SHRI VITTHALRESIDENCY
by SHRIPAD VINAYAK THOMBRE · Sinnar Phata, Nashik
Registered on MahaRERA under P51600014806, and currently active. Its completion date has moved from June 2019 to April 2028, 106 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on SHRI VITTHALRESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600014806
- Status
- Registered and active
- Builder
- SHRIPAD VINAYAK THOMBRE
- Location
- Sinnar Phata, Nashik · 422101
- Project type
- Residential / Group Housing
- Registered on
- 2 Jan 2018
- Completion date at registration
- June 2019
- Latest completion date
- April 2028
- Delay so far
- 106 months
- Homes
- 65
- Sold or booked
- 37%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Kundli Watch
SHRI VITTHALRESIDENCY: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about SHRI VITTHALRESIDENCY
Is SHRI VITTHALRESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHRI VITTHALRESIDENCY is registered as P51600014806 and its status is "Registered and active".
Where is SHRI VITTHALRESIDENCY?
SHRI VITTHALRESIDENCY by SHRIPAD VINAYAK THOMBRE is in Sinnar Phata, Nashik (pincode 422101), Maharashtra, and is registered on MahaRERA as P51600014806, per GharKundli's check of MahaRERA records.
When is possession of SHRI VITTHALRESIDENCY due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHRI VITTHALRESIDENCY in Sinnar Phata, Nashik is 30 April 2028 — 106 months later than 30 June 2019, the date given at registration.
Does SHRI VITTHALRESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of SHRI VITTHALRESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRIPAD VINAYAK THOMBRE.
Other projects in pincode 422101
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.