VARAD VINAYAK WING A

by SHIRISH CONSTRUCTIONS · Nashik Road, NashikAlso near Sukena, Ycm Open Univesity, B.S. Nagar

Possession date of VARAD VINAYAK WING A: 31 July 2027, moved from 30 June 2026 (9 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600080135, and currently active. Its completion date has moved from June 2026 to July 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VARAD VINAYAK WING A?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VARAD VINAYAK WING A has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA29062621607)

    Reason the builder gave MahaRERA:
    “Due to slow Booking and slack market we had to face shortage of funds therefore we were not able to complete the project within Specified time. We also had major setback, on schedule when RCC contractor couldn't provide enough manpower in s…” Read the full reason“Due to slow Booking and slack market we had to face shortage of funds therefore we were not able to complete the project within Specified time. We also had major setback, on schedule when RCC contractor couldn't provide enough manpower in slab castings, Undiscipline of work, wrong commitments, lack of working, quality etc. they has major setback in work progress overall delay in project some months.”
  3. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VARAD VINAYAK WING A’s extension records on MahaRERA (P51600080135), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VARAD VINAYAK WING A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600080135
Status
Registered and active
Builder
SHIRISH CONSTRUCTIONS
Location
Nashik Road, Nashik · 422101
Project type
Others
Registered on
30 Apr 2025
Completion date at registration
June 2026
Latest completion date
July 2027
Delay so far
9 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
30
Sold or booked
52%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of VARAD VINAYAK WING A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Varad Vinayak Wing A100%100%50%0%

Commencement certificate (CC), as filed on MahaRERA

  • Varad Vinayak Wing A: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VARAD VINAYAK WING A every month.

VARAD VINAYAK WING A: buildings, flats and land, as filed on MahaRERA

  • Buildings: Varad Vinayak Wing A (8 floors, 34 units)
  • Land: 562 sq m (about 0.1 acres) · sanctioned built-up 2,099 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of VARAD VINAYAK WING A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VARAD VINAYAK WING A: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VARAD VINAYAK WING A

What is the possession date of VARAD VINAYAK WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VARAD VINAYAK WING A in Nashik Road, Nashik is 31 July 2027 — 9 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VARAD VINAYAK WING A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VARAD VINAYAK WING A's builder has filed on MahaRERA, the official one, is 31 July 2027, already 9 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VARAD VINAYAK WING A extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VARAD VINAYAK WING A's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Due to slow Booking and slack market we had to face shortage of funds therefore we were not able to complete the project within Specified time. We also had major setback, on schedule when RCC contractor couldn't provide enough manpower in slab castings, Undiscipline of work, wrong commitments, lack of working, quality etc. they has major setback in work progress overall delay in project some months.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VARAD VINAYAK WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VARAD VINAYAK WING A in Nashik Road, Nashik is P51600080135.

Is VARAD VINAYAK WING A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VARAD VINAYAK WING A is registered as P51600080135 and its status is "Registered and active".

What is the construction status of VARAD VINAYAK WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), VARAD VINAYAK WING A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Varad Vinayak Wing A is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does VARAD VINAYAK WING A have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is VARAD VINAYAK WING A safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VARAD VINAYAK WING A is registered on MahaRERA as P51600080135, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VARAD VINAYAK WING A's possession date changes?

The latest dates are on VARAD VINAYAK WING A's MahaRERA page (P51600080135). GharKundli's Kundli Watch sends a free WhatsApp update on VARAD VINAYAK WING A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VARAD VINAYAK WING A have?

According to GharKundli's check of MahaRERA records (updated October 2026), VARAD VINAYAK WING A has one building filed: Varad Vinayak Wing A with 8 floors and 34 units.

How big is the land of VARAD VINAYAK WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), VARAD VINAYAK WING A stands on 562 sq m of land (about 0.1 acres), with 2,099 sq m of sanctioned built-up area.

Where can I read reviews of VARAD VINAYAK WING A?

Google Maps has reviews of VARAD VINAYAK WING A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VARAD VINAYAK WING A?

VARAD VINAYAK WING A by SHIRISH CONSTRUCTIONS is in Nashik Road, Nashik (pincode 422101), near Sukena, Ycm Open Univesity, B.S. Nagar, Maharashtra, and is registered on MahaRERA as P51600080135, per GharKundli's check of MahaRERA records.

How many homes are in VARAD VINAYAK WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), VARAD VINAYAK WING A has 30 homes in 1 tower registered on MahaRERA, and 52% of them are sold or booked.

When was VARAD VINAYAK WING A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VARAD VINAYAK WING A was registered on MahaRERA on 30 April 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on VARAD VINAYAK WING A?

No court cases are listed for VARAD VINAYAK WING A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of VARAD VINAYAK WING A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHIRISH CONSTRUCTIONS.

All projects with possession due in 2027 in Nashik →

Other projects in pincode 422101

All 178 projects in Nashik Road (422101) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.