SURYA SUNDER CO-OP HSG. SOC. LTD.
by NARAYAN INFRA · Deolali Shiwar, Nashik Road, NashikAlso near Opp Gopal Nagar, TP Station Eklahre
Possession date of SURYA SUNDER CO-OP HSG. SOC. LTD.: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1220002501365, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SURYA SUNDER CO-OP HSG. SOC. LTD.?
How the possession date of SURYA SUNDER CO-OP HSG. SOC. LTD. has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SURYA SUNDER CO-OP HSG. SOC. LTD.’s extension records on MahaRERA (PR1220002501365), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SURYA SUNDER CO-OP HSG. SOC. LTD.
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1220002501365
- Status
- Registered and active
- Builder
- NARAYAN INFRA
- Location
- Deolali Shiwar, Nashik Road, Nashik · 422101
- Project type
- Residential / Group Housing
- Registered on
- 31 Oct 2025
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 41
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SURYA SUNDER CO-OP HSG. SOC. LTD., as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SURYA SUNDER CO-OP. HSG. SOC. LTD. / A | 0% | 0% | 0% | 0% |
| SURYA SUNDER CO-OP. HSG. SOC. LTD. / B | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SURYA SUNDER CO-OP. HSG. SOC. LTD.: covers 7 floors
- SURYA SUNDER CO-OP. HSG. SOC. LTD.: covers 7 floors
Latest CC order on MahaRERA: dated 21/03/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SURYA SUNDER CO-OP HSG. SOC. LTD. every month.
SURYA SUNDER CO-OP HSG. SOC. LTD.: buildings, flats and land, as filed on MahaRERA
- Buildings: SURYA SUNDER CO-OP. HSG. SOC. LTD. (7 floors, 24 units) · SURYA SUNDER CO-OP. HSG. SOC. LTD. (7 floors, 17 units)
- Car parking: 18 covered
- Land: 867 sq m (about 0.2 acres) · sanctioned built-up 2,627 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Narayan Infra has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of SURYA SUNDER CO-OP HSG. SOC. LTD. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SURYA SUNDER CO-OP HSG. SOC. LTD.: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SURYA SUNDER CO-OP HSG. SOC. LTD.
What is the possession date of SURYA SUNDER CO-OP HSG. SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SURYA SUNDER CO-OP HSG. SOC. LTD. in Deolali Shiwar, Nashik Road, Nashik is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SURYA SUNDER CO-OP HSG. SOC. LTD.?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SURYA SUNDER CO-OP HSG. SOC. LTD.'s builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SURYA SUNDER CO-OP HSG. SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SURYA SUNDER CO-OP HSG. SOC. LTD. in Deolali Shiwar, Nashik Road, Nashik is PR1220002501365.
Is SURYA SUNDER CO-OP HSG. SOC. LTD. registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SURYA SUNDER CO-OP HSG. SOC. LTD. is registered as PR1220002501365 and its status is "Registered and active".
What is the construction status of SURYA SUNDER CO-OP HSG. SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), SURYA SUNDER CO-OP HSG. SOC. LTD.'s status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SURYA SUNDER CO-OP HSG. SOC. LTD. have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SURYA SUNDER CO-OP HSG. SOC. LTD. safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SURYA SUNDER CO-OP HSG. SOC. LTD. is registered on MahaRERA as PR1220002501365, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SURYA SUNDER CO-OP HSG. SOC. LTD.'s possession date changes?
The latest dates are on SURYA SUNDER CO-OP HSG. SOC. LTD.'s MahaRERA page (PR1220002501365). GharKundli's Kundli Watch sends a free WhatsApp update on SURYA SUNDER CO-OP HSG. SOC. LTD. every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SURYA SUNDER CO-OP HSG. SOC. LTD. have?
According to GharKundli's check of MahaRERA records (updated October 2026), SURYA SUNDER CO-OP HSG. SOC. LTD. has 2 buildings filed: SURYA SUNDER CO-OP. HSG. SOC. LTD. with 7 floors and 24 units; SURYA SUNDER CO-OP. HSG. SOC. LTD. with 7 floors and 17 units.
How much parking does SURYA SUNDER CO-OP HSG. SOC. LTD. have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 covered car parking spaces for SURYA SUNDER CO-OP HSG. SOC. LTD..
How big is the land of SURYA SUNDER CO-OP HSG. SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), SURYA SUNDER CO-OP HSG. SOC. LTD. stands on 867 sq m of land (about 0.2 acres), with 2,627 sq m of sanctioned built-up area.
What is the track record of SURYA SUNDER CO-OP HSG. SOC. LTD.'s builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Infra has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SURYA SUNDER CO-OP HSG. SOC. LTD.?
Google Maps has reviews of SURYA SUNDER CO-OP HSG. SOC. LTD. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SURYA SUNDER CO-OP HSG. SOC. LTD.?
SURYA SUNDER CO-OP HSG. SOC. LTD. by NARAYAN INFRA is in Deolali Shiwar, Nashik Road, Nashik (pincode 422101), near Opp Gopal Nagar, TP Station Eklahre, Maharashtra, and is registered on MahaRERA as PR1220002501365, per GharKundli's check of MahaRERA records.
How many homes are in SURYA SUNDER CO-OP HSG. SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), SURYA SUNDER CO-OP HSG. SOC. LTD. has 41 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.
When was SURYA SUNDER CO-OP HSG. SOC. LTD. registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SURYA SUNDER CO-OP HSG. SOC. LTD. was registered on MahaRERA on 31 October 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on SURYA SUNDER CO-OP HSG. SOC. LTD.?
No court cases are listed for SURYA SUNDER CO-OP HSG. SOC. LTD. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SURYA SUNDER CO-OP HSG. SOC. LTD.?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NARAYAN INFRA, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SURYA SUNDER CO-OP HSG. SOC. LTD.
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Nashik →
Other projects in pincode 422101
- ARRPAN HOUSING
- MATRUCHAYA
- NIWARA GANARAYA ROW HOUSE
- SHIV CRYSTAL
- VARAD VINAYAK WING A
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- Silk Route
- Ishwar Prem
Other projects by NARAYAN INFRA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.