by A C JAIN BUILDERS AND DEVELOPERS LLP · Vihitgaon, NashikAlso near Opp Gopal Nagar, TP Station Eklahre, Devlali Air Force
Possession date of ARRPAN HOUSING: 19 November 2026, moved from 17 April 2025 (19 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600022627, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ARRPAN HOUSING?
How the possession date of ARRPAN HOUSING has moved
17 April 2025
Completion date given when the project was registered
19 November 2026
Extended at the builder's request (MahaRERA application EA20082622285)
Reason the builder gave MahaRERA:
“The project has been completed, and the extension is being sought to facilitate necessary corrections and updates in the application. Upon completion of the required corrections, the application will be updated accordingly, following which…” Read the full reason
“The project has been completed, and the extension is being sought to facilitate necessary corrections and updates in the application. Upon completion of the required corrections, the application will be updated accordingly, following which the completion update will be submitted.”
Source: ARRPAN HOUSING’s extension records on MahaRERA (P51600022627), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ARRPAN HOUSING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600022627
- Status
- Registered and active
- Builder
- A C JAIN BUILDERS AND DEVELOPERS LLP
- Location
- Vihitgaon, Nashik · 422101
- Project type
- Others
- Registered on
- 9 Oct 2019
- Completion date at registration
- April 2025
- Latest completion date
- November 2026
- Delay so far
- 19 months
- Homes
- 392
- Sold or booked
- 67%
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of ARRPAN HOUSING, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ARRPAN HOUSING - B BUILDING - A, B AND C WING | 100% | 100% | 100% | 100% |
| ARRPAN HOUSING - A BUILDING - A,B AND C WINGS | 100% | 100% | 100% | 100% |
| ARRPAN HOUSING- D BUILDING- A,B AND C WING | 100% | 100% | 100% | 100% |
| ARRPAN HOUSING - C BUILDING - A, B AND C WING | 100% | 100% | 100% | 100% |
| ARRPAN HOUSING - E BUILDING - A AND B WING MHADA | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- ARRPAN HOUSING - B BUILDING - A, B AND C WING: covers 8 floors
- ARRPAN HOUSING - A BUILDING - A,B AND C WINGS: covers 8 floors
- ARRPAN HOUSING- D BUILDING- A,B AND C WING: covers 8 floors
- ARRPAN HOUSING - C BUILDING - A, B AND C WING: covers 8 floors
- ARRPAN HOUSING - E BUILDING - A AND B WING MHADA: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARRPAN HOUSING every month.
ARRPAN HOUSING: buildings, flats and land, as filed on MahaRERA
- Buildings: ARRPAN HOUSING - B BUILDING - A, B AND C WING (8 floors, 89 units) · ARRPAN HOUSING - A BUILDING - A,B AND C WINGS (8 floors, 102 units) · ARRPAN HOUSING- D BUILDING- A,B AND C WING (8 floors, 84 units) · ARRPAN HOUSING - C BUILDING - A, B AND C WING (8 floors, 84 units) · ARRPAN HOUSING - E BUILDING - A AND B WING MHADA (8 floors, 56 units)
- Land: 10,645 sq m (about 2.6 acres) · sanctioned built-up 18,054 sq m · recreational space 1,067 sq m
- Boundaries filed include: VIHITGAON VADNER ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
A C Jain Builders AND Developers has 8 projects on MahaRERA since 2019, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 26 months); 2 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of ARRPAN HOUSING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ARRPAN HOUSING: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ARRPAN HOUSING
What is the possession date of ARRPAN HOUSING?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARRPAN HOUSING in Vihitgaon, Nashik is 19 November 2026 — 19 months later than 17 April 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ARRPAN HOUSING?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ARRPAN HOUSING's builder has filed on MahaRERA, the official one, is 19 November 2026, already 19 months later than the 17 April 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ARRPAN HOUSING extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ARRPAN HOUSING's builder applied to MahaRERA to extend the completion date once: to 19 November 2026, giving the reason "The project has been completed, and the extension is being sought to facilitate necessary corrections and updates in the application. Upon completion of the required corrections, the application will be updated accordingly, following which the completion update will be submitted.".
What is the RERA number of ARRPAN HOUSING?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARRPAN HOUSING in Vihitgaon, Nashik is P51600022627.
Is ARRPAN HOUSING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARRPAN HOUSING is registered as P51600022627 and its status is "Registered and active".
What is the construction status of ARRPAN HOUSING?
According to GharKundli's check of MahaRERA records (updated October 2026), ARRPAN HOUSING's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does ARRPAN HOUSING have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ARRPAN HOUSING safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ARRPAN HOUSING is registered on MahaRERA as P51600022627, its completion date has moved 19 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ARRPAN HOUSING's possession date changes?
The latest dates are on ARRPAN HOUSING's MahaRERA page (P51600022627). GharKundli's Kundli Watch sends a free WhatsApp update on ARRPAN HOUSING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ARRPAN HOUSING have?
According to GharKundli's check of MahaRERA records (updated October 2026), ARRPAN HOUSING has 5 buildings filed: ARRPAN HOUSING - B BUILDING - A, B AND C WING with 8 floors and 89 units; ARRPAN HOUSING - A BUILDING - A,B AND C WINGS with 8 floors and 102 units; ARRPAN HOUSING- D BUILDING- A,B AND C WING with 8 floors and 84 units; ARRPAN HOUSING - C BUILDING - A, B AND C WING with 8 floors and 84 units; ARRPAN HOUSING - E BUILDING - A AND B WING MHADA with 8 floors and 56 units.
How big is the land of ARRPAN HOUSING?
According to GharKundli's check of MahaRERA records (updated October 2026), ARRPAN HOUSING stands on 10,645 sq m of land (about 2.6 acres), with 18,054 sq m of sanctioned built-up area and 1,067 sq m of recreational open space.
What is the track record of ARRPAN HOUSING's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), A C Jain Builders AND Developers has 8 projects on MahaRERA since 2019, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 26 months); 2 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ARRPAN HOUSING?
Google Maps has reviews of ARRPAN HOUSING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ARRPAN HOUSING?
ARRPAN HOUSING by A C JAIN BUILDERS AND DEVELOPERS LLP is in Vihitgaon, Nashik (pincode 422101), near Opp Gopal Nagar, TP Station Eklahre, Devlali Air Force, Maharashtra, and is registered on MahaRERA as P51600022627, per GharKundli's check of MahaRERA records. Its boundaries filed there include VIHITGAON VADNER ROAD.
How many homes are in ARRPAN HOUSING?
According to GharKundli's check of MahaRERA records (updated October 2026), ARRPAN HOUSING has 392 homes in 5 towers registered on MahaRERA, and 67% of them are sold or booked.
When was ARRPAN HOUSING registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARRPAN HOUSING was registered on MahaRERA on 9 October 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on ARRPAN HOUSING?
No court cases are listed for ARRPAN HOUSING on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ARRPAN HOUSING?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is A C JAIN BUILDERS AND DEVELOPERS LLP, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ARRPAN HOUSING
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- YUNUS RESIDENCY
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHREE VISHVA
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SARA SERENITY APARTMENT
Other projects by A C JAIN BUILDERS AND DEVELOPERS LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.