C (69 floors, 348 units)
- Car parking: 1,148 covered
- Land: 8,833 sq m (about 2.2 acres) · sanctioned built-up 49,098 sq m · recreational space 2,208 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Realgem Buildtech has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 13 months); 1 still being built, 1 past the promised date (typically 18 months late). 101 complaints on MahaRERA across 2 projects.
Read Google reviews of RUSTOMJEE CROWN -PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RUSTOMJEE CROWN -PHASE II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RUSTOMJEE CROWN -PHASE II
What is the possession date of RUSTOMJEE CROWN -PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RUSTOMJEE CROWN -PHASE II in Prabhadevi, Mumbai is 29 October 2027 — 42 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for RUSTOMJEE CROWN -PHASE II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RUSTOMJEE CROWN -PHASE II's builder has filed on MahaRERA, the official one, is 29 October 2027, already 42 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RUSTOMJEE CROWN -PHASE II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE CROWN -PHASE II's builder applied to MahaRERA to extend the completion date 4 times: to 29 December 2024, giving the reason "Due to the several difficulties encountered by our project contractors owing to the difficulties posed due to the covid - 19 pandemic situation including restrictions on travel , transport and delivery of material and goods, curfew related restrictions that impacted process of making and procuring the requisite approvals and sanctions from concerned authorities, the working hours of various industries and commute to work places , they may not be able to meet the previously estimated timelines for completing work of Facade, internal furnishing and lift installation, which is likely to affect…"; to 29 December 2025, giving the reason "(1) The Project comprises of Tower C consisting of Grd flr + 3 Basement + 65 floors. The further CC for the said Project has been issued on 6.06.2024 for upto top of 65th (pt.) floor. The issuance of further CC was dependent on handing over of Public Parking Lot (PPL) to the MCGM. The work of PPL was delayed on account of pandemic and various other issues. The supply chains and logistics were adversely affected, as a result of which there was shortage of construction material, mass labour shortage, import shipment delays which impacted the projected timelines for construction. (2)Upon compl…"; to 29 June 2026, giving the reason "The Promoter has completed the super structure of the said Real Estate Project which includes the external façade work and internal works in the said Real Estate Project are also nearing completion. However, due to certain circumstances and events beyond the control of the Promoter, including the dynamic geopolitical tensions which have severely impacted the prices and the supply chain of the materials and goods needed for the construction and completion of the said Real Estate Project, the changes and amendments to various applicable statutory rules, regulations and governmental notificati…"; to 29 June 2027, giving the reason "Based on the explanatory note, the following concise **Reason for Delay (within 2500 characters)** can be used in the MahaRERA Extension Application: The completion of the balance work of the project has been delayed due to circumstances beyond the reasonable control of the Promoter. Although substantial construction of the project has been completed and a Part Occupation Cum Building Completion Certificate dated 30th December 2025 has already been obtained for 322 residential units, certain balance works pertaining to the remaining 26 residential units are yet to be completed. The project,…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of RUSTOMJEE CROWN -PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RUSTOMJEE CROWN -PHASE II in Prabhadevi, Mumbai is P51900006367.
Is RUSTOMJEE CROWN -PHASE II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE CROWN -PHASE II is registered as P51900006367 and its status is "Registered and active".
What is the construction status of RUSTOMJEE CROWN -PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE CROWN -PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Tower C is 100% done and internal work 92.7%. GharKundli's full report compares construction progress with the deadline.
Does RUSTOMJEE CROWN -PHASE II have complaints on MahaRERA?
31 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RUSTOMJEE CROWN -PHASE II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE CROWN -PHASE II is registered on MahaRERA as P51900006367, its completion date has moved 42 months since registration and 31 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does RUSTOMJEE CROWN -PHASE II have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: RUSTOMJEE CROWN - PHASE I (P51900003268, possession 30 Dec 2024). Check that your agreement names the registration of your own wing.
How can I get updates if RUSTOMJEE CROWN -PHASE II's possession date changes?
The latest dates are on RUSTOMJEE CROWN -PHASE II's MahaRERA page (P51900006367). GharKundli's Kundli Watch sends a free WhatsApp update on RUSTOMJEE CROWN -PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RUSTOMJEE CROWN -PHASE II have?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE CROWN -PHASE II has one building filed: Tower C with 69 floors and 348 units.
What are the flat sizes (carpet area) in RUSTOMJEE CROWN -PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for RUSTOMJEE CROWN -PHASE II: 3 BHK: 1335 to 1586 sq ft carpet (251 homes); 4 BHK: 1581 to 1586 sq ft carpet (97 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does RUSTOMJEE CROWN -PHASE II have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1,148 covered car parking spaces for RUSTOMJEE CROWN -PHASE II.
How big is the land of RUSTOMJEE CROWN -PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE CROWN -PHASE II stands on 8,833 sq m of land (about 2.2 acres), with 49,098 sq m of sanctioned built-up area and 2,208 sq m of recreational open space.
What is the track record of RUSTOMJEE CROWN -PHASE II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Realgem Buildtech has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 13 months); 1 still being built, 1 past the promised date (typically 18 months late). 101 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of RUSTOMJEE CROWN -PHASE II?
Google Maps has reviews of RUSTOMJEE CROWN -PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 31 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RUSTOMJEE CROWN -PHASE II?
RUSTOMJEE CROWN -PHASE II by REAL GEM BUILDTECH PRIVATE LIMITED is in Prabhadevi, Mumbai (pincode 400025), near Lower Parel, Dadar West, Worli, Maharashtra, and is registered on MahaRERA as P51900006367, per GharKundli's check of MahaRERA records.
How many homes are in RUSTOMJEE CROWN -PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE CROWN -PHASE II has 348 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.
When was RUSTOMJEE CROWN -PHASE II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE CROWN -PHASE II was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RUSTOMJEE CROWN -PHASE II?
5 court cases are listed for RUSTOMJEE CROWN -PHASE II on MahaRERA, and 13 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RUSTOMJEE CROWN -PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is REAL GEM BUILDTECH PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of RUSTOMJEE CROWN -PHASE II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in pincode 400025
- 1515 Moneco
- Kshitij Omkar
- Lotus Aquaria
- The V Mansion
- Vakratunda Crest
- Lodha Promina
- Lodha Worli Residential Project
- NAIA